Portugal’s Start Campus Launches SIN01, Advancing a 1.2GW Gigascale Vision |
Sines, Portugal (Atlantic Coast) |
2030+ |
Operational (First Building, SIN01) |
1.2 GW (Secured Total Grid Capacity) |
|
|
AWS European Cloud Region for Data Sovereignty |
Germany |
Initial launch by late 2026; full investment deployed by 2029 |
Confirmed / Under Construction |
Significant capacity as part of the total €7.8B investment in the region |
|
|
Start Campus SINES01 | Next-Generation Data Center Campus in Sines, Portugal |
ZILS (Sines Industrial and Logistics Zone), Sines, Portugal |
2028 - 2030 |
Under Construction / Phase 1 Operational |
1.2 GW |
|
|
WBS Power / Prime Capital Hyperscale Campus | Co-Located Project Jupiter AI Hub |
Former military airfield, Brandenburg, Germany |
Phased development |
Pre-Construction/Planning (Targeting 2026/2027 Start) |
500 MW |
|
|
DUB20 Hyperscale Campus |
Arklow, County Wicklow, Ireland (Greater Dublin Area) |
Target 2028-2030 |
Under Construction (Initial Phase Piling & Shell) |
90 MW |
|
|
Apto Data Center Campus in Lacchiarella |
Lacchiarella (Milan Metropolitan Area), Italy |
N/A |
Announced / Early Development Phase |
300 MW |
|
|
Global Switch London East GS2 | High-Density Colocation & Infrastructure Expansion |
London Docklands (East India Dock), United Kingdom |
Expected completion in the late 2020s. |
Upgrade/Reconfiguration - Underway |
74 MW |
|
|
Madrid Sur Campus by Echelon Iberdrola Digital Infra |
Madrid Sur Area, Spain (South of Madrid) |
N/A (Potential for 700 MW+ across the JV's secured portfolio) |
Planning / Pre-Construction (Secured Power Connection) |
230 MW |
|
|
Microsoft DUB14 Dublin Data Center | Next-Gen Hyperscale Compute Campus in Ireland |
Grange Castle Business Park, Clondalkin, Dublin, Ireland |
Projected over 5-7 years |
Under Construction / Phased Buildout |
240 MW |
|
|
CyrusOne FRA7 Frankfurt Westside Campus |
Griesheim (West of Frankfurt), Germany |
Expected completion in phases over several years. |
Under Construction |
126 MW |
|
|
SINES 4.0 | Next-Generation Data Center Campus in Sines, Portugal |
Sines, Portugal (ZILS - Sines Industrial and Logistics Area) |
Estimated by 2030-2035 (phased) |
Under Construction/Ongoing Phased Development |
Up to 1.2 GW |
|
|
Brookfield AI Data Center Campus Development |
Strängnäs (Stockholm Metro Area), Sweden |
Est. 2035 – 2040 (10-15 year construction timeline) |
Announced / Long-term Development |
Initial planned expansion from 300 MW to 750 MW |
|
|
VIRTUS Wustermark Megacampus | Next-Generation Colocation & Digital Infrastructure Campus |
Wustermark (30 km west of Berlin), Germany |
Est. 2028-2030 |
Under Construction / Phased Development |
Up to 300 MW (Across 9 data center buildings) |
|
|
Microsoft Middenmeer Campus | High-Performance AI & Cloud Infrastructure Expansion (AMS13/14) |
Middenmeer, Hollands Kroon (North Holland), Netherlands |
Long-term development |
Announced / Under Phased Construction |
Significant multi-MW capacity added over 50 hectares of new land |
|
|
Fossefall Data Center | AI Factory for Scalable Cloud & GPU Workloads |
Fyresdal, Vestfold and Telemark County, Norway |
Phased towards 500 MW goal by 2030 across the Nordic region. |
Announced / Acquisition Complete (Late 2025) Commissioning Commissioning Phased conversion, initial AI capacity launch expected H |
Initial 5.5 MW (Existing reserved capacity) |
