AWS St. Joseph County Indiana Data Center Campus

Status: Active Construction & Operational Expansion   |   Location: Indiana Enterprise Center footprint, New Carlisle, St. Joseph County, Indiana 46552, USA


Project Overview

Amazon Web Services’ (AWS) $26 billion multi-campus development in St. Joseph County, Indiana, represents one of the largest digital infrastructure investments in North American history. Building upon an initial $11 billion commitment in New Carlisle, AWS expanded the master plan with an additional $15 billion allocation to deliver 2.4 gigawatts (2.4 GW) of cumulative IT and facility capacity across Northern Indiana. Engineered specifically as a core processing node for generative AI and frontier computing models including custom AWS Trainium/Inferentia silicon and dense NVIDIA GPU clusters the campus provides the underlying infrastructure for high-throughput AI workloads like Project Rainier. The campus footprint spans dozens of modular multi-story data hall structures integrated with dedicated high-voltage substation switchyards. Power distribution is secured through a landmark long-term agreement with Northern Indiana Public Service Company (NIPSCO), which provides high-voltage transmission interconnects backed by regional renewable power purchase agreements (PPAs). Sustainability and resource conservation are built into the facility design. The site utilizes AWS’s advanced liquid-to-chip direct cooling and dry-cooling closed-loop architectures, minimizing water consumption during peak thermal operational cycles. The development acts as a massive economic anchor for Northern Indiana, supporting over 1,100 direct high-tech roles, thousands of union construction jobs, and partnerships with local technical institutions.


Quick Facts

FieldValue
Project NameAWS St. Joseph County Indiana Data Center Campus
LocationIndiana Enterprise Center footprint, New Carlisle, St. Joseph County, Indiana 46552, USA
StatusActive Construction & Operational Expansion
CommissioningH1 2025 (Initial Phase Live)
Total IT Load2,000 MW
Total Capacity2,400 MW (2.4 GW master-planned campus grid capacity)
Tier LevelTier III Compliant System Architecture Standards
Project TypeGreenfield Hyperscale Cloud & Frontier AI Supercomputing Megahub

City Profile

HeaderDetails
City NameIndiana
Population~6.83 million
Urban AgglomerationMajor metros: Indianapolis ~2.1M, Chicago metro (IN portion included)
City GDP~$450 billion (state GDP)
Per Capita Income~$58,000
City TierTier 1 (Developed U.S. state with strong industrial base)
Key StrengthsManufacturing hub (automotive, steel), logistics & transportation, growing data center market, central U.S. location, strong infrastructure, affordable power

Companies Involved

HeaderDetails
Developer / Operator Amazon Web Services
Strategic Infrastructure Partner Northern Indiana Public Service Company (NIPSCO), St. Joseph County Board of Commissioners, Indiana Economic Development Corporation (IEDC)
Construction Contractor Mortenson Construction / Pepper Construction Joint Venture & Specialized Mission-Critical EPC Partners
MEP Engineering AWS Infrastructure Design & Specialized Global Engineering Partners
Network Connectivity Subterranean concrete fiber vaults, redundant terrestrial dark fiber trunks to Chicago Infomart, and dual Meet-Me-Rooms.
Power Infrastructure Direct connection via dual 345kV high-voltage utility substations engineered by NIPSCO.

Technical Specifications

HeaderDetails
Power Capacity2,400 MW (2.4 GW) gross utility substation design capacity
UPS RedundancyN+1 block-isolated static UPS systems backed by containerized emergency standby diesel generator arrays with bulk fuel storage.
Cooling System Direct-to-chip liquid cooling manifolds combined with closed-loop dry cooling systems for ultra-low water utilization.
Connectivity Carrier-neutral design featuring four physically separated subterranean concrete fiber entry vaults and dual Meet-Me-Rooms.
PUE Target 1.13
Energy Mix Matched with 100% clean energy via NIPSCO green tariffs, regional wind, and solar Power Purchase Agreements (PPAs).

Milestones

HeaderDetails
Announcement April 2024 (Initial $11B) / November 2025 (Expanded $15B)
Construction Start Q3 2024
Phase 1 Go-Live H1 2025
Full Buildout 2032 (Phased commissioning across full 2.4 GW campus footprint)

Investment Details

HeaderDetails
Total Investment$26,000,000,000 USD ($11B initial + $15B Northern Indiana expansion)
Funding Direct corporate capital expenditure via Amazon.com, Inc. balance sheet reserves