Equinix xScale Paris Hyperscale Data Center Expansion (23MW) |
114 Rue Ambroise Croizat, 93200 Saint-Denis |
February 2025 (PA13x fully operational and pre-leased) |
Operational |
23 MW total across primary xScale modules (expandable via future phases) |
|
|
Equinix PA10: 15MW Highly Connected Eco-Hub Paris |
114 Rue Ambroise Croizat, 93200 Saint-Denis |
2025–2026 |
Live / Operational (Active AI Liquid-Cooling Upgrades) |
15 MW Total Utility Connection |
|
|
Equinix AM5: 13MW High-Density Amsterdam South East Hub |
Amsterdam |
Continuous Expansion / 2026 AI Infrastructure Upgrades |
Live / Operational (Active AI-Ready Upgrades) |
13 MW Total Utility Supply |
|
|
Equinix AM11 International Business Exchange™ |
Lemelerbergweg 28, 1101 AH Amsterdam |
2026 / early 2027 |
Operational / Continuous Interconnection Optimization (May 2026) |
9.0 MW |
|
|
Equinix KL2 Kuala Lumpur: 1.4MW High-Density Interconnection Hub |
Cyberjaya Tech Hub, Kuala Lumpur |
2028 (Estimated) |
Operational / Phase 1 Complete |
1.4 MW (Phase 1) / Scalable |
|
|
Equinix MD5 Madrid: New Q2 2026 Launch for Southern Europe AI |
Madrid Metropolitan Area |
NA |
In Development / Targeted Q2 2026 Opening |
Multi-MW Scalable |
|
|
Equinix SY5: 54MW Sydney AI-Ready Hyperscale IBX |
200 Bourke Road, Alexandria, AU |
May 2026 Completion (Final Phase cabinets live). |
Operational / Phase 3 AI-Density Upgrade (May 2026) |
54.0 MW |
|
|
Oracle Indiana: $12B 1GW AI Giga-Campus & OpenAI Partnership |
Indiana Enterprise Center |
Projected Completion: 2028 |
Active Construction / Phase 1 Fit-out (May 2026) |
1,000.0 MW (1.0 GW) |
|
|
Equinix TR7: 16.6 MVA Brampton Hyperscale Hub & Toronto IBX |
1895 Williams Parkway East, Brampton |
Continuous incremental expansion through 2026 |
Operational / Continuous Expansion (May 2026) |
16.6 MVA (Total) |
|
|
Equinix SP7: $110M AI-Ready São Paulo IBX® Facility |
-23.589496 |
2027 |
Under Construction / Active Fit-out (April 2026) |
20.0 MW |
|
|
Equinix MB3 International Business Exchange™ (IBX®) |
Mumbai (Chandivali, Powai), Maharashtra |
2028 |
Operational / Phase 1 Live (April 2026) |
~25.0 MW (Full Build-out potential) |
|
|
Equinix SY10x Sydney: 28MW Hyperscale AI Data Center Hub |
10 Grand Avenue, Rosehill, Sydney |
2027 |
Implementation / Commissioning (April 2026) |
28.0 MW |
|
|
Equinix SY9x Sydney: 28MW Hyperscale AI Data Center |
sydney NSW 2142, Australia |
2026 (28MW) |
Operational / Phase 2 Expansion (April 2026) |
28.0 MW (Fully Built-Out) |
|
|
Equinix SY8 Sydney: 4MW High-Density AI Peering Hub |
74 Mentmore Avenue, Rosebery NSW 2018, Australia |
2026 (Current optimized capacity) |
Operational / High-Density Upgrade (April 2026) |
4.0 MW |
|
|
Equinix CA1 Canberra: Premium Australian Government Hub |
Equinix CA1, 51 Dacre Street, Mitchell ACT 2911, Australia |
2026 (Current optimized state) |
Operational / AI-Ready Upgrade (April 2026) |
~3 MW (Phase 1 Aggregate) |
|
|
Equinix SY6 Sydney: 4MW Scalable AI & GovDC Infrastructure |
8-14 Egerton Street, Silverwater NSW 2128, Australia |
2026 (Current modular capacity) |
Operational / High-Density Expansion (April 2026) |
4.0 MW |
|
|
Equinix SY1 Sydney: 7MW High-Connectivity AI Edge Campus |
Sydney (Mascot), NSW |
Completed / Optimized for 2026 AI standards |
Operational / High-Density Upgrade (April 2026) |
7.0 MW |
|
|
Equinix DA11 International Business Exchange™ (IBX®) Data Center |
1990 North Stemmons Freeway, Dallas, TX 75207, USA |
Complete (Total colocation space $\approx 144,000 \text{ sq ft}$ with $\approx 3,850$ cabinets) |
Operational with phased expansion complete (Fully Built Out) |
$8 \times 3,000 \text{ kW}$ diesel generators |
|
|
Equinix DA12 Dallas Data Center - 372,517 SQ FT Facility |
Dallas |
March 2028 |
Under Construction (Groundbreaking) |
Est. 40MW+ Critical IT Load |
|
|
Equinix SG6: $260M 20MW AI-Ready Data Center Singapore |
Jalan Tukang, Jurong (Near SG5 Tanjong Kling), Singapore |
2027 |
Under Construction (Awarded Mar 2026) |
20 MW |
|
|
Equinix Hertfordshire Campus (DC01UK) |
Hertfordshire, UK |
2029 |
Under Development / Construction Phase |
250 MW IT Load |
|
|
Equinix Lelystad AI Data Center (AMS10) |
Flevokust Haven, Lelystad, Netherlands |
2030 |
Planning / Pre-Construction |
150 MW Dedicated Site Power |
|
|
Equinix SG4 IBX Data Center |
7 Tai Seng Drive, Singapore, Singapore 535218 |
Ongoing phases, rapidly reached 4,000 cabinet capacity. |
Operational (Completed Phase I - Continual Efficiency Upgrades) |
$\approx 4.5\text{ kVA}$ per cabinet (Specified density) |
|