Meta Kansas City: $1B AI-Optimized Data Center Missouri
Status: Operational / Serving Traffic (March 2026) | Location: golden plains technology park ,kansas city
Project Overview
Formally brought online in August 2025, Meta’s Kansas City campus represents a significant evolution in hyperscale infrastructure, purpose-built to meet the rapidly intensifying demands of artificial intelligence workloads. Located in Kansas City within the expansive 5.5-million-square-foot Golden Plains Technology Park, the $1 billion facility serves as a foundational pillar for Meta’s growing AI ecosystem, supporting applications such as Meta AI, Ray-Ban Meta smart glasses, and the Quest virtual reality platform. Unlike traditional data centers, the campus is engineered with AI-first architecture, prioritizing high-density compute, ultra-low latency networking, and advanced thermal management systems required for next-generation machine learning models.
A defining feature of the facility is its adoption of cutting-edge liquid-to-chip cooling technologies, which enable efficient heat dissipation directly at the processor level. This approach significantly enhances energy efficiency while supporting the extreme power densities associated with custom AI accelerators. In parallel, the campus demonstrates a strong commitment to sustainability and resource optimization. During construction, the project conserved over 1 million gallons of potable water by leveraging onsite retention ponds for dust suppression and site operations, setting an early benchmark for water stewardship in large-scale infrastructure development.
Beyond its technical and environmental innovations, the Kansas City campus also plays a meaningful role in local economic and community development. At peak construction, the project generated approximately 1,500 jobs, transitioning to around 100 permanent operational roles post-completion. In March 2026, Meta further reinforced its community engagement by announcing 13 local grants, including support for the Make48 initiative, which focuses on equipping middle school students with AI and STEAM skills. This integration of advanced infrastructure with community investment highlights the campus not only as a technological asset but also as a catalyst for regional growth and digital skill development.
Quick Facts
| Field | Value |
| Project Name | Meta Kansas City: $1B AI-Optimized Data Center Missouri |
| Location | golden plains technology park ,kansas city |
| Status | Operational / Serving Traffic (March 2026) |
| Commissioning | Phase 1 Live: August 2025; Expansion Active: 2026 |
| Total IT Load | ~200 MW (Initial phase) |
| Total Capacity | 1.0 Million Sq. Ft. (Initial); 5.5 Million Sq. Ft. (Campus Total) |
| Tier Level | Tier IV (AI-Native Design) |
| Project Type | Next-Gen AI Training & Social Media Infrastructure |
City Profile
| Header | Details |
| City Name | Kansas |
| Population | ~197,000 (Kansas City, Kansas) |
| Urban Agglomeration | ~2.2 million (Kansas City Metropolitan Area) |
| City GDP | ~$150–170 billion (Kansas City Metro) |
| Per Capita Income | ~$55,000 |
| City Tier | Tier 2 (Emerging U.S. Tech & Logistics Hub) |
| Key Strengths | Central U.S. location, strong logistics and transportation network, growing data center market, affordable land and power, skilled workforce |
Companies Involved
| Header | Details |
| Developer / Operator | Meta Platforms, Inc. |
| Strategic Infrastructure Partner | Evergy (Renewable Energy matching). |
| Construction Contractor | Turner Construction Company. |
| MEP Engineering | Meta Global Infrastructure Design. |
| Network Connectivity | Dedicated high-bandwidth backbone for real-time AI inference. |
| Power Infrastructure | 100% renewable energy matching via Evergy partnership. |
Technical Specifications
| Header | Details |
| Power Capacity | ~200 MW (Phase 1) |
| UPS Redundancy | $2N$ configuration with high-efficiency battery backup. |
| Cooling System | AI-optimized water-efficient cooling (LEED Gold). |
| Connectivity | Global node for Facebook, Instagram, and Meta AI. |
| PUE Target | < 1.10 |
| Energy Mix | 100% Wind/Solar matching via Evergy’s regional portfolio. |
Milestones
| Header | Details |
| Announcement | March 2022 |
| Construction Start | 2022 |
| Phase 1 Go-Live | August 20, 2025 |
| Full Buildout | 2028 (Ongoing expansion) |
Investment Details
| Header | Details |
| Total Investment | Total Investment: $1.0 Billion |
| Funding | Meta Platforms Inc. Capital Expenditures. |