Cirion Technologies Lima Data Center Campus: Peru's 20MW AI & Cloud Hub

Status: Under Construction / Active Phased Expansion   |   Location: Av. Manuel Olguín 395, Santiago de Surco 15023, Peru


Project Overview

Cirion Technologies’ Lima Data Center Campus is a premier digital infrastructure development strategically positioned to support Peru’s growing demand for cloud computing, artificial intelligence (AI), and enterprise digital transformation services. The campus is anchored by the newly developed LIM2 facility in the Macrópolis Industrial District of Lurín, complemented by the operational LIM1 data center in Surco, creating a highly resilient multi-site platform serving domestic and international customers. Together, the campus delivers more than 20 MW of total IT power capacity across approximately 12,000 square metres of purpose-built data center space, providing scalable colocation solutions for hyperscale cloud providers, telecommunications operators, financial institutions, government organizations, and large enterprises. The LIM2 facility has been engineered from the ground up to accommodate high-density computing environments, including AI, machine learning (ML), high-performance computing (HPC), and next-generation GPU deployments, with direct-to-chip liquid cooling readiness for future high-density workloametersstainability is a core feature of the campus, which is powered entirely by 100% renewable hydroelectric energy, supporting customers' environmental and carbon reduction objectives. The campus is further strengthened by redundant fiber backhaul infrastructure connecting Lurín to Lima’s central business district, major carrier hotels, internet exchange points, and Pacific coast subsea cable landing stations, enabling low-latency domestic and international connectivity. Combining renewable energy, resilient network infrastructure, scalable capacity, and AI-ready design, Cirion Technologies’ Lima Data Center Campus provides a future-ready digital infrastructure platform supporting Peru’s expanding cloud ecosystem and the broader digital economy across Latin America.


Quick Facts

FieldValue
Project NameCirion Technologies Lima Data Center Campus: Peru's 20MW AI & Cloud Hub
LocationAv. Manuel Olguín 395, Santiago de Surco 15023, Peru
StatusUnder Construction / Active Phased Expansion
CommissioningPhase 1 (LIM2) Launching: Target Q4 2025 / 2026 Phase Rollout
Total IT Load~15 MW – 20 MW Critical IT Power Allocation
Total Capacity20+ MW Total Utility Power Allocation across 25,000 m² (~269,000 sq ft) total site area
Tier LevelTier III Certified Design Architecture / ISO 9001, ISO 14001, ISO 20000-1, ISO 27001, ISO 45001, PCI-DSS 4.0 Certified Platform
Project TypePurpose-Built Hyperscale, High-Density AI-Ready Colocation & Cloud Interconnect Gateway

City Profile

HeaderDetails
City NameLima
Population~10.1 million
Urban Agglomeration~11.5 million (Lima Metropolitan Area)
City GDP~USD 110 billion (estimated metropolitan economy)
Per Capita Income~USD 10,000
City TierTier 1 – Business, Financial & Digital Infrastructure Hub
Key StrengthsCapital and largest city of Peru; country's financial and commercial center; major Pacific trade gateway; expanding cloud and data center market; strong telecommunications and fiber connectivity; growing fintech and technology ecosystem; skilled workforce; modern logistics infrastructure; leading business process outsourcing (BPO) hub; strategic gateway to Andean and Pacific Alliance markets.

Companies Involved

HeaderDetails
Developer / Operator Cirion Technologies
Strategic Infrastructure Partner Luz del Sur / Enel Distribución Perú (Electric Utilities) & Regional Subsea Cable Consortium Partners
Construction Contractor Specialized LATAM Mission-Critical Engineering & EPC Contractors
MEP Engineering Cirion Technologies In-House Technical Infrastructure & Thermal Engineering Teams
Network Connectivity Carrier-neutral platform with dual redundant underground fiber entrance vaults; multi-tenant Meet-Me-Rooms (MMRs); direct low-latency redundant fiber ring linking LIM2 in Lurín to LIM1 in Surco (35 km) and direct express on-ramps to global cloud providers.
Power Infrastructure 9 independent high-voltage utility feeders, static distributed N+N (2N / 2N+2C) uninterruptible power supply (UPS) systems, automated switchgear, and standby N+N diesel generator plants (6 x 2.1MW DCC) with on-site fuel reserves.

Technical Specifications

HeaderDetails
Power Capacity20+ MW Total Secured Utility Power Capacity Allocation
UPS RedundancyDistributed Redundant N+N (2N / 2N+2C) Static UPS Configuration
Cooling System Precision perimeter N+1 CRAC cooling units, Direct-to-Chip Liquid Cooling (DLC) readiness for high-density AI/HPC GPU cabinets (up to 9.8+ kW/rack density), and water mist environmental controls.
Connectivity Carrier-neutral host offering direct low-latency cloud express on-ramps and cross-connect options across Peru and Latin America.
PUE Target < 1.35 Annualized Operational Design PUE
Energy Mix 100% Certified Green Renewable Energy (Hydroelectric Power PPAs).

Milestones

HeaderDetails
Announcement Initial Launch: 2023 / Pre-Sale & Development: 2024–2025
Construction Start 2023 / 2024
Phase 1 Go-Live Target Q4 2025 / 2026
Full Buildout Active Multi-Site Metro Expansion

Investment Details

HeaderDetails
Total InvestmentEstimated $120,000,000 USD to $180,000,000 USD Total Campus Investment
Funding Corporate Capital Expenditure & Infrastructure Financing by Cirion Technologies / Stonepeak

Stay Ahead in the Data Center World

Subscribe to our exclusive newsletter and get the latest insights on data center trends, market forecasts, and infrastructure innovations delivered straight to your inbox.