CapitaLand Data Centre Chennai 01: 54MW High-Density AI-Ready Hub

Status: Active Development / Under Construction   |   Location: Pattravakkam Rd, Sidco Industrial Estate, Ambattur, Chennai, Greater Chennai, Tamil Nadu 600053


Project Overview

CapitaLand Data Centre Chennai 01 (CLDC Chennai 01) is a flagship hyperscale-ready data center located on a 4-acre site in Ambattur, one of Chennai’s primary industrial and information technology corridors. Designed to support global hyperscale cloud providers, enterprise organizations, and digital service operators, the facility delivers 54 MW of gross power, including approximately 34 MW of critical IT capacity. The campus comprises 12 purpose-built data halls engineered to accommodate high-density computing environments, featuring slab-to-slab ceiling heights of 7.3 meters and floor-loading capacities of up to 2,000 kg/m² to support advanced rack configurations and AI infrastructure. CLDC Chennai 01 is equipped with a combination of Direct-to-Chip liquid cooling and high-efficiency air-cooled systems, enabling the deployment of GPU-intensive artificial intelligence (AI) and high-performance computing (HPC) workloads while optimizing energy efficiency. Additional sustainability features include water economizers, solar power integration, and energy-efficient building systems designed to achieve LEED Gold certification. Strategically located near Chennai’s major telecommunications infrastructure, the facility offers low-latency optical connectivity to regional carrier networks and nearby international submarine cable landing stations, providing resilient access to domestic and global digital ecosystems. With redundant power and cooling infrastructure, advanced physical security, scalable expansion capabilities, and AI-ready design, CLDC Chennai 01 serves as a future-focused digital infrastructure hub supporting cloud computing, enterprise applications, and next-generation AI deployments across India and the Asia-Pacific region.


Quick Facts

FieldValue
Project NameCapitaLand Data Centre Chennai 01: 54MW High-Density AI-Ready Hub
LocationPattravakkam Rd, Sidco Industrial Estate, Ambattur, Chennai, Greater Chennai, Tamil Nadu 600053
StatusActive Development / Under Construction
CommissioningPhase 1 Go-Live: Target 2025–2026 / Active Phased Buildout
Total IT Load34 MW Critical IT Power Capacity Allocation (54 MW Gross Power Capacity)
Total Capacity54 MW Gross Power Capacity across a 4-acre (~16,187 m²) freehold site footprint with 12 data halls
Tier LevelTier III Equivalent Hyper-Resilient Design / LEED Gold Certification Target / ISO 27001, PCI-DSS Compliant
Project TypePurpose-Built Hyperscale, AI-Ready High-Density Colocation & Enterprise Cloud Hub

City Profile

HeaderDetails
City NameChennai
Population~7.09 million (2021)
Urban Agglomeration~11 million (Chennai Metropolitan Area)
City GDP~$78.6 Billion USD (Estimated for Chennai, making it a key economic center)
Per Capita IncomeHigh (Relative to national average)
City TierTier 1 (Major metro and economic hub)
Key StrengthsMajor subsea cable landing station hub for South Asia, strong IT/ITES presence, established industrial and manufacturing base, skilled workforce.

Companies Involved

HeaderDetails
Developer / Operator CapitaLand
Strategic Infrastructure Partner TNEB / TANGEDCO Utility Network & Government of Tamil Nadu Municipal Authorities
Construction Contractor Specialized Indian Mission-Critical General EPC Contractors
MEP Engineering CapitaLand In-House Data Centre Engineering & Global Technical Infrastructure Teams
Network Connectivity Carrier-neutral platform with 4 diversified subterranean fiber entrance points; 2 Meet-Me-Rooms (MMRs) per floor; direct dark fiber access to local cable landing stations, major IXPs, and carrier networks.
Power Infrastructure High-voltage utility grid connections, N+N static redundant uninterruptible power supply (UPS) modules with 8 minutes EOL battery backup, dual power distribution (single/3-phase per rack), and standby diesel generator backup arrays.

Technical Specifications

HeaderDetails
Power Capacity54 MW Gross Power Capacity Allocation (34 MW IT Load)
UPS RedundancyN+N Redundant Static UPS Architecture for IT Load
Cooling System N+4 redundant air-cooled chilled-water system, water economization integration, Direct-to-Chip Liquid Cooling readiness for high-density AI clusters, and automated BMS environmental controls.
Connectivity Carrier-neutral host offering direct low-latency cloud express on-ramps and cross-connect options across Indian domestic fiber corridors.
PUE Target < 1.35 Annualized Operational Design PUE
Energy Mix High-efficiency utility grid mix integrated with on-site solar panel power generation and green power purchase agreements.

Milestones

HeaderDetails
Announcement December 2022 (Land Acquisition) / October 2023
Construction Start April 2024 / Q2 2025 (Official Commencement)
Phase 1 Go-Live Target 2025–2026
Full Buildout Active Multi-Phase Development

Investment Details

HeaderDetails
Total InvestmentEstimated ₹1,200+ Crores INR (~$145,000,000 USD / S$195,000,000 SGD) Capital Expenditure
Funding CapitaLand India Trust (CLINT) Equity, Onshore Construction Debt & CapitaLand India Data Centre Fund