Lighthouse Campus (part of OpenAI/Oracle Stargate)

Status: Under Construction (Groundbreaking: Dec 17, 2025)   |   Location: Port Washington, Ozaukee County, Wisconsin, USA


Project Overview

The Lighthouse Campus represents the single largest private investment in Wisconsin’s history and a pivotal milestone for the global Stargate Project. Launched as a joint venture between Vantage Data Centers, Oracle, and OpenAI, this facility is purposefully built to support the massive computational requirements of Artificial General Intelligence (AGI) research.

Covering 672 acres on the north side of Port Washington, the campus features four single-story buildings totaling 2.5 million square feet. Unlike traditional data centers, Lighthouse is optimized for high-density AI workloads using closed-loop liquid cooling, which allows for a near-zero Water Utilization Effectiveness (WUE). This technology is essential for cooling the thousands of power-hungry GPUs expected to be housed within the facility.

The project is as much an energy infrastructure play as it is a computing one. Vantage has partnered with WEC Energy Group to bring nearly 2 GW of new energy to the local grid, with the campus itself drawing up to 1.3 GW. To balance this footprint, 70% of the campus's energy will come directly from new zero-emission resources (wind, solar, and battery storage), with the remaining 30% matched through renewable energy purchases.

Economically, the Lighthouse project is a "once-in-a-generation" catalyst for the region. It is expected to create 4,000 union construction jobs at its peak and over 1,000 permanent roles upon completion. Beyond the technical specs, the developer is investing $175 million in local infrastructure upgrades, including wastewater treatment and road improvements, ensuring that the local community benefits directly from the presence of this global AI hub.


Quick Facts

FieldValue
Project NameLighthouse Campus (part of OpenAI/Oracle Stargate)
LocationPort Washington, Ozaukee County, Wisconsin, USA
StatusUnder Construction (Groundbreaking: Dec 17, 2025)
CommissioningPhase 1: Late 2026; Full Buildout: 2028
Total IT Load~902 MW (Scaling to 1.3 GW site capacity)
Total Capacity2.5 Million Sq. Ft. (4 Data Center Buildings)
Tier LevelTier III+ (High-Density AI Design)
Project TypeGreenfield Hyperscale AI Campus

City Profile

HeaderDetails
City NamePort Washington, WI
Population~12,500 (Small town with global scale infrastructure)
Urban AgglomerationMilwaukee-Waukesha-West Allis Metro Area
City GDPEstimated $2.7 Billion contribution to regional GDP
Per Capita Income~$67k
City TierTier 3 (Emerging High-Tech/AI Hub)
Key StrengthsNear-zero water waste cooling, stable grid, union labor.

Companies Involved

HeaderDetails
Developer / Operator Vantage Data Centers
Strategic Infrastructure Partner Oracle & OpenAI (Primary Tenants/End-Users)
Construction Contractor Whiting-Turner, Weitz, Turner-McCarthy JV, Michels
MEP Engineering Specialized High-Density Engineering (Liquid-to-Liquid)
Network Connectivity Multiple diverse fiber paths (Dark and Lit fiber access)
Power Infrastructure WEC Energy Group (We Energies)

Technical Specifications

HeaderDetails
Power Capacity1.3 GW peak (dedicated high-voltage substation)
UPS RedundancyN+1 across all electrical systems
Cooling System Closed-loop liquid cooling / Zero-water use design
Connectivity Minimum 2 points-of-entry (POE) per building
PUE Target < 1.2 (Designed for 100% uptime and efficiency)
Energy Mix 70% Zero-Emission (Solar/Wind/Battery); 30% matched.

Milestones

HeaderDetails
Announcement January 21, 2025 (Initial Stargate Reveal)
Construction Start December 17, 2025 (Official Ceremony)
Phase 1 Go-Live Q4 2026
Full Buildout 2028

Investment Details

HeaderDetails
Total Investment$15 Billion USD
Funding DigitalBridge Group, Inc. and Silver Lake