Viettel Hoàng Hoa Thám 1 Data Center: Tier III Enterprise Hub in Ho Chi Minh City

Status: Fully Operational / Active Modernized Facility   |   Location: 158/2A Alley, Hoang Hoa Tham, Bay Hien Ward, Tan Binh 72510 Ho Chi Minh Vietnam


Project Overview

Viettel IDC’s Hoàng Hoa Thám 1 Data Center is one of the company’s foundational Tier III-certified urban edge facilities, strategically located in Ho Chi Minh City’s Tân Bình district near Tan Son Nhat International Airport. Delivering 5 MW of critical IT capacity across more than 700 server racks, the facility is designed to support enterprises, financial institutions, telecommunications providers, cloud service operators, government organizations, and mission-critical digital applications requiring secure, low-latency infrastructure. Built in accordance with ANSI/TIA-942 Tier III standards, Hoàng Hoa Thám 1 incorporates Schneider Electric/APC modular UPS systems with N+1 and 2N electrical redundancy, high-capacity 1600A Busway power distribution, and water-cooled heat-dissipation towers supported by 1+1 thermal redundancy to ensure continuous operations and high service availability. The data center is engineered to deliver reliable performance for enterprise IT, hybrid cloud deployments, disaster recovery environments, and latency-sensitive workloads while offering flexible colocation options for future growth. As one of Viettel IDC’s core network exchange facilities, Hoàng Hoa Thám 1 provides direct low-latency cross-connects to major enterprise cloud platforms, domestic telecommunications networks, internet exchanges, and Vietnam’s international subsea fiber cable systems, enabling seamless regional and global connectivity. Combined with advanced physical security, continuous infrastructure monitoring, and scalable digital infrastructure, the facility serves as a critical interconnection hub supporting cloud adoption, enterprise modernization, and digital transformation across southern Vietnam and Southeast Asia.


Quick Facts

FieldValue
Project NameViettel Hoàng Hoa Thám 1 Data Center: Tier III Enterprise Hub in Ho Chi Minh City
Location158/2A Alley, Hoang Hoa Tham, Bay Hien Ward, Tan Binh 72510 Ho Chi Minh Vietnam
StatusFully Operational / Active Modernized Facility
CommissioningOperational / Phased Expansion (Established 2008–2010)
Total IT Load5 MW Critical IT Power Capacity Allocation
Total Capacity5 MW Total Critical Power Capacity across a ~4,000 m² (~43,000 sq ft) gross facility footprint supporting 700+ racks
Tier LevelANSI/TIA-942 Tier III Certified / ISO 27001, ISO 9001, ISO 27017, PCI-DSS, SOC 2 Type II
Project TypePurpose-Built High-Density Enterprise Colocation, Network Peering & Urban Cloud Gateway

City Profile

HeaderDetails
City Nameho chi minh
Population 10 million
Urban Agglomeration14 million as of 2025
City GDP $59.5 billion
Per Capita Income around $9,000 in 2025
City TierTier 1/Primary Economic & Digital Hub
Key StrengthsFastest-growing digital economy in Southeast Asia, high cloud/AI demand, strong government push for digital transformation.

Companies Involved

HeaderDetails
Developer / Operator Viettel IDC
Strategic Infrastructure Partner EVN (Electricity of Vietnam) & Tân Bình District Municipal Infrastructure Authorities
Construction Contractor Specialized Vietnamese Mission-Critical EPC Contractors
MEP Engineering Viettel IDC In-House Technical Infrastructure & Critical Facilities Engineering Teams
Network Connectivity Carrier-neutral platform featuring diverse subterranean fiber entrance vaults; redundant Meet-Me-Rooms (MMRs); direct low-latency dark fiber backhaul to Viettel Complex (285 CMMT), national backbone networks, and subsea cable landing stations (AAE-1, APG, IA, ADC, ALC).
Power Infrastructure Dual path-diverse utility grid connections supplied by EVN, static distributed 2(N+1) APC/Schneider Electric uninterruptible power supply (UPS) modules (15-min battery autonomy), 1600A Busway power distribution, and 1+1 redundant standby diesel generators with 3-day fuel autonomy.

Technical Specifications

HeaderDetails
Power Capacity5 MW Secured Utility Power Allocation
UPS Redundancy2(N+1) / N+1 Distributed Redundant Static UPS Architecture
Cooling System Precision chilled-water precision air-conditioning units with Liangchi 1+1 cooling towers, cool aisle containment, automated water leak detection systems, and BMS environmental monitoring.
Connectivity Carrier-neutral host offering direct low-latency cloud express on-ramps and cross-connect options across Vietnamese and regional fiber corridors.
PUE Target < 1.50 Annualized Operational Design PUE
Energy Mix High-reliability EVN grid power integrated with energy-efficient Schneider PDU controls and localized efficiency optimizations.

Milestones

HeaderDetails
Announcement Operational Phase
Construction Start Facility Construction Phase
Phase 1 Go-Live Operational
Full Buildout Operational Active Facility

Investment Details

HeaderDetails
Total InvestmentEstimated $20,000,000 USD to $35,000,000 USD Cumulative Facility Capital Expenditure
Funding Corporate Capital Expenditure & Infrastructure Equity Financing by Viettel Group / Viettel-CHT