London Kao Data KL03 40MW AI-Ready Data Center
Status: Under Development / Planning | Location: Park Royal, West London, UK
Project Overview
The Kao Data KL03 data center, situated on the former Frogmore Industrial Estate in Park Royal, West London, represents a critical infrastructure development designed to support the UK's expanding AI capabilities and high-performance computing (HPC) landscape. Acquired by Kao Data as a 4.7-acre brownfield site, the project transforms industrial land into an AI-ready hyperscale facility. Delivering a 40 megawatt (MW) critical IT load across its advanced structural envelope, KL03 is engineered from the ground up to accommodate modern high-density hardware architectures, such as dense liquid-cooled GPU clusters running demanding enterprise AI workloads. Power delivery and operational sustainability are fundamental to the KL03 design. Backed by a dedicated high-voltage grid connection from SSEN (Scottish and Southern Electricity Networks), the facility features an N+1 distributed redundant UPS architecture to ensure continuous power availability. To efficiently manage the extreme heat generated by dense compute configurations, Kao Data integrates industrial closed-loop chilled water plants optimized for maximum free-cooling hours. Operating entirely on a 100% renewable energy mix and utilizing hydrotreated vegetable oil (HVO) for its backup generation fleet, KL03 targets an aggressive Power Usage Effectiveness (PUE) rating while reinforcing London’s competitive edge in European digital sovereignty.
Quick Facts
| Field | Value |
| Project Name | London Kao Data KL03 40MW AI-Ready Data Center |
| Location | Park Royal, West London, UK |
| Status | Under Development / Planning |
| Commissioning | Q3 2028 |
| Total IT Load | 40 MW |
| Total Capacity | 40 MW |
| Tier Level | Tier III Equivalent (High-Availability Industrial Build) |
| Project Type | Hyperscale / AI-Ready Colocation |
City Profile
| Header | Details |
| City Name | london |
| Population | 8.9 Million |
| Urban Agglomeration | 9.8 to 11.4 million |
| City GDP | £110.8 billion in 2023 |
| Per Capita Income | £69,077 in 2023 |
| City Tier | Tier 1 |
| Key Strengths | Global Financial Hub; Dense Connectivity; Low Latency to Europe and North America; large skilled talent pool. |
Companies Involved
| Header | Details |
| Developer / Operator | Kao Data |
| Strategic Infrastructure Partner | Infratil (Major Shareholder) & Legal & General Capital |
| Construction Contractor | To Be Announced |
| MEP Engineering | Kao Data Technical Design & Engineering Division |
| Network Connectivity | Diverse Telecom Carriers, Dark Fiber Links to Slough & Docklands |
| Power Infrastructure | High-Voltage Interconnect via SSEN Local Substation |
Technical Specifications
| Header | Details |
| Power Capacity | 40 MW Dedicated Critical Power Allocation |
| UPS Redundancy | Distributed Redundant (N+1) Topology |
| Cooling System | Closed-Loop Chilled Water Plant with Evaporative Free Cooling |
| Connectivity | Multiple Carrier-Neutral Meet-Me Rooms, Ultra-Low Latency Links |
| PUE Target | 1.20 (Optimized for Temperate Climates) |
| Energy Mix | 100% Certified Renewable Energy + HVO Fuel Bio-Diesel Backup |
Milestones
| Header | Details |
| Announcement | Q2 2026 |
| Construction Start | Q1 2027 |
| Phase 1 Go-Live | Q3 2028 |
| Full Buildout | Q4 2029 |
Investment Details
| Header | Details |
| Total Investment | £350,000,000 GBP (Estimated Capital Expenditure) |
| Funding | Corporate Capital via Infratil Infrastructure Holdings |