atNorth ICE02 Keflavik Mega Data Center Sjónarhóll Reykjanesbær Iceland |
Sjónarhóll 6, 235 Reykjanesbær (Keflavik), Iceland |
Operational / Multi-Phase High-Density Expansion |
Operational & High-Density Expansion Phase |
80.0 MW Gross Power Allocation / 64.0 MW Critical IT Load |
|
|
atNorth NOR01 Data Center Campus: 350MW Sustainable Mega Hub in Haugaland, Norway |
Haugaland Business Park, 5570 Aksdal, Tysvær Municipality, Rogaland, Norway |
Active Multi-Phase Mega Campus Development |
Active Development / Under Construction |
350 MW Secured Critical IT Utility Allocation (Initial 120 MW) |
|
|
atNorth DEN01 Copenhagen AI Data Center Campus: 30MW Sustainable HPC Hub in Denmark |
Tonsbakken 12, 2740 Skovlunde / Ballerup, Greater Copenhagen, Denmark |
Operational Active Campus |
Fully Operational / Active HPC & AI Deployment |
30 MW Total Secured Utility Power Capacity Allocation |
|
|
atNorth HEL1 AI Data Center Helsinki Finland: Sustainable High-Density & AI Computing Hub |
Kuortaneenkatu 3, 00510 Helsinki, Finland |
Fully Operational / Ongoing High-Density AI Expansions |
Operational / Upgraded for AI & High-Density Workloads |
~1.5 MW Utility Supply Connection |
|
|
atNorth FIN02 Helsinki Expansion: 45MW High-Density AI & HPC Campus |
Sinimäentie 6, 02630 Espoo, Greater Helsinki Area, Finland |
Q3/Q4 2027 (Completion of 45 MW Expansion Extension) |
Active Construction Phase (5-Story Extension Underway) |
35 MW Critical IT Power Capacity / 45 MW Gross Substation Feed |
|
|
Solleftea atNorth 300MW High-Density Nordic AI Campus |
SWE04 Industrial Zone, Solleftea, Sweden |
Q4 2029 |
Under Construction (Phase 1 Framing) |
300 MW |
|
|
atNorth SWE04 Sollefteå AI Campus (300 MW) |
Sollefteå (Långsele) |
2031 |
Announced (Feb 24, 2026) |
300 MW Total Utility Capacity |
|