Maincubes BER2: 186MW AI-Ready Hyperscale Campus Berlin
Status: Under Construction (Phase 2 Groundbreaking May 2026) | Location: Luckenwalde, South of Berlin
Project Overview
The MainHub Berlin (BER2) campus is a massive 186 MW infrastructure development designed to position Berlin as a major AI and cloud hub, alleviating the capacity constraints currently seen in Frankfurt. Developed by maincubes, the campus is specifically engineered to handle the thermal and electrical demands of modern AI factories, offering liquid-to-chip cooling capabilities for high-density GPU racks. The facility utilizes a modular design that allows for rapid deployment of compute capacity for global hyperscalers and sovereign cloud providers. Strategically located in the South Berlin cluster, it benefits from a direct connection to major international fiber backbones while operating under Germany’s strict GDPR and data sovereignty laws. The project is a pioneer in sustainable urban integration, featuring an advanced heat recovery system that feeds waste thermal energy into local municipal heating networks. By combining massive scale with specialized AI infrastructure, BER2 serves as a critical node for the training and inference of large language models across Central and Eastern Europe.
Quick Facts
| Field | Value |
| Project Name | Maincubes BER2: 186MW AI-Ready Hyperscale Campus Berlin |
| Location | Luckenwalde, South of Berlin |
| Status | Under Construction (Phase 2 Groundbreaking May 2026) |
| Commissioning | Phase 1: Q3 2025; Phase 2: Q4 2026 |
| Total IT Load | 160 MW |
| Total Capacity | 186 MW |
| Tier Level | Tier III+ (High Availability Design) |
| Project Type | Hyperscale / AI-Optimized Colocation |
City Profile
| Header | Details |
| City Name | Berlin |
| Population | ~3.7 million (city proper) |
| Urban Agglomeration | ~6.2–6.3 million |
| City GDP | ~€180–€200 billion |
| Per Capita Income | ~€45,000–€55,000 |
| City Tier | Alpha Global City / Tier 1 World City |
| Key Strengths | Strong startup and tech ecosystem |
Companies Involved
| Header | Details |
| Developer / Operator | maincubes Asset Management |
| Strategic Infrastructure Partner | DTCP (Digital Transformation Capital Partners) |
| Construction Contractor | Royal BAM Group / Zech Group |
| MEP Engineering | Deerns / Arup |
| Network Connectivity | DE-CIX / Colt / EXA Infrastructure |
| Power Infrastructure | E.DIS (Regional Grid Operator) |
Technical Specifications
| Header | Details |
| Power Capacity | 186 MW Total Utility Power |
| UPS Redundancy | N+1 Block Redundant |
| Cooling System | Closed-loop Hybrid (Air + Direct-to-Chip Liquid Cooling) |
| Connectivity | Carrier-neutral; Multiple 100G+ Interconnects |
| PUE Target | 1.15 |
| Energy Mix | 100% Green Power (Wind & Solar PPAs) |
Milestones
| Header | Details |
| Announcement | Q4 2023 |
| Construction Start | Phase 1: 2024; Phase 2: May 2026 |
| Phase 1 Go-Live | September 2025 |
| Full Buildout | Late 2027 |
Investment Details
| Header | Details |
| Total Investment | €1.2 Billion+ |
| Funding | Private Equity (DTCP) & Infrastructure Debt |