QTS Northumberland: 720MW UK Hyperscale AI Campus
Status: Under Construction (Enabling Works & Site Remediation Active) | Location: 133-acre (540,000 sqm) former Britishvolt site, Cambois, Northumberland NE24, UK
Project Overview
QTS Data Centers’ £10 billion ($13.5 billion) hyperscale campus in Cambois, Northumberland, represents one of the largest single-site data center investments in European history. Spanning 133 acres on the former industrial site of the Blyth Power Station, the master-planned development encompasses 10 state-of-the-art three-story data center buildings totaling over 5.8 million square feet (540,000 sqm) of computing space. Engineered specifically to support next-generation artificial intelligence workloads, deep learning model training, and European multi-cloud hosting, the facility reinforces the UK’s position as a primary European AI infrastructure hub. The development represents a major economic rebirth for North East England, replacing a stalled industrial battery factory scheme with long-term digital infrastructure. The site selection leverages direct access to high-voltage national grid capacity and subsea fiber routes while creating thousands of regional construction jobs and hundreds of permanent technical positions. The project has earned CITB National Skills Academy for Construction status, establishing local workforce training initiatives across Northumberland Sustainability is central to the campus master plan. The facility utilizes QTS’s proprietary water-free, closed-loop liquid cooling system that recirculates coolant to maintain optimal thermal thresholds for high-density GPU racks without consuming local municipal water. Powered by clean energy through offshore wind Power Purchase Agreements (PPAs) from the North Sea grid, the Northumberland campus operates as a zero-carbon, highly resilient compute core for cloud providers and AI enterprises across EMEA.
Quick Facts
| Field | Value |
| Project Name | QTS Northumberland: 720MW UK Hyperscale AI Campus |
| Location | 133-acre (540,000 sqm) former Britishvolt site, Cambois, Northumberland NE24, UK |
| Status | Under Construction (Enabling Works & Site Remediation Active) |
| Commissioning | H1 2028 (Phase 1 Target Go-Live) |
| Total IT Load | 600 MW |
| Total Capacity | 720 MW (Ten 3-story data halls delivering 72 MW each) |
| Tier Level | Tier III Compliant System Architecture |
| Project Type | Greenfield Hyperscale Cloud & Enterprise AI Compute Super-Campus |
City Profile
| Header | Details |
| City Name | Cambois |
| Population | Approximately 1,400 |
| Urban Agglomeration | Approximately 37,000 (Blyth urban area) |
| City GDP | Not officially reported (part of the North East England regional economy) |
| Per Capita Income | Not officially reported |
| City Tier | Tier 4 – Small coastal village with growing industrial significance |
| Key Strengths | Strategic location on the Northumberland coast |
Companies Involved
| Header | Details |
| Developer / Operator | QTS Data Centers |
| Strategic Infrastructure Partner | Blackstone & Northumberland County Council |
| Construction Contractor | Leading UK Mission-Critical Prime Contractors & Civil Engineering Partners |
| MEP Engineering | Corgan & QTS Global Infrastructure Design Division |
| Network Connectivity | Redundant subsea fiber landings (North Sea routes to Nordics & Europe), dark fiber links to London, and carrier-neutral Meet-Me-Rooms. |
| Power Infrastructure | Direct connection to National Grid’s high-voltage 400kV electricity transmission substation at Blyth. |
Technical Specifications
| Header | Details |
| Power Capacity | 720 MW total allocated utility grid capacity |
| UPS Redundancy | N+1 block-isolated static UPS modules backed by containerized emergency standby generator arrays with bulk fuel storage. |
| Cooling System | QTS water-free closed-loop cooling system paired with direct-to-chip liquid cooling manifolds for high-density AI clusters. |
| Connectivity | Carrier-neutral design featuring four subterranean concrete fiber entry vaults and dual fortified Meet-Me-Rooms. |
| PUE Target | 1.18 |
| Energy Mix | Matched 100% with renewable energy backed by regional UK offshore wind Power Purchase Agreements (PPAs). |
Milestones
| Header | Details |
| Announcement | April 2024 (Land Acquisition) |
| Construction Start | Late 2025 (Enabling and site preparation works) |
| Phase 1 Go-Live | H1 2028 (First two data center halls operational) |
| Full Buildout | 2035 (Phased completion across all 10 planned buildings) |
Investment Details
| Header | Details |
| Total Investment | £10,000,000,000 GBP ($13,500,000,000 USD) |
| Funding | Multi-billion-pound global infrastructure equity funds managed by Blackstone and QTS capital reserves |