|
|
Google Data Center Expansion, Saint-Ghislain Campus |
Saint-Ghislain, Hainaut Province, Belgium |
Continuous phased expansion over the next decade. |
Announced / Active Expansion (Investment committed late 2025) |
Significant increase from current load; scaled to support multi-phase gigawatt-scale AI requirements. |
|
|
Amsterdam Hyperscale Campus |
Greater Amsterdam Region, Netherlands |
To be determined (Likely multi-year development) |
Announced / Pre-Construction (Lease Secured) |
Up to €1 Billion in construction investment; Hyperscale scale, multi-megawatt IT load. |
|
|
Frankfurt Hyperscale Campus Colt DCS 4 & 5 |
Rhine-Main Region, Frankfurt, Germany |
TBC |
Announced / Land Secured & Power Contracts Signed |
63 MW (Total IT Load) |
|
|
Vantage CWL1 Cardiff | Next-Generation Colocation & Digital Infrastructure Campus |
Celtic Way, Newport, South Wales, UK |
Estimated completion of all three buildings by 2026-2027 |
Partially Operational / Expanding |
148MW+ (Upgradeable) |
|
|
Equinix Lelystad AI Data Center (AMS10) |
Flevokust Haven, Lelystad, Netherlands |
2030 |
Planning / Pre-Construction |
150 MW Dedicated Site Power |
|
|
QuantumBasel Tempo Hub | IonQ Quantum Computing & Data Science Platform |
uptownBasel Campus, Arlesheim/Basel, Switzerland |
2029 |
Active Expansion / Technology Integration |
Scalable Hub (Quantum systems are high-efficiency) |
|
|
Goodman GEDCDP | European Data Centre Development & Investment Partnership |
Frankfurt (Germany), Amsterdam (Netherlands), Paris (France) |
2030 |
Announced / Pre-construction |
435 MW Total Portfolio |
|
|
AMS11 Amsterdam Data Tower Campus by Digital Realty |
Science Park, Amsterdam, Netherlands |
Q3 2026 |
Live / Operational |
27 MW IT Capacity |
|
|
Sesterce "Rhône-Alps" AI Mega-Campus |
Lyon-Valence Logistics Hub, Auvergne-Rhône-Alpes |
2032 |
Latest Launch (Active Execution Phase - Jan 2026) |
1 GW (Initial Execution) |
|
|
Hertfordshire Campus Equinix DC01UK |
Hertfordshire, UK |
2029 |
Under Development / Construction Phase |
250 MW IT Load |
|
|
Villasequilla AI Campus | High-Performance AI Compute & Connectivity Facility |
Villasequilla, Spain |
2029 |
Approved / Ready-to-Build (RTB) |
600 MW IT Load |
|
|
Digital Realty FRA18: 16MW AI-Ready Heritage Facility |
Frankfurt |
Estimated late 2027 |
Phase 1 Live (Operational) |
16 MW Total |
|
|
DayOne Nurmijärvi: 300MW Renewable AI Campus |
Nurmijärvi, Finland |
2030 |
Phase 1 Groundbreaking / Early Construction |
300 MW (Total Campus Buildout) |
|
|
Mediterra Barcelona: 12MW AI-Ready Edge-Hyperscale Hub |
Strategic site in Catalonia, near Barcelona |
2029 |
Launched / Site Acquired (Feb 20, 2026) |
Secured 12 MW |
|
|
Osae-NFU 250MW AI Data Center Bordeaux France |
Former Industrial Site, Bordeaux Metropole |
2029 |
Groundbreaking (Today) |
250 MW IT Load |
|
|
Digital Realty FRA20: 16MW AI-Ready Hyper-Scale Frankfurt |
Digital Park Fechenheim, Frankfurt |
Estimated 2028–2029 (Total Campus) |
Under Construction (Phase 1 Groundbreaking) |
16 MW (IT Load) |
|
|
Google Skien Norway: 240MW Hyperscale AI-Ready Data Center |
Skådalsvegen, Skien, Telemark, Norway |
2030 (Planned 840 MW) |
Live / Commissioning |
240 MW |
|
|
atNorth SWE04 Sollefteå AI Campus (300 MW) |
Sollefteå (Långsele) |
2031 |
Announced (Feb 24, 2026) |
300 MW Total Utility Capacity |
|
|
AWS Aragon Expansion: 33.7B Euro AI & Cloud Infrastructure |
