PDG Greater Jakarta JC3: $1B 120MW Green AI Campus
Status: Active / Under Heavy Structural Construction (Tracking June 2026) | Location: Greenland International Industrial Center (GIIC), Deltamas, Bekasi Regency, Greater Jakarta, Indonesia
Project Overview
The Princeton Digital Group JC3 Data Center Campus is a monumental $1 billion USD digital infrastructure asset under active deployment in the Greenland International Industrial Center (GIIC) in Bekasi Regency, Greater Jakarta. Built as a primary cornerstone for Indonesia's accelerating cloud and artificial intelligence ecosystem, JC3 is engineered specifically to absorb the extreme power envelopes and high-density thermal challenges generated by next-generation machine learning clusters. Advancing rapidly through structural framing and high-voltage electrical grid line setups in mid-2026, the campus expands PDG's extensive regional footprint to anchor a total planned Indonesian portfolio of 400 MW. Strategically situated in a premium industrial corridor outside Jakarta's dense urban core to avoid line bottlenecks, JC3 features advanced hybrid architecture designed for speed and modular scalability. The facility provides international hyperscalers with immense processing space paired with ultra-low latency dark fiber cross-connects directly to the capital’s central internet exchanges.
Quick Facts
| Field | Value |
| Project Name | PDG Greater Jakarta JC3: $1B 120MW Green AI Campus |
| Location | Greenland International Industrial Center (GIIC), Deltamas, Bekasi Regency, Greater Jakarta, Indonesia |
| Status | Active / Under Heavy Structural Construction (Tracking June 2026) |
| Commissioning | Phase 1 initial data hall ready-for-service target set for Q4 2026 |
| Total IT Load | ~96.0 MW net critical operational compute capacity across full buildout |
| Total Capacity | 120.0 Megawatts (120 MW) gross ultimate utility power envelope |
| Tier Level | Tier III Compliant (Concurrently maintainable infrastructure) |
| Project Type | Greenfield Hyperscale, Eco-Sustainable AI-Ready & Cloud Hub |
City Profile
| Header | Details |
| City Name | Jakarta |
| Population | over 42 million |
| Urban Agglomeration | 42 million |
| City GDP | $420.192 |
| Per Capita Income | $9,789 |
| City Tier | Tier 1: Mega-City |
| Key Strengths | Largest digital market in Southeast Asia, high cloud demand, government support. |
Companies Involved
| Header | Details |
| Developer / Operator | Princeton Digital Group |
| Strategic Infrastructure Partner | PT Puradelta Lestari Tbk (Deltamas Industrial Estate Management) |
| Construction Contractor | Premier Pan-Asian Technical Civil & Structural Engineering Contractors |
| MEP Engineering | PDG Global Data Center Design & Critical Infrastructure Engineering Division |
| Network Connectivity | Carrier-neutral platform deploying multiple physically isolated, concrete-hardened network entry points with diverse routing to Jakarta's core switching fabric |
| Power Infrastructure | PT Perusahaan Listrik Negara (PLN) Transmission Grid (Dedicated high-voltage on-site utility substation) |
Technical Specifications
| Header | Details |
| Power Capacity | 120 MW gross utility line allocation engineered to support high-density configurations utilizing advanced AI accelerator architectures |
| UPS Redundancy | $N+1$ block-redundant static solid-state UPS topologies integrated with highly efficient, low-maintenance lithium-ion energy storage systems |
| Cooling System | Next-generation hybrid design deploying direct-to-chip liquid cooling alongside highly flexible, waterless adiabatic air conditioning blocks |
| Connectivity | 4 physically isolated, concrete-hardened subterranean network vaults ensuring absolute fiber path and multi-carrier route diversity |
| PUE Target | $\le 1.20$ design-optimized annualized operating profile exceeding local environmental performance guidelines |
| Energy Mix | 100% matched with clean, renewable energy sources and targeting comprehensive LEED certification under PDG's Net Zero 2030 framework |
Milestones
| Header | Details |
| Announcement | Finalized site master acquisition, environmental planning, and 120MW power allocation frameworks approved |
| Construction Start | Ground officially broken with major civil foundation work and structural piling initialized Q4 2025 |
| Phase 1 Go-Live | Projected Q4 2026 |
| Full Buildout | 2029 - Q2 |
Investment Details
| Header | Details |
| Total Investment | $1.0 Billion USD total projected capital allocation for master campus construction and mechanical fit-out |
| Funding | Direct corporate equity and a newly closed $856 Million USD green syndicated loan facility provided by DBS, HSBC, Maybank, SMBC, and Standard Chartered |