EcoDataCenter Falun Data Center Expansion: 80MW Sustainable AI Hub

Status: Active Multi-Building Expansion / Under Construction   |   Location: Slaggvarpsvägen 21, 791 77 Falun, Dalarna County, Sweden


Project Overview

EcoDataCenter 1 in Falun, Sweden, is widely recognized as one of the world’s first climate-positive data center campuses, purpose-built to support high-performance computing (HPC), artificial intelligence (AI), and other compute-intensive digital workloads. Designed with sustainability as its foundation, the campus spans approximately 35,000 m² and is undergoing continuous expansion with modular data halls that will increase total utility capacity to approximately 80 MW. A defining feature of the facility is its innovative construction using Cross-Laminated Timber (CLT) mass timber supplied by Stora Enso, significantly reducing embodied carbon compared with conventional concrete and steel structures. EcoDataCenter 1 operates entirely on 100% renewable electricity generated from Swedish wind and hydroelectric power, providing customers with a low-carbon platform for cloud computing, AI model training, and enterprise digital infrastructure. The campus also incorporates advanced cooling systems and energy-efficient operational practices to maximise performance while minimising environmental impact. Through direct integration with Falu Energi & Vatten’s combined heat and power (CHP) plant, excess heat generated by the data center is recovered and supplied to the local district heating network while also supporting commercial biofuel pellet manufacturing, creating a highly efficient circular energy ecosystem. By combining renewable energy, sustainable construction materials, innovative heat recovery, and scalable AI-ready infrastructure, EcoDataCenter 1 has established itself as a global benchmark for environmentally responsible, high-density digital infrastructure and next-generation sustainable data center development.


Quick Facts

FieldValue
Project NameEcoDataCenter Falun Data Center Expansion: 80MW Sustainable AI Hub
LocationSlaggvarpsvägen 21, 791 77 Falun, Dalarna County, Sweden
StatusActive Multi-Building Expansion / Under Construction
CommissioningInitial Phase: 2019 / Expansion Halls Go-Live: 2025–2026
Total IT Load~60 MW Critical IT Load
Total Capacity80 MW to 90 MW Total Utility Power Allocation across a 35,000 m² campus footprint
Tier LevelTier III / EN 50600 Certified Architecture (ISO 27001, ISO 14001, ISO 9001 Certified)
Project TypePurpose-Built High-Density AI/HPC Colocation, Solid Wood Modular Architecture & Climate-Positive Hub

City Profile

HeaderDetails
City NameFalun
Population~39,000
Urban Agglomeration~105,000
City GDP~USD 4.5 billion
Per Capita Income~USD 48,000
City TierTier 3 City
Key StrengthsUNESCO World Heritage mining heritage, strong education sector, winter sports hub, sustainable urban planning, healthcare services, tourism, regional manufacturing, high quality of life

Companies Involved

HeaderDetails
Developer / Operator EcoDataCenter
Strategic Infrastructure Partner Falu Energi & Vatten (Municipal Energy & Utility) & Stora Enso (Timber Structure Engineering)
Construction Contractor ByggPartner & Specialized Nordic Mission-Critical EPC Contractors
MEP Engineering Vertiv, Schneider Electric, & EcoDataCenter In-House Thermal Design Engineering Teams
Network Connectivity Carrier-neutral platform with dual diverse underground fiber entrance vaults; redundant Meet-Me-Rooms (MMRs); ultra-low-latency direct connections to Stockholm (3 ms RTD) and global European carrier backbones.
Power Infrastructure Dual 80 MW high-voltage grid incomers fed by independent substations, static 2N / N+1 uninterruptible power supply (UPS) systems, automated switchgear, and backup diesel generator plants fueled by Hydrotreated Vegetable Oil (HVO100).

Technical Specifications

HeaderDetails
Power Capacity80 MW Total Secured Utility Power Capacity
UPS Redundancy2N / N+1 Static Uninterruptible Power Supply (UPS) Configuration
Cooling System High-efficiency chilled-water Liebert PCW cooling units (Vertiv), direct-to-chip liquid cooling readiness, closed-loop heat recovery, and direct thermal export loop to city power/biofuel plants.
Connectivity Carrier-neutral access with direct low-latency cloud express on-ramps and cross-connect options across Scandinavian fiber networks.
PUE Target < 1.15 Annualized Operational Design PUE (Net-Negative Carbon Footprint via heat reuse)
Energy Mix 100% Green Renewable Energy (Hydroelectric & Wind Power) backed by long-term PPAs.

Milestones

HeaderDetails
Announcement Initial Build: 2018 / Expansion Phases: 2022–2024
Construction Start Active Phased Buildouts
Phase 1 Go-Live Operational (Halls A–D) / 2025–2026 (Halls E & F)
Full Buildout Operational Active Expansion

Investment Details

HeaderDetails
Total InvestmentEstimated SEK 1.5 Billion to SEK 2.8 Billion (~$140M–$260M USD)
Funding Corporate Capital Expenditure & Sustainable Infrastructure Financing by EcoDataCenter / Areim