London Kao Data KL03 40MW AI-Ready Data Center

Status: Under Development / Planning   |   Location: Park Royal, West London, UK


Project Overview

The Kao Data KL03 data center, situated on the former Frogmore Industrial Estate in Park Royal, West London, represents a critical infrastructure development designed to support the UK's expanding AI capabilities and high-performance computing (HPC) landscape. Acquired by Kao Data as a 4.7-acre brownfield site, the project transforms industrial land into an AI-ready hyperscale facility. Delivering a 40 megawatt (MW) critical IT load across its advanced structural envelope, KL03 is engineered from the ground up to accommodate modern high-density hardware architectures, such as dense liquid-cooled GPU clusters running demanding enterprise AI workloads. Power delivery and operational sustainability are fundamental to the KL03 design. Backed by a dedicated high-voltage grid connection from SSEN (Scottish and Southern Electricity Networks), the facility features an N+1 distributed redundant UPS architecture to ensure continuous power availability. To efficiently manage the extreme heat generated by dense compute configurations, Kao Data integrates industrial closed-loop chilled water plants optimized for maximum free-cooling hours. Operating entirely on a 100% renewable energy mix and utilizing hydrotreated vegetable oil (HVO) for its backup generation fleet, KL03 targets an aggressive Power Usage Effectiveness (PUE) rating while reinforcing London’s competitive edge in European digital sovereignty.


Quick Facts

FieldValue
Project NameLondon Kao Data KL03 40MW AI-Ready Data Center
LocationPark Royal, West London, UK
StatusUnder Development / Planning
CommissioningQ3 2028
Total IT Load40 MW
Total Capacity40 MW
Tier LevelTier III Equivalent (High-Availability Industrial Build)
Project TypeHyperscale / AI-Ready Colocation

City Profile

HeaderDetails
City Namelondon
Population 8.9 Million
Urban Agglomeration9.8 to 11.4 million
City GDP£110.8 billion in 2023
Per Capita Income£69,077 in 2023
City TierTier 1
Key StrengthsGlobal Financial Hub; Dense Connectivity; Low Latency to Europe and North America; large skilled talent pool.

Companies Involved

HeaderDetails
Developer / Operator Kao Data
Strategic Infrastructure Partner Infratil (Major Shareholder) & Legal & General Capital
Construction Contractor To Be Announced
MEP Engineering Kao Data Technical Design & Engineering Division
Network Connectivity Diverse Telecom Carriers, Dark Fiber Links to Slough & Docklands
Power Infrastructure High-Voltage Interconnect via SSEN Local Substation

Technical Specifications

HeaderDetails
Power Capacity40 MW Dedicated Critical Power Allocation
UPS RedundancyDistributed Redundant (N+1) Topology
Cooling System Closed-Loop Chilled Water Plant with Evaporative Free Cooling
Connectivity Multiple Carrier-Neutral Meet-Me Rooms, Ultra-Low Latency Links
PUE Target 1.20 (Optimized for Temperate Climates)
Energy Mix 100% Certified Renewable Energy + HVO Fuel Bio-Diesel Backup

Milestones

HeaderDetails
Announcement Q2 2026
Construction Start Q1 2027
Phase 1 Go-Live Q3 2028
Full Buildout Q4 2029

Investment Details

HeaderDetails
Total Investment£350,000,000 GBP (Estimated Capital Expenditure)
Funding Corporate Capital via Infratil Infrastructure Holdings