Nostrum Evergreen Badajoz: €1.9B 500MW AI Data Center Spain
Status: Permitting / Pre-Construction (March 2026) | Location: Badajoz
Project Overview
Nostrum Evergreen stands as a flagship hyperscale initiative positioned to meet accelerating AI and cloud demand across Europe, with a total investment of €1.9 billion ($2.2 billion). Developed by Nostrum Group, the project is located in Badajoz within the energy-rich region of Extremadura. As of March 13, 2026, the company has formally submitted the Major Works Permit for Phase 1, which is designed to deliver 170 MW of IT capacity, with “Ready-to-Build” status anticipated by September 2026 placing it on a fast-track development timeline relative to other European data center markets.
A critical differentiator for Nostrum Evergreen is its early-stage power procurement strategy. The project has already secured 300 MW of guaranteed grid capacity ahead of Spain’s national Spanish Electrical Grid Development Plan (2025–2030), effectively insulating it from the widespread grid congestion that is delaying deployments in core hubs such as Madrid. This proactive approach to power access significantly enhances certainty around delivery timelines and positions the campus as a near-term capacity solution for hyperscalers facing constraints elsewhere in Europe.
From a technical standpoint, the campus is engineered for ultra-high efficiency and sustainability. It targets a Power Usage Effectiveness (PUE) of 1.1, placing it among the most efficient large-scale facilities globally, and incorporates a zero-water cooling architecture. This design is particularly critical in Extremadura, where water scarcity is an ongoing structural challenge, and aligns with broader industry shifts toward minimizing resource intensity while supporting increasingly dense AI workloads.
Quick Facts
| Field | Value |
| Project Name | Nostrum Evergreen Badajoz: €1.9B 500MW AI Data Center Spain |
| Location | Badajoz |
| Status | Permitting / Pre-Construction (March 2026) |
| Commissioning | Phase 1 (170MW): Q4 2027; Full 500MW: 2029+ |
| Total IT Load | 500 MW (Scalable up to 1 GW) |
| Total Capacity | Equivalent to Spain's entire 2024 operational capacity |
| Tier Level | Tier IV (High-Density AI Architecture) |
| Project Type | AI Gigafactory & Next-Gen Hyperscale Campus |
City Profile
| Header | Details |
| City Name | Badajoz |
| Population | ~150,000 |
| Urban Agglomeration | ~200,000 |
| City GDP | ~$4–5 billion (est.) |
| Per Capita Income | ~$22,000–$26,000 (est.) |
| City Tier | Tier 3 (Regional Economic Hub) |
| Key Strengths | Strategic border location with Portugal, renewable energy surplus (solar & wind), logistics and trade gateway, emerging data center potential, low land & power costs |
Companies Involved
| Header | Details |
| Developer / Operator | Nostrum Data Centers |
| Strategic Infrastructure Partner | City Council of Badajoz / JLL (Advisory & Leasing). |
| Construction Contractor | AECOM (Program Management) / Local civil partners. |
| MEP Engineering | AECOM Global Engineering Team. |
| Network Connectivity | Integrated into the Iberian digital backbone; proximity to subsea routes. |
| Power Infrastructure | 300MW secured; infrastructure designed for 1GW peak load. |
Technical Specifications
| Header | Details |
| Power Capacity | 500 MW |
| UPS Redundancy | High-resiliency $2N$ architecture with modular backup. |
| Cooling System | Advanced Waterless Cooling (Refrigerant-based, 0% water consumption). |
| Connectivity | Core European node for high-performance GPU-driven AI training. |
| PUE Target | < 1.10 |
| Energy Mix | 100% Renewable energy sourcing (Regional Solar/Wind integration). |
Milestones
| Header | Details |
| Announcement | December 2, 2025 (Official AECOM Partnership) |
| Construction Start | Expected Q4 2026 |
| Phase 1 Go-Live | Q4 2027 |
| Full Buildout | 2029 (for 500MW) |
Investment Details
| Header | Details |
| Total Investment | €1.9 Billion (Initial Phasing) |
| Funding | Nostrum Group Equity + Project Finance (BBVA). |