NTT Chicago: $10B Global Expansion CH3 Data Center Itasca

Status: Under Construction (Completion Scheduled for 2026)   |   Location: Arlington Heights Road, Itasca


Project Overview

On March 3, 2026, NTT DATA announced it had secured nearly 115 MW in new capacity commitments across its North American portfolio, with the Chicago Itasca campus serving as a primary beneficiary. The CH3 facility, currently under construction and slated for completion later in 2026, is part of a multi-phase development on a 35-acre site. This expansion is a key component of NTT's massive $10 billion global investment plan (running through 2027) aimed at delivering infrastructure capable of supporting dense AI workloads. The Itasca campus is designed for high-availability and extreme scalability, featuring a dedicated on-site electric substation to bypass local grid congestion. CH3 follows the successful launch of CH1 (2019) and CH2 (2023), further solidifying the Chicago market as a critical hub for financial services, gaming, and cloud providers. The facility is engineered to support the latest Smart AI Agent™ Ecosystem and high-density liquid cooling requirements for generative AI training and inference.


Quick Facts

FieldValue
Project NameNTT Chicago: $10B Global Expansion CH3 Data Center Itasca
LocationArlington Heights Road, Itasca
StatusUnder Construction (Completion Scheduled for 2026)
CommissioningPhased: CH3 Completion H2 2026
Total IT Load126 MW (Total Campus Potential)
Total Capacity4 Data Center Buildings (Fully Built Out)
Tier LevelTier III+ (Enterprise & Hyperscale)
Project TypeHyperscale & High-Density Colocation

City Profile

HeaderDetails
City NameItasca
Population~9,500 (2024 estimate)
Urban Agglomeration~9.5 million (part of the Chicago–Naperville–Elgin metropolitan area)
City GDP~USD 1.0–1.2 Billion (estimated based on local income levels and economic activity)
Per Capita Income~USD 62,700
City TierSmall City / Chicago Metropolitan Suburb (Tier 3)
Key StrengthsProximity to Chicago, strong corporate parks, logistics and transportation access, high household income, business-friendly suburban environment

Companies Involved

HeaderDetails
Developer / Operator NTT Global Data Centers
Strategic Infrastructure Partner Village of Itasca / DuPage County Economic Development.
Construction Contractor Clune Construction / JE Dunn (Preferred Regional Partners).
MEP Engineering Syska Hennessy / KW Mission Critical Engineering.
Network Connectivity Direct low-latency mesh to 350 Cermak and local fiber rings.
Power Infrastructure Dedicated 110kV On-site Substation; 100% renewable energy options.

Technical Specifications

HeaderDetails
Power Capacity126 MW Total Planned Campus Load
UPS Redundancy$N+1$ or $2N+2$ Distributed Redundant
Cooling System Air-cooled chillers with integrated water-side economization.
Connectivity Carrier-neutral; diverse fiber points-of-entry (POEs).
PUE Target 1.25
Energy Mix Matched 100% with renewable energy via NTT's Green Power program.

Milestones

HeaderDetails
Announcement March 3, 2026 (Capacity Expansion Update)
Construction Start Active (CH3 Build)
Phase 1 Go-Live 2019 (CH1)
Full Buildout 2027

Investment Details

HeaderDetails
Total Investment~$1.2 Billion (Campus Total)
Funding NTT DATA Group Corporate Finance.