CDC Perth Maddington Campus: 200MW Sovereign AI Data Centre
Status: Under Construction / Active Phased Development | Location: 307 Kenwick Road, Maddington, WA 6109 (Greater Perth Area), Australia
Project Overview
CDC Data Centres’ Maddington Campus in Perth is set to become Western Australia’s largest AI and advanced technology data centre campus, delivering more than 200 MW of scalable, high-density IT capacity to meet the rapidly growing demand for artificial intelligence, cloud computing, and mission-critical digital infrastructure. Strategically located to strengthen Australia's sovereign digital capabilities, the campus is purpose-built to support AI supercomputing; government agencies; defence programs, including the AUKUS ecosystem; research institutions; and operators of critical national infrastructure. Designed for next-generation GPU-intensive workloads, the campus incorporates advanced liquid cooling technologies alongside CDC’s proprietary closed-loop waterless cooling system, significantly reducing water consumption while enabling efficient thermal management for high-density AI racks. The facility is engineered with resilient power infrastructure, multiple redundant electrical systems, and highly secure physical and cyber protection measures that meet the stringent requirements of government and defence customers. As a carrier-neutral campus, it provides diverse, low-latency connectivity to major telecommunications providers and cloud platforms, enabling seamless hybrid cloud and edge computing deployments. Sustainability is central to the development, with energy-efficient infrastructure, intelligent building management systems, and a design focused on reducing operational environmental impact while maintaining maximum performance and availability. With substantial room for future expansion, the Maddington Campus will serve as a cornerstone of Australia's AI and digital infrastructure strategy, providing secure, scalable, and future-ready capacity to support the nation's technological innovation, sovereign computing capabilities, and long-term economic growth.
Quick Facts
| Field | Value |
| Project Name | CDC Perth Maddington Campus: 200MW Sovereign AI Data Centre |
| Location | 307 Kenwick Road, Maddington, WA 6109 (Greater Perth Area), Australia |
| Status | Under Construction / Active Phased Development |
| Commissioning | Phase 1 Operational: 2026 / Full Campus Buildout: 2026–2028+ |
| Total IT Load | 200 MW+ Critical IT Load (upon full completion) |
| Total Capacity | 200 MW+ High-Density Capacity across multi-building campus (DC1–DC4) |
| Tier Level | Tier III / Tier IV Equivalent Sovereign Security Architecture (Zone 3–5 Defense Standards Aligned) |
| Project Type | Sovereign AI & Advanced Technology Hyperscale Campus |
City Profile
| Header | Details |
| City Name | Perth |
| Population | ~2.4 million |
| Urban Agglomeration | ~2.4 million (Greater Perth) |
| City GDP | ~AUD 220 billion (≈ USD 145 billion) |
| Per Capita Income | ~AUD 90,000 |
| City Tier | Tier 1 – Global Mining, Energy & Technology Hub |
| Key Strengths | Capital of Western Australia; strong mining and energy sector; growing technology and digital infrastructure market; excellent international connectivity; business-friendly environment; highly skilled workforce; abundant renewable energy potential; expanding hyperscale and colocation data center market; strategic gateway to Asia-Pacific; high quality of life. |
Companies Involved
| Header | Details |
| Developer / Operator | CDC Data Centres |
| Strategic Infrastructure Partner | Western Power (Grid Authority), Government of Western Australia, & Australian Federal Sovereign Defense Partners |
| Construction Contractor | Tier 1 Australian Mission-Critical EPC & General Contractors |
| MEP Engineering | CDC In-House Engineering & Technical Design Teams |
| Network Connectivity | Sovereign carrier-neutral network environment featuring multi-path direct fiber routes, dual secure Meet-Me-Rooms (MMRs), and high-speed regional connections to subsea cable landings in Perth. |
| Power Infrastructure | High-voltage dual grid connections via Western Power transmission, block-redundant (2N) static UPS infrastructure, and standby diesel/biodiesel generators with multi-day fuel storage. |
Technical Specifications
| Header | Details |
| Power Capacity | 200 MW+ Total Campus Utility Capacity |
| UPS Redundancy | 2N / Block-Redundant Uninterruptible Power Supply (UPS) Topology |
| Cooling System | Closed-loop chilled water cooling system featuring zero primary water consumption and direct-to-chip liquid cooling capability for ultra-high-density AI compute racks. |
| Connectivity | Carrier-neutral access with direct enterprise/government cloud interconnects and low-latency national fiber rings. |
| PUE Target | < 1.25 Annualized Design PUE |
| Energy Mix | High-efficiency supply backed by regional Western Australia renewable energy power purchase agreements (PPAs). |
Milestones
| Header | Details |
| Announcement | August 2025 |
| Construction Start | Late 2025 |
| Phase 1 Go-Live | 2026 |
| Full Buildout | 2028–2029+ |
Investment Details
| Header | Details |
| Total Investment | ~AU$415,000,000 (Initial Phase 1 Investment) / Total Campus Capital Expenditure exceeding AU$1.5B+ |
| Funding | Corporate Capital Expenditure by CDC Data Centres (backed by Infratil and Commonwealth Superannuation Corporation) |