Zaragoza, Multi-site: Zaragoza, Huesca, and Teruel (Aragon Region) |
2030 |
Announced / Under Expansion |
Total regional capacity projected at 1 GW+ by full buildout |
|
|
DT-NVIDIA AI Factory Munich: €1B 10,000 Blackwell GPU Hub |
Munich (Refurbished Industrial Site) |
2028 |
Go-Live: March 4, 2026 |
10,000 NVIDIA Blackwell GPUs (Initial phase) |
|
|
Google Waltham Cross: $1B AI Data Centre Hertfordshire UK |
, Waltham Cross, Hertfordshire |
2026 |
Operational (Inaugurated Sept 2025) |
Estimated 100 MW Utility Feed |
|
|
Google Dietzenbach: €5.5B AI Data Center & Heat Recovery Germany |
Dietzenbach (near Frankfurt), Hesse |
2029 |
Under Construction / Groundwork (March 2026) |
Part of a regional 4-GW-ready German grid strategy. |
|
|
Project Lusitanus Mérida: €2.8B AI Data Center FRV Spain |
Mérida (Extremadura) |
2029 |
Under Construction / Phase 1 Foundations (March 2026) |
1,000 MW (1 GW) Target |
|
|
Nostrum Evergreen Badajoz: €1.9B 500MW AI Data Center Spain |
Badajoz |
2029 (for 500MW) |
Permitting / Pre-Construction (March 2026) |
500 MW |
|
|
Microsoft Italy Project Raven | Next-Gen 800MW AI & Data Center Platform |
Lombardy and Lazio, Milan |
2027 |
Operational / Rapid Scaling Phase (March 2026) |
800 MW |
|
|
Newport Wales Data Centre | Microsoft £2.5B AI-Ready Hyperscale Campus (200MW) |
Newport, Wales |
2028 |
Under Construction / Fit-out (March 2026) |
200 MW |
|
|
Google Netherlands Winschoten | High-Performance AI & Hyperscale Cloud Hub |
Winschoten (Municipality of Oldambt), Groningen |
2026 (Active Scaling) |
Operational (Opened November 18, 2025) |
~200 MW (Phase 1) |
|
|
Lappeenranta AI Factory | Nebius 310MW Hyperscale Liquid-Cooling Infrastructure |
Lappeenranta |
2028 |
Announced / Pre-Construction (March 31, 2026) |
310 MW |
|
|
Stargate Norway Narvik | $1B 520MW AI Gigafactory |
Narvik (Kvandal), Nordland |
2028 |
Under Construction / Initial Phase (April 2026) |
520 MW |
|
|
Digital Realty FRA32 Frankfurt: 9MW AI-Ready Data Center |
Frankfurt am Main |
Operational (Ongoing high-density retrofits) |
Operational / High-Density Upgrade (April 2026) |
9.0 MW |
|
|
Google Azores Nuvem & Sol | 10MW AI-Ready Subsea Connectivity Data Center |
Tecnoparque da Lagoa, São Miguel, Azores |
Q1 2027 |
Under Construction (April 2026) |
10 MW |
|
|
Digital Realty PAR12 Paris AI & Connectivity Hub |
16 Avenue Joseph Froelicher, 77600 Ferrières-en-Brie, France |
Operational |
Operational / High-Density Optimized (April 2026) |
20.0 MW |
|
|
Paris Digital Park | Next-Generation 130MW Hyperscale AI Compute Campus |
12-14 Rue de la Gare, 93120 La Courneuve, France |
2026 (Final capacity tranches) |
Operational / Phased Expansion (April 2026) |
130.0 MW |
|
|
Digital Realty Marseille MRS5 River-Cooled AI Hub |
Port of Marseille Fos, Marseille, France |
2027 |
Under Construction (April 2026) |
14.0 MW |
|
|
London III West London Data Center | 56MW Hyperscale AI & Cloud Infrastructure Hub |
Digital Park, Crawley, UK |
2028 |
Under Construction / Phased Expansion (April 2026) |
56.0 MW |
|
|
Prime Finland: €6B Järvenpää AI-Ready 550MW Campus |
Vähänummi Industrial Area, Järvenpää |
2031 |
EIA Phase / Pre-Development (April 2026) |
550 MW |
|
|
Vantage BER1 Brandenburg | 56MW Hyperscale AI & Cloud Infrastructure Hub |
25-Acre Campus within Brandenburg Park |
2026 |
Operational / Active Phase 2 & 3 Expansion (April 2026) |
56.0 MW |
|
|
Google Kronstorf AI Data Center |
Business Park Kronstorf |
2029 |
Under Construction (Groundbreaking) |
150 MW IT Load |
|
|
Digital Realty ROM1 Rome |
Rome West |
2029 |
Under Construction (Phase 1) |
120 MW Total IT Load |
|
|
Pantheon AI Topusko |
Zagreb |
2032 |
Announced / Permitting |
500 MW IT Load |
|
|
Nexus-1 | 100MW Distributed AI Cloud & High-Performance Compute Hub |
Distributed across Southern France |
2028 (1,000 Units Worldwide) |
Groundbreaking / Launch Phase |
100 MW (First 100 Units) |
|
|
Equinix MD5 Madrid | Next-Gen AI Data Center Launching Q2 2026 in Southern Europe |
Madrid Metropolitan Area |
NA |
In Development / Targeted Q2 2026 Opening |
Multi-MW Scalable |
|
|
Pangea 5 Supercomputer | €100M AI Compute & Sustainable Energy Infrastructure Hub |
Technical Center (CSTJF) pau |
2027 |
Project Announced / Design Phase (May 6, 2026) |
Scalable High-Density (HPC Optimized) |
|
|
TikTok Lahti | €1 Billion AI-Ready Expansion for European Data Sovereignty |
Lahti, Finland |
H2 2027 |
Phase 1 Planning / Tenant Agreement Signed (May 2026) |
128.0 MW (Full Build) |
|
|
Microsoft Centurion Spain: 300MW Aragon Hyperscale AI Region |
Centrovía Industrial Park, La Muela (Zaragoza) |
2029 (Projected) |
Phase 1 Commissioning / Active Buildout |
300 MW (Campus Total) |
|
|
Maincubes BER2: 186MW AI-Ready Hyperscale Campus Berlin |
Luckenwalde, South of Berlin |
Late 2027 |
Under Construction (Phase 2 Groundbreaking May 2026) |
186 MW Total Utility Power |
|
|
Transatlantic Innovation Campus: 500MW AI Hub Croatia |
Dugopolje |
2030 |
Under Construction (Announced May 2026) |
500 MW Total Utility Power |
|
|
Equinix AM11 International Business Exchange™ |
Lemelerbergweg 28, 1101 AH Amsterdam |
2026 / early 2027 |
Operational / Continuous Interconnection Optimization (May 2026) |
9.0 MW |
|
|
Equinix AM5: 13MW High-Density Amsterdam South East Hub |
Amsterdam |
Continuous Expansion / 2026 AI Infrastructure Upgrades |
Live / Operational (Active AI-Ready Upgrades) |
13 MW Total Utility Supply |
|
|
CyrusOne MIL1: 27MW Eco-Sovereign Data Center Milan |
Via delle Regioni, Segrate, Lombardy |
Late 2028 |
Under Construction (Groundbreaking March 25, 2026) |
35 MW Total Utility Connection |
|
|
CyrusOne AMS1: 54MW Hyperscale Amsterdam-Gateway Campus |
Linieweg 1, 1165 AA Halfweg (Haarlemmerliede) |
Ongoing / 2025-2026 |
Live / Operational (Active AI-Density Modernization) |
54 MW IT Load (27 MW Dedicated per Building) |
|
|
NTT Amsterdam 1: 40MW High-Density Network Gateway |
Aviolanda 1, 1437 Rozenburg |
2025–2026 |
Live / Operational (Active AI-Density Modernization) |
40 MW Total White Space Capacity |
|
|
Equinix PA10: 15MW Highly Connected Eco-Hub Paris |
114 Rue Ambroise Croizat, 93200 Saint-Denis |
2025–2026 |
Live / Operational (Active AI Liquid-Cooling Upgrades) |
15 MW Total Utility Connection |
|
|
Digital Realty BCN1: 14MW Mediterranean Interconnection Gateway |
Sant Adrià de Besòs Innovation Area, Barcelona, Catalonia |
May 18, 2026 |
Live / Operational (Launched May 18, 2026) |
14 MW Planned IT White Space Load |
|
|
Project Monet: €2.2B High-Density Hyperscale AI Campus |
Île-de-France Corridor |
Late 2027 |
Approved / Pre-Construction Planning (Siting Finalized May 2026) |
360 MW Maximum Allocated Site Power Envelope |
|
|
Yondr London Slough Building 3: 40MW Hyperscale Data