Yondr Johor: 300MW Sedenak Tech Park AI Campus

Status: Under Construction (Phase 1 Substation Energized & Live)   |   Location: Sedenak Tech Park (STeP), Sedenak Technology Valley, Kulai, Johor, Malaysia


Project Overview

Yondr Group’s 300 MW Sedenak Tech Park campus in Johor, Malaysia, represents one of the largest hyperscale data center developments in Southeast Asia. Spanning 72.5 acres within the strategic Sedenak Technology Valley corridor, the multi-building campus was conceived as a primary computing alternative to power-constrained Singapore. By offering ultra-low latency interconnectivity across the Johore Strait, the campus provides global cloud providers and artificial intelligence platforms with high-density processing capacity The campus layout is built around modular, high-efficiency data halls designed to handle dense racks for AI model training and parallel processing arrays. Supported by a landmark $150 million financing package from the World Bank’s International Finance Corporation (IFC), the project serves as a key pillar in Malaysia's digital economic growth strategy. Power delivery is secured through a direct agreement with Tenaga Nasional Berhad (TNB) via its Green Lane Pathway initiative, which accelerated grid readiness and enabled the commissioning of a dedicated 275kV high-voltage main intake substation on-site. Sustainability and resource conservation are built directly into the facility design. The buildings integrate advanced closed-loop cooling systems that significantly reduce water usage compared to standard evaporative cooling systems, protecting regional water reserves. Combined with carrier-neutral dark fiber routes into Singapore, Kuala Lumpur, and broader pan-Asian cable networks, Yondr’s Johor campus functions as an essential, high-availability digital crossroads for regional cloud workloads and enterprise AI deployments across Asia-Pacific.


Quick Facts

FieldValue
Project NameYondr Johor: 300MW Sedenak Tech Park AI Campus
LocationSedenak Tech Park (STeP), Sedenak Technology Valley, Kulai, Johor, Malaysia
StatusUnder Construction (Phase 1 Substation Energized & Live)
CommissioningH2 2024 (Phase 1 Go-Live)
Total IT Load300 MW
Total Capacity300 MW (Master-planned across 72.5 acres of dedicated tech park footprint)
Tier LevelTier III Compliant System Standards
Project TypeGreenfield Hyperscale Cloud & AI Infrastructure Super-Campus

City Profile

HeaderDetails
City NameKulai, Johor
Populationsim 280,000 (Kulai District)
Urban AgglomerationPart of the larger Johor Bahru/Iskandar Malaysia economic zone.
City GDPKey contributor to Johor States economy, driven by industrial and tech parks.
Per Capita IncomeAbove national average due to proximity to Singapore and industrial development.
City TierKey Regional Hub / Emerging Hyperscale Gateway
Key StrengthsLand availability, government support (Digital Investment Office), proximity to Singapore, and robust power/fibre infrastructure.

Companies Involved

HeaderDetails
Developer / Operator Yondr Group
Strategic Infrastructure Partner Tenaga Nasional Berhad (TNB) & Johor Corporation (JCorp)
Construction Contractor Leading Regional EPC Prime Contractors & Civil Engineering Partners
MEP Engineering Yondr Global Engineering & Specialized APAC Mission-Critical MEP Consultants
Network Connectivity Redundant dark fiber routes into Singapore, cross-border terrestrial links, and direct connections to regional subsea landing stations.
Power Infrastructure Dedicated on-site 275kV high-voltage substation connected directly to Tenaga Nasional Berhad's (TNB) transmission grid.

Technical Specifications

HeaderDetails
Power Capacity300 MW gross utility allocation across all planned campus phases
UPS RedundancyN+1 block-redundant static UPS topology supported by containerized standby diesel generator arrays with on-site bulk fuel reserves.
Cooling System Closed-loop chilled water systems combined with direct-to-chip liquid cooling options to support high-density GPU racks.
Connectivity Carrier-neutral design featuring four physically separated subterranean concrete fiber entry vaults and dual Meet-Me-Rooms.
PUE Target 1.20
Energy Mix Integrated with TNB green energy initiatives and regional renewable energy purchase agreements.

Milestones

HeaderDetails
Announcement March 2022
Construction Start Q4 2022
Phase 1 Go-Live H2 2024 (Substation energized Q1 2024)
Full Buildout 2028 (Phased commissioning across multi-hall layout)

Investment Details

HeaderDetails
Total Investment$1,200,000,000 USD (Estimated full multi-phase development value)
Funding Corporate capital expenditure, equity lines, and $150M IFC World Bank loan facility