NEXTDC M4 Melbourne: $2B 162MW Sovereign AI Factory Campus

Status: Approved / Pre-Construction & Site Preparation Phase   |   Location: 127 Todd Road, Port Melbourne, Victoria 3207, Australia


Project Overview

NEXTDC’s M4 Melbourne is a flagship A$2.0 billion (US$1.3 billion+) digital infrastructure campus strategically located on a 127 Todd Road site within the Fishermans Bend Innovation Precinct in Port Melbourne, one of Australia’s most significant technology and innovation districts. Purpose-built as Australia’s premier sovereign AI Factory and hyperscale data center campus, M4 is designed to deliver 162 MW of critical IT capacity across approximately 50,000 m² of technical whitespace, providing exceptional scalability for hyperscale cloud providers, government agencies, research institutions, and enterprise customers. Located just minutes from Melbourne’s Central Business District (CBD), the campus combines low-latency connectivity with resilient infrastructure to support the next generation of artificial intelligence, machine learning, and high-performance computing (HPC) applications. M4 is specifically engineered for ultra-high-density GPU deployments, supporting rack densities of up to 1,000 kW per rack through advanced closed-loop direct-to-chip liquid cooling, enabling efficient operation of the world’s most demanding AI workloads while optimising energy and thermal performance. Designed to achieve Tier IV fault-tolerant reliability, the facility offers industry-leading resilience, redundant power and cooling systems, and a 100% uptime guarantee for mission-critical digital operations. Customers also benefit from direct cross-connects to AXON, NEXTDC’s high-performance interconnection platform, along with native access to all major public cloud providers, enabling seamless hybrid and multi-cloud connectivity. Combined with enterprise-grade security, scalable infrastructure, and future-ready AI capabilities, NEXTDC’s M4 Melbourne establishes a world-class digital platform that strengthens Australia’s sovereign computing capacity and supports the rapidly growing demands of AI, cloud, and advanced digital services.


Quick Facts

FieldValue
Project NameNEXTDC M4 Melbourne: $2B 162MW Sovereign AI Factory Campus
Location127 Todd Road, Port Melbourne, Victoria 3207, Australia
StatusApproved / Pre-Construction & Site Preparation Phase
CommissioningTarget Phase 1 Go-Live: 2027/2028 (Phased expansion through 2030+)
Total IT Load150 MW to 162 MW Total Critical IT Capacity
Total Capacity162 MW Total IT Load across 50,000 m² (538,000 sq ft) technical data hall space
Tier LevelTarget Tier IV Certified / Fault-Tolerant Design (Uptime Institute Tier IV Constructed Facility & Gold Operational Sustainability Target)
Project TypePurpose-Built Greenfield Hyperscale, Sovereign Cloud & NVIDIA-Certified AI Factory Campus

City Profile

HeaderDetails
City Namemelbourne
PopulationCity Proper (Estimated 2026): ~5.2–5.3 million
Urban Agglomeration~5.3+ million (Greater Melbourne region)
City GDP~USD 320–380 billion
Per Capita IncomeApprox.: USD 65,000–75,000
City TierGlobal Alpha City (Beta+ to Alpha tier depending on index)
Key StrengthsStrong finance, banking, and professional services sector

Companies Involved

HeaderDetails
Developer / Operator NEXTDC
Strategic Infrastructure Partner CitiPower / Powercor (Electrical Utilities), Victorian State Government, NVIDIA (AI Factory Alliance)
Construction Contractor Specialized Australian Mission-Critical EPC & Tier 1 Construction Contractors
MEP Engineering NEXTDC Global Engineering & High-Density Thermal Design Teams
Network Connectivity Dual geodiverse underground fiber entry paths; interconnected via AXON to NEXTDC M1, M2, and M3; direct carrier-neutral access to 70+ network providers, Megaport, and native cloud access points (AWS, Azure, Google Cloud).
Power Infrastructure Dual high-voltage 66kV/22kV utility substation connections, static 2N / block-redundant uninterruptible power supply (UPS) topology, and 2N emergency standby diesel generators with 72+ hours of on-site fuel autonomy.

Technical Specifications

HeaderDetails
Power Capacity162 MW Critical IT Power Capacity / High-Voltage Substation Feed
UPS Redundancy2N Static UPS Architecture
Cooling System Closed-loop chilled water systems utilizing non-potable recycled water, direct-to-chip liquid cooling, and immersion cooling capability engineered to support high-density AI nodes up to 1,000 kW per rack.
Connectivity Carrier-neutral ecosystem with dual Meet-Me-Rooms (MMRs), high-capacity dark fiber Data Center Interconnect (DCI) links across Greater Melbourne, and global cloud orchestration via AXON.
PUE Target < 1.15 Annualized Operational Design PUE
Energy Mix 100% clean renewable power procurement options backed by Australian Large-scale Generation Certificates (LGCs) and NEXTDC Corporate PPA strategy.

Milestones

HeaderDetails
Announcement Late 2024 / Victorian Planning Approval: January 2026
Construction Start 2026
Phase 1 Go-Live 2027 / 2028
Full Buildout 2028–2031+ (Phased delivery across campus technical halls)

Investment Details

HeaderDetails
Total InvestmentEstimated A$2,000,000,000 AUD (~$1.35 Billion USD)
Funding NEXTDC Limited corporate capital expenditure (CapEx) allocation & institutional capital raisings