Colt DCS Osaka AI Cloud Campus: 130MW Hyperscale Data Center
Status: Operational & Active Phased Expansion | Location: 2-chōme-3-3 Honjōhigashi, Kita Ward, Osaka, 531-0074, Japan
Project Overview
Colt Data Centre Services’ Osaka AI Cloud Campus is a major hyperscale digital infrastructure hub serving the Kansai region, Japan’s second-largest data center market and a critical gateway for cloud and enterprise connectivity across Asia-Pacific. Comprising the operational 45 MW Keihanna facility together with the planned 130 MW Minoh expansion developed through a joint venture with ESR, the campus is designed to deliver approximately 175 MW of scalable critical IT capacity for global hyperscale cloud providers, over-the-top (OTT) content platforms, financial institutions, telecommunications operators, and enterprises deploying artificial intelligence (AI), machine learning (ML), and high-performance computing (HPC) workloads. Purpose-built for next-generation computing environments, the campus incorporates advanced closed-loop cooling systems, high floor loading, and flexible electrical infrastructure capable of supporting high-density GPU deployments and liquid-cooling-ready AI clusters. Operating entirely on 100% certified renewable electricity, the campus aligns with customers’ sustainability objectives while maintaining exceptional operational resilience and energy efficiency. Built with highly redundant power and cooling infrastructure, it ensures continuous availability for mission-critical digital operations. As a carrier-neutral campus, it provides direct connectivity to Osaka’s major carrier exchanges, cloud availability zones, and transpacific subsea cable landing stations, enabling low-latency access to domestic and international digital ecosystems. Supported by advanced physical security, continuous infrastructure monitoring, and scalable expansion capabilities, the Osaka AI Cloud Campus serves as a future-ready platform for cloud growth, AI innovation, and sustainable digital transformation across Japan and the wider Asia-Pacific region.
Quick Facts
| Field | Value |
| Project Name | Colt DCS Osaka AI Cloud Campus: 130MW Hyperscale Data Center |
| Location | 2-chōme-3-3 Honjōhigashi, Kita Ward, Osaka, 531-0074, Japan |
| Status | Operational & Active Phased Expansion |
| Commissioning | Phase 1 Go-Live: 2023 / Multi-Phase Expansion through 2027–2029 |
| Total IT Load | 130 MW Critical IT Power Capacity Allocation (45 MW Keihanna + 130 MW Minoh Campus) |
| Total Capacity | 130 MW Total IT Power Capacity across a gross floor footprint exceeding 140,000 m² |
| Tier Level | Tier III Certified Design Architecture / ISO 27001, ISO 14001, ISO 22301, SOC 2 Type II |
| Project Type | Purpose-Built Greenfield Hyperscale, High-Density AI-Ready Colocation & Cloud Hub |
City Profile
| Header | Details |
| City Name | Osaka |
| Population | ~2.7 Million (Osaka City) |
| Urban Agglomeration | ~19.3 Million (Kansai Metropolitan Area) |
| City GDP | Significant regional economic engine of Japan |
| Per Capita Income | High |
| City Tier | Tier 1/Emerging Hyperscale Hub (Complementary to Tokyo) |
| Key Strengths | Second-largest metropolitan economy, robust infrastructure, growing hyperscale cloud region status, lower seismic risk than parts of Tokyo. |
Companies Involved
| Header | Details |
| Developer / Operator | Colt Data Centre Services |
| Strategic Infrastructure Partner | Kansai Electric Power Company (KEPCO) |
| Construction Contractor | Specialized Japanese Mission-Critical General Contractors (Kajima / Obayashi) |
| MEP Engineering | Colt DCS In-House Global Technical Infrastructure & Engineering Teams |
| Network Connectivity | Carrier-neutral platform with dual subterranean path-diverse fiber entrance vaults; redundant Meet-Me-Rooms (MMRs); direct low-latency dark fiber backhaul connecting to Dojima (Osaka's primary carrier hotel), JPNAP, BBIX, and Pacific subsea cable landing routes. |
| Power Infrastructure | Dual high-voltage grid connections supplied by Kansai Electric Power Company, static distributed 2N / N+1 uninterruptible power supply (UPS) modules, automated switchgear, and backup diesel generator plants with multi-day on-site fuel autonomy. |
Technical Specifications
| Header | Details |
| Power Capacity | 130 MW Secured Utility Power Allocation |
| UPS Redundancy | 2N / N+1 Distributed Redundant Static UPS Architecture |
| Cooling System | High-efficiency chilled-water cooling system with free-cooling economizers, Direct-to-Chip Liquid Cooling (DLC) readiness for ultra-high-density AI server clusters, and automated BMS environmental controls. |
| Connectivity | Carrier-neutral access with direct low-latency cloud express on-ramps and cross-connect options across Japanese and international fiber corridors. |
| PUE Target | < 1.30 Annualized Operational Design PUE |
| Energy Mix | 100% Certified Carbon-Free Renewable Energy. |
Milestones
| Header | Details |
| Announcement | 2021 (Keihanna) / 2025 (Minoh) |
| Construction Start | 2021 |
| Phase 1 Go-Live | Operational (2023) |
| Full Buildout | Active Multi-Phase Development |
Investment Details
| Header | Details |
| Total Investment | Estimated $1,000,000,000+ USD Total Campus Capital Expenditure |
| Funding | Joint Venture Equity Financing & Infrastructure Capital Expenditure (Colt DCS / ESR / Fidelity) |