Digital Edge Manila NARRA1 AI Data Center Campus – 10 MW |
120 E Science Ave, Laguna Technopark, 4024 Biñan, Laguna, Philippines |
March 2023 (Operational across all 2,200 cabinet spaces) |
Fully Operational |
10 MW total site power allocation |
|
|
Digital Edge Navi Mumbai BOM1 Data Center |
Babasaheb Ambedkar Road, Ghansoli / Thane-Belapur Belt, Navi Mumbai, Maharashtra 400701, India |
Early 2027 |
Under Construction Phase |
50.0 MW Gross Power Allocation / 40.0 MW Critical IT Power Load |
|
|
Digital Edge CGK1 Data Center Cikarang GIIC Bekasi Greater Jakarta Indonesia |
Greenland International Industrial Center (GIIC), Cikarang, Bekasi 17530, Indonesia |
Q2 2027 (Campus Phase 1 Three-Building Buildout) |
Under Construction (Topped Out Q2 2026) |
125 MW Gross Utility Power Capacity (CGK1 Building) |
|
|
Digital Edge Ansan SEL2 AI Data Center: Greater Seoul South Korea Specs |
Seonggok-dong, Danwon-gu, Ansan-si, Gyeonggi-do, Greater Seoul, South Korea |
Multi-Phase 120 MW Master Campus Delivery |
Under Construction / Commissioning Phase |
~140+ MVA Dedicated Substation Grid Capacity Allocation |
|
|
Digital Edge Tokyo Data Center Campus (TYO Metro Facilities) |
3-chōme-1-1 Sekiguchi, Bunkyo City, Tokyo 112-0014, Japan |
Fully Operational Active Multi-Site Campus |
Fully Operational Multi-Site Metro Campus |
~45.0+ MW Total Combined Utility Power Allocation |
|
|
Digital Edge Seoul Bupyeong Campus: 96MW AI-Ready Data Center in South Korea |
Bupyeong-gu, Incheon, Greater Seoul Metropolitan Area, South Korea |
Active Multi-Building Campus Expansion (SEL3 RFS Q4 2027) |
Phase 1 Operational (SEL2) / Phase 2 Under Construction (SEL3) |
96 MW Secured Utility Power Allocation |
|
|
Digital Edge Jakarta H1: $4.5B AI-Centric Megacampus |
Cikarang Digital Zone, Greater Jakarta, Indonesia |
Q2 2032 |
Under Construction (Groundbroken Q2 2026) |
450 MW ultimate secured power allocation from the national grid |
|
|
Digital Edge Palava 270MW Hyperscale Data Center Campus Mumbai |
30-acre dedicated land parcel within the Green Integrated Data Centre Park, Palava |
NA |
Announced / Initial Planning & Site Preparation |
Scalable multi-stage power blocks engineered to deliver up to 270MW of total capability at full buildout. |
|
|
Digital Edge SEL3: $582M 60MW Incheon AI Hyperscale Hub |
422 Cheongcheon-dong, Bupyeong-gu, Incheon, Greater Seoul, South Korea |
2027 - Q4 |
Active / Under Heavy Structural Fabrication (Tracking June 2026) |
60 MW net critical IT capacity dedicated to SEL3, supporting advanced rack densities exceeding 10kW per cabinet |
|
|
Digital Edge SEL2: 36MW Incheon AI-Ready Hyperscale Hub |
Cheongcheon-dong, Bupyeong-gu, Incheon, Greater Seoul, South Korea |
2024 - Q4 |
Active / Operational & Fully Leased (Tracking June 2026) |
36 MW net critical IT capacity optimized for high-power density applications |
|
|
Digital Edge SEL5: 60MW Ansan AI Hyperscale Project |
Sihwa National Industrial Complex, Seonggok-dong, Danwon-gu, Ansan, Gyeonggi Province, South Korea |
2029 - Q4 |
Active / Secured Land & Early Civil Design Planning (Tracking June 2026) |
60 MW net critical IT capacity supported by a dedicated 90 MVA utility allocation built to mitigate localized cluster spikes |
|
|
EEC Hyperscale Data Center Campus Digital Edge |
Eastern Economic Corridor (EEC), Chon Buri Province, Thailand |
The partnership aims to develop multiple next-generation hyperscale and AI-ready data center campuses across Thailand. |
Under Construction (Greenfield Project) |
100 MW (IT Load for the flagship campus). |
|
|
Digital Edge CGK Campus |
GIIC Industrial Estate, Kota Deltamas, Bekasi |
Q2 2027 |
Announced / Phase 1 Under Construction |
500 MW (Current Phase) / 1,000 MW (Full Buildout) |
|