Yotta G1 GIFT City Superscale Cloud Data Center (2 MW)

Status: Live / Operational   |   Location: 12th Floor, Signature Building, Road No 1c, GIFT City, Gandhinagar, Gujarat 382355


Project Overview

The Yotta G1 Superscale Cloud Data Center represents a highly specialized, niche addition to India's digital infrastructure, located directly inside the Special Economic Zone (SEZ) / International Financial Services Centre (IFSC) of Gujarat International Finance Tec-City (GIFT City). Housed within the iconic Signature Building, this 2 MW facility is tailored specifically to meet the high-security, compliance, and latency requirements of banking, financial services, and insurance (BFSI) enterprises. It also serves global businesses leveraging the progressive regulatory environment of the IFSC. A standout feature of Yotta G1 is its unique "Data Embassy" designation. This status allows foreign enterprises and sovereign nations to store their critical information in a physical environment that operates under the legal jurisdiction and data laws of their home countries, right on Indian soil. Structurally, the 21,000-square-foot facility houses up to 350 high-density racks. It is physically engineered with robust security protocols, biometric controls, and redundant utility pathways that are heavily insulated from standard metropolitan vulnerabilities. On the technical and environmental front, the data center operates with high resource efficiency. G1 is the first facility of its kind to integrate with GIFT City's advanced central District Cooling System (DCS). This system routes chilled water directly into the facility from a central cooling plant through a shared underground utility tunnel, eliminating the need for bulky, water-consuming on-site cooling towers. Grid power is delivered via a 33 kV dual-feed circuit running through the same utility tunnel, backed by 2N redundant power distribution units (PDUs) and backup diesel generator systems. This makes G1 an exceptionally secure, sustainable hub for high-performance sovereign cloud hosting and financial colocation.  


Quick Facts

FieldValue
Project NameYotta G1 GIFT City Superscale Cloud Data Center (2 MW)
Location12th Floor, Signature Building, Road No 1c, GIFT City, Gandhinagar, Gujarat 382355
StatusLive / Operational
CommissioningQ1 2024
Total IT Load1 MW
Total Capacity2 MW
Tier LevelTier III equivalent standard (designed for high availability)
Project TypeEdge / Superscale Cloud Data Center & Data Embassy

City Profile

HeaderDetails
City NameGandhinagar
Population208,299 (2011 Census; current estimates are higher)
Urban AgglomerationApproximately 1 million+ (Gandhinagar–Ahmedabad urban region estimate)
City GDPNo official standalone city GDP is published; Gandhinagar is part of Gujarat’s major economic and industrial corridor
Per Capita IncomeGujarat per capita NSDP: approximately ₹2.50 lakh at current prices
City TierTier 2
Key StrengthsGujarat’s administrative capital; strong government and institutional presence; proximity to Ahmedabad; growing technology and digital infrastructure ecosystem; planned urban development; strong connectivity and industrial corridor access.

Companies Involved

HeaderDetails
Developer / Operator Yotta Data Services Private Limited
Strategic Infrastructure Partner Government of Gujarat & International Financial Services Centres Authority (IFSCA)
Construction Contractor Hiranandani Group Construction Division
MEP Engineering Yotta In-house Design & Technical Engineering Team
Network Connectivity Redundant dual 24-core fiber optic pathways connecting directly to the central GIFT Meet-Me-Room (MMR)
Power Infrastructure Dual-feed 33 kV connection routed through GIFT City's underground utility tunnel

Technical Specifications

HeaderDetails
Power Capacity2 MW Grid Allocation
UPS Redundancy2N Redundant UPS configuration with dedicated battery systems
Cooling System Deep integration with GIFT City's underground central District Cooling System (DCS)
Connectivity Carrier-neutral, high-density copper and fiber cross-connects
PUE Target 1.50
Energy Mix High-reliability grid energy combined with green power procurement matching

Milestones

HeaderDetails
Announcement Late 2023
Construction Start Late 2023
Phase 1 Go-Live Operational
Full Buildout Operational

Investment Details

HeaderDetails
Total Investment~ $20 Million USD
Funding Corporate capital allocation (Hiranandani Group equity)