QTS & Lancium Hall County: $10B Texas Hyperscale Hub
Status: Under Development / Site Civil Works | Location: 465-acre Lancium Clean Campus site, Hall County, Texas, USA
Project Overview
Representing a joint mega-development between Blackstone-backed QTS Data Centers and energy technology firm Lancium, the $10 billion clean energy hyperscale campus in Hall County, Texas, introduces an innovative model for self-sufficient digital infrastructure. Spanning 465 acres near Turkey, Texas, the master-planned campus accommodates up to 11 individual data center buildings designed specifically to support high-density artificial intelligence models, deep learning training clusters, and massive parallel computing workloads. The defining aspect of the development is its integrated behind-the-meter energy and water strategy. Lancium and QTS are fully funding 100 percent of the required energy infrastructure improvements, relieving local municipal utility ratepayers of grid upgrade costs. Power delivery is fortified through on-site utility-scale solar generation paired with a high-capacity Battery Energy Storage System (BESS) to buffer grid operations and ensure uninterruptible compute availability. To protect regional water resources in West Texas, the campus utilizes closed-loop cooling systems that eliminate municipal water reliance. All operational water is sourced strictly from dedicated private on-site wells or trucked in from approved external suppliers, avoiding any draw on local municipal systems. The project serves as a major economic catalyst, creating up to 7,000 peak construction jobs and approximately 350 permanent operational roles. Upon completion, the Hall County campus will operate as a premier, islanded compute core for North American hyperscale AI deployment.
Quick Facts
| Field | Value |
| Project Name | QTS & Lancium Hall County: $10B Texas Hyperscale Hub |
| Location | 465-acre Lancium Clean Campus site, Hall County, Texas, USA |
| Status | Under Development / Site Civil Works |
| Commissioning | H1 2027 (Phase 1 Target Go-Live) |
| Total IT Load | 800 MW |
| Total Capacity | 1,000 MW (Multi-building gigawatt-scale master plan across 11 data center halls) |
| Tier Level | Tier III Compliant System Architecture |
| Project Type | Greenfield Self-Powered Hyperscale Cloud & AI Training Super-Campus |
City Profile
| Header | Details |
| City Name | Texas |
| Population | ~30.5 million (2025 est.) |
| Urban Agglomeration | ~27–28 million (major metro clusters combined) |
| City GDP | ~$2.4 trillion (2024 est., comparable to G7 economies) |
| Per Capita Income | ~$78,000 |
| City Tier | Tier 1 (Global Economic Powerhouse) |
| Key Strengths | Energy (oil, gas, renewables), Data Centers & AI Infrastructure, Technology (Austin hub), Logistics & Trade (US–Mexico corridor), Manufacturing, Business-friendly policies, Large land & power availability |
Companies Involved
| Header | Details |
| Developer / Operator | QTS Data Centers |
| Strategic Infrastructure Partner | Lancium Energy Technology & Texas ERCOT Transmission Grid Operators |
| Construction Contractor | DPR Construction & Mortenson Construction (Civil & Power Infrastructure) |
| MEP Engineering | QTS Global Design & Lancium Power Engineering Division |
| Network Connectivity | Redundant long-haul subterranean fiber trunks, carrier-neutral Meet-Me-Rooms, and direct dark fiber interlinks to Dallas-Fort Worth carrier exchange hubs. |
| Power Infrastructure | Islanded/behind-the-meter hybrid setup incorporating on-site solar resources, large-scale BESS, and dual high-voltage grid interconnects. |
Technical Specifications
| Header | Details |
| Power Capacity | 1,000 MW total utility and on-site generation capacity |
| UPS Redundancy | N+1 block-isolated static UPS systems paired with containerized emergency standby generator arrays and integrated battery energy storage (BESS). |
| Cooling System | Closed-loop chilled water and direct-to-chip liquid cooling manifolds engineered for high-density GPU racks without municipal water consumption. |
| Connectivity | Carrier-neutral design featuring four physically separated subterranean concrete fiber entry vaults and dual fortified Meet-Me-Rooms. |
| PUE Target | 1.15 |
| Energy Mix | High-penetration renewable mix backed by dedicated on-site solar, utility-scale BESS, and ERCOT clean power purchase agreements. |
Milestones
| Header | Details |
| Announcement | July 2026 |
| Construction Start | Q4 2026 (Site ground clearing and civil earthworks) |
| Phase 1 Go-Live | H1 2027 |
| Full Buildout | 2031 (Phased deployment across all 11 planned data center halls) |
Investment Details
| Header | Details |
| Total Investment | $10,000,000,000 USD |
| Funding | 100% developer and private equity funded via QTS (Blackstone) capital reserves and Lancium project financing |