NEXTDC P2 Perth Data Center Campus: 20MW Tier IV Certified Gateway

Status: Operational   |   Location: 11 Newcastle Street, Perth, WA 6000, Australia


Project Overview

NEXTDC’s P2 Perth (PER2) Data Center is a flagship Tier IV fault-tolerant hyperscale digital infrastructure facility located in the Perth CBD, Western Australia. Designed as a critical connectivity and computing hub for the region, P2 delivers more than 20 MW of scalable IT capacity across approximately 12,000 m² of technical space and supports up to 6,300 racks for enterprise, government, cloud, and hyperscale workloads. The facility serves as a strategic interconnection gateway for Western Australia, providing direct access to major subsea cable networks that connect Australia with key global markets across Asia, Africa, and the Middle East. Built to support mission-critical applications, P2 incorporates highly resilient power systems, advanced cooling infrastructure, and redundant network pathways to ensure continuous availability and operational reliability. The data center meets stringent ASIO T4 security requirements and Australian Government sovereign hosting standards, making it suitable for highly sensitive workloads across public sector, defense, finance, and regulated industries. P2 also provides direct cloud connectivity through dedicated on-ramps to leading platforms including AWS and Microsoft Azure, enabling customers to deploy hybrid cloud and digital transformation solutions with ultra-low latency performance. With its premium location, carrier-neutral ecosystem, and enterprise-grade resilience, NEXTDC P2 Perth plays a vital role in strengthening Australia’s digital infrastructure landscape and supporting the growing demand for secure, high-performance computing capacity.


Quick Facts

FieldValue
Project NameNEXTDC P2 Perth Data Center Campus: 20MW Tier IV Certified Gateway
Location11 Newcastle Street, Perth, WA 6000, Australia
StatusOperational
CommissioningJuly 2020
Total IT Load20 MW+ Critical IT Load
Total Capacity20 MW+ Critical IT Power across 12,000 m² of technical whitespace (~6,300 racks)
Tier LevelUptime Institute Tier IV Certified Design, Constructed Facility, and Gold Operational Sustainability (ISO 27001, ISO 14001, SOC 1/2, PCI-DSS Certified)
Project TypePurpose-Built Hyperscale, Sovereign Cloud Gateway & Subsea Cable Landing Hub

City Profile

HeaderDetails
City NamePerth
Population~2.4 million
Urban Agglomeration~2.4 million (Greater Perth)
City GDP~AUD 220 billion (≈ USD 145 billion)
Per Capita Income~AUD 90,000
City TierTier 1 – Global Mining, Energy & Technology Hub
Key StrengthsCapital of Western Australia; strong mining and energy sector; growing technology and digital infrastructure market; excellent international connectivity; business-friendly environment; highly skilled workforce; abundant renewable energy potential; expanding hyperscale and colocation data center market; strategic gateway to Asia-Pacific; high quality of life.

Companies Involved

HeaderDetails
Developer / Operator NEXTDC
Strategic Infrastructure Partner Western Power (Electricity Utility), City of Perth & Australian Federal Government Hosting Framework
Construction Contractor Multiplex Construction & Tier 1 Australian Mission-Critical Contractors
MEP Engineering NEXTDC In-House Technical Design & Infrastructure Engineering Teams
Network Connectivity Carrier-neutral platform with direct optical fiber interconnectivity to major subsea cable landing stations (Indigo, Oman Australia Cable, ASC); dual Meet-Me-Rooms (MMRs); direct access to AWS Direct Connect, Microsoft ExpressRoute, and Megaport.
Power Infrastructure Isolated Parallel Bus topology supporting N+N distribution to the rack, 1.5 MW Piller rotary UPS units supported by Penske diesel engines, and 24+ hours of on-site fuel reserves per engine.

Technical Specifications

HeaderDetails
Power Capacity20 MW+ Critical IT Load
UPS RedundancyN+N / Fault-Tolerant Isolated Parallel Rotary UPS Architecture
Cooling System Stulz indirect free cooling CRAC units paired with modular cooling tower infrastructure, N+2 CRAC units per data hall, cold flooded room with hot aisle containment, 24-hour peak water storage, and direct liquid-cooling readiness.
Connectivity Carrier-neutral access with direct connectivity to 50+ network providers and local internet exchanges (IX Australia / WA-IX).
PUE Target 1.29 Annualized Operational Design PUE
Energy Mix 100% renewable power option backed by NEXTDC’s corporate ESG strategy and ISO 14001 certification.

Milestones

HeaderDetails
Announcement 2018
Construction Start 2019
Phase 1 Go-Live July 2020
Full Buildout Operational

Investment Details

HeaderDetails
Total InvestmentAU$200,000,000 to AU$300,000,000
Funding Corporate Capital Expenditure by NEXTDC Limited