KIO MEX2 Querétaro Data Center Campus: 19MW Digital Hub

Status: Operational (Phase 1) / Active Expansion   |   Location: Circuito El Marqués Norte 21A, Parque Industrial El Marqués, 76246 El Marqués, Querétaro, Mexico


Project Overview

KIO Networks’ MEX2 / QRO2 Data Center Campus in El Marqués, Querétaro, is a strategically located digital infrastructure hub that serves as one of the most important connectivity, cloud, and colocation platforms for Mexico and Central America. Situated within Querétaro’s leading industrial and technology corridor, the campus is designed to meet the increasing demand for hyperscale cloud computing, enterprise digital transformation, artificial intelligence (AI), and mission-critical government and sovereign workloads. The facility delivers up to 12 MW of critical IT capacity across three purpose-built 1,200 m² data halls, expanding KIO Networks’ combined Querétaro campus capacity to nearly 19 MW while providing scalable infrastructure for future growth. Engineered for maximum resilience, the campus features N+1 electrical block redundancy, redundant UPS systems, backup power generation, and advanced environmental monitoring to ensure continuous operations for business-critical applications. Connectivity is a key strength of the development, with dual underground fibre routes, direct interconnection to KIO’s regional fibre rings, and low-latency access to major telecommunications carriers, cloud service providers, and internet exchanges throughout Mexico and neighbouring markets. The campus also incorporates energy-efficient cooling technologies and intelligent building management systems that optimise power usage while maintaining the thermal performance required for high-density compute environments. Supported by robust physical security, multiple layers of cyber protection, and carrier-neutral network architecture, the MEX2 / QRO2 Campus provides a secure, scalable, and future-ready platform for enterprises, hyperscale cloud providers, financial institutions, and public sector organisations, reinforcing Querétaro’s position as Mexico’s premier data centre and digital infrastructure destination.


Quick Facts

FieldValue
Project NameKIO MEX2 Querétaro Data Center Campus: 19MW Digital Hub
LocationCircuito El Marqués Norte 21A, Parque Industrial El Marqués, 76246 El Marqués, Querétaro, Mexico
StatusOperational (Phase 1) / Active Expansion
CommissioningPhase 1 Go-Live: Q1 2024 / QRO2 Campus Operational Milestone: December 2025
Total IT Load12 MW Critical IT Load (QRO2) / ~19 MW Total Campus Capacity (QRO Hub)
Total Capacity19 MW Total Power Capacity across 12,917 m² (139,000 sq ft) of technical whitespace across 3 data halls
Tier LevelTier III Certified Design & Facility / Concurrently Maintainable Architecture (ICREA Level V / ISO 27001 Certified)
Project TypePurpose-Built Greenfield Hyperscale, Enterprise Colocation & Cloud Gateway Campus

City Profile

HeaderDetails
City NameEl Marqués
Population~190,000
Urban Agglomeration~1.4 million (Querétaro Metro Area)
City GDP~USD 8–10 billion (est., part of Querétaro industrial economy)
Per Capita Income~USD 12,000–14,000
City TierEmerging Industrial / Tier 2
Key StrengthsStrategic location in central Mexico; strong aerospace and automotive clusters; proximity to Querétaro International Airport; growing logistics and data center potential; skilled workforce; stable business environment

Companies Involved

HeaderDetails
Developer / Operator KIO Data Centers
Strategic Infrastructure Partner CFE (Comisión Federal de Electricidad) & Parque Industrial El Marqués
Construction Contractor IDOM & Specialized Mexican Mission-Critical Engineering Contractors
MEP Engineering IDOM Engineering & KIO Data Centers Infrastructure Engineering Teams
Network Connectivity Carrier-neutral platform with over 20 telecommunications operators; dual diverse underground fiber entry vaults; direct dark fiber interconnectivity to KIO QRO1, QRO3, and MEX network backbones; and direct access to regional Internet Exchange Points (IXPs).
Power Infrastructure Dual high-voltage grid incomers supplied by CFE, static N+1 / 2N uninterruptible power supply (UPS) system architecture, 6 main electrical distribution blocks plus reserve, and standby diesel backup generators with 48+ hours on-site fuel autonomy.

Technical Specifications

HeaderDetails
Power Capacity12 MW Critical IT Power (QRO2) / 19 MW Total Campus Power
UPS RedundancyN+1 / 2N Block-Redundant UPS Architecture
Cooling System Closed-loop chilled water systems with N+1 redundant cooling design, hot/cold aisle containment, eco-mode air-side economizers, and high-density liquid cooling readiness.
Connectivity Carrier-neutral access with dual Meet-Me-Rooms (MMRs), high-speed fiber cross-connects, and direct low-latency cloud direct-connect gateways.
PUE Target < 1.35 Annualized Design PUE
Energy Mix Utility power grid supply backed by KIO Green sustainability protocols and regional renewable energy certificates (I-RECs).

Milestones

HeaderDetails
Announcement Q2 2022
Construction Start Q1 2023
Phase 1 Go-Live Q1 2024 (Initial 4 MW Phase) / December 2025 (19 MW Milestone Launch)
Full Buildout 2026–2027 (Final Whitespace Phase Delivery)

Investment Details

HeaderDetails
Total InvestmentEstimated $150,000,000 USD to $250,000,000 USD (Full Campus Buildout)
Funding Corporate Capital Expenditure by KIO Data Centers (backed by I Squared Capital)