atNorth SWE04 Sollefteå AI Campus (300 MW)
Status: Announced (Feb 24, 2026) | Location: Sollefteå (Långsele)
Project Overview
The atNorth SWE04 Sollefteå Campus is a flagship 300 MW high-density data center development announced on February 24, 2026. Located in the Hamre Industrial Park in Långsele, Sweden, this project is designed to be one of the largest and most sustainable AI-ready campuses in the Nordic region. Spanning a 50-hectare plot, the facility is engineered specifically for the next generation of high-performance computing (HPC) and generative AI workloads, with the ability to support extreme power densities of up to 1 MW per rack.
The project distinguishes itself through its "circular economy" approach. atNorth is implementing an advanced heat reuse system designed to export excess heat from the servers to local industrial or residential heating networks, significantly reducing the carbon footprint. The site utilizes 100% renewable energy from Sweden’s robust hydroelectric and wind power grid. Leveraging the naturally cold Nordic climate, the facility will use direct liquid cooling and free air cooling for the majority of the year, aiming for a market-leading PUE. The first phase is expected to be operational by the first half of 2028, positioning Sollefteå as a critical node in Europe’s digital infrastructure.
Quick Facts
| Field | Value |
| Project Name | atNorth SWE04 Sollefteå AI Campus (300 MW) |
| Location | Sollefteå (Långsele) |
| Status | Announced (Feb 24, 2026) |
| Commissioning | H1 2028 (Phase 1) |
| Total IT Load | 17.0587 |
| Total Capacity | 50-Hectare Campus (Multiple Data Halls) |
| Tier Level | Tier III Equivalent |
| Project Type | Hyperscale / AI Factory |
City Profile
| Header | Details |
| City Name | Sollefteå |
| Population | Around 19,000 people |
| Urban Agglomeration | Similar, around 19,000-20,000 (as it's a small town) |
| City GDP | €700 million |
| Per Capita Income | €25,000-€30,000 annually |
| City Tier | Tier 3 |
| Key Strengths | Strong connection to nature and tourism (forests, lakes) |
Companies Involved
| Header | Details |
| Developer / Operator | atNorth |
| Strategic Infrastructure Partner | Sollefteå Municipality / Local Utility Providers |
| Construction Contractor | To be announced |
| MEP Engineering | atNorth In-house |
| Network Connectivity | Multiple Dark Fiber Routes; Carrier Neutral |
| Power Infrastructure | Regional Renewable Grid (Hydro/Wind) |
Technical Specifications
| Header | Details |
| Power Capacity | 300 MW Total Utility Capacity |
| UPS Redundancy | N+1 / Distributed Redundancy |
| Cooling System | Direct Liquid Cooling (DLC) & Heat Reuse Technology |
| Connectivity | NA |
| PUE Target | < 1.15 |
| Energy Mix | 100% Renewable (Hydro/Wind) |
Milestones
| Header | Details |
| Announcement | February 24, 2026 |
| Construction Start | Q4 2026 (Expected) |
| Phase 1 Go-Live | 2028 |
| Full Buildout | 2031 |
Investment Details
| Header | Details |
| Total Investment | Estimated $1.5 Billion+ |
| Funding | Private Equity / Corporate Capital |