AVAIO Appomattox: $3B AI Data Center 1GW Virginia

Status: Under Construction (Site Prep / Early Civil)   |   Location: 452-Acre Site, Heartland Innovation Technology Park, Appomattox


Project Overview

AVAIO Appomattox, internally known as Project Hercules, is a strategic $3 billion hyperscale development designed to expand Virginia’s data center footprint beyond the power-constrained Northern Virginia corridor. Officially moving into site preparation in late 2024 and entering active civil works by March 2026, the campus covers 452 acres of shovel-ready land. The site is uniquely positioned outside the "Data Center Alley" gridlock, offering a high-reliability alternative for AI, HPC, and cloud deployments.

The "Hercules" campus is defined by its dual-power path. While it has secured an initial 300 MW of grid capacity from Dominion Energy and CVEC, the site is located directly atop the Williams Transco gas pipeline. This allows AVAIO to implement behind-the-meter (BTM) thermal generation to scale the campus to 1 gigawatt total capacity without waiting for traditional grid transmission upgrades. Sustainability is integrated via 30+ MW of on-site solar and a focus on water-neutral cooling to preserve the Central Virginia watershed.


Quick Facts

FieldValue
Project NameAVAIO Appomattox: $3B AI Data Center 1GW Virginia
Location452-Acre Site, Heartland Innovation Technology Park, Appomattox
StatusUnder Construction (Site Prep / Early Civil)
CommissioningPhase 1: Q3 2027; Full Buildout: 2030+
Total IT Load300 MW (Grid) / 1,000 MW (Total Master Plan)
Total CapacityMulti-building Hyperscale Campus (436-452 Acres)
Tier LevelTier III+ (AI-Optimized)
Project TypeHyperscale / AI & Power Campus

City Profile

HeaderDetails
City NameAppomattox
Population18,000 (Population estimate, adjust accordingly)
Urban Agglomeration20,000 (Urban area population, adjust accordingly)
City GDP$300 million (Adjust based on the latest data)
Per Capita Income$35,000 (Based on the national average or city data)
City TierTier 4 (Example: Tier 4 city classification, adjust if needed)
Key StrengthsRich historical significance

Companies Involved

HeaderDetails
Developer / Operator AVAIO Digital
Strategic Infrastructure Partner Dominion Energy / CVEC / Williams Transco
Construction Contractor TBD (National Hyperscale Specialist)
MEP Engineering DLB Associates / Schneider Electric
Network Connectivity Dense long-haul fiber (Zayo, Windstream, Segra)
Power Infrastructure Dual-feed Grid + On-site Gas Pipeline access

Technical Specifications

HeaderDetails
Power Capacity300 MW (Grid) / 700 MW (BTM Gas) / 1 GW (Total)
UPS Redundancy$N+1$ with Lithium-Ion BESS integration
Cooling System High-Efficiency Evaporative Hybrid (Water-Optimized)
Connectivity Strategic access to primary North-South long-haul fiber
PUE Target 1.15
Energy Mix Grid + 30MW On-site Solar + Natural Gas BTM

Milestones

HeaderDetails
Announcement December 10, 2024
Construction Start Late 2025 / Early 2026
Phase 1 Go-Live Q3 2027 (Target 50MW energized)
Full Buildout 2030+

Investment Details

HeaderDetails
Total Investment$3 Billion
Funding AVAIO Capital / Institutional Partners