CyrusOne DFW10: $1.2B Co-Located Hyperscale Campus |
557 County Rd 3610, Whitney, TX 76692 |
2027–2028 (Phased 5-Building Rollout) |
Under Construction (Topping Out Milestone: March 2026) |
400 MW Maximum Dedicated Delivery (190MW Initial Phase PPA) |
|
|
CyrusOne MIL1: 27MW Eco-Sovereign Data Center Milan |
Via delle Regioni, Segrate, Lombardy |
Late 2028 |
Under Construction (Groundbreaking March 25, 2026) |
35 MW Total Utility Connection |
|
|
CyrusOne AMS1: 54MW Hyperscale Amsterdam-Gateway Campus |
Linieweg 1, 1165 AA Halfweg (Haarlemmerliede) |
Ongoing / 2025-2026 |
Live / Operational (Active AI-Density Modernization) |
54 MW IT Load (27 MW Dedicated per Building) |
|
|
CyrusOne Freestone: 760MW AI-Ready Powered Land Texas |
Freestone County (near Fairfield, TX) |
2027 |
Active Development / Construction Prep |
760 MW Total (Two 380MW Phases) |
|
|
CyrusOne FRA7 (Frankfurt Westside) |
Griesheim (West of Frankfurt), Germany |
Expected completion in phases over several years. |
Under Construction |
126 MW |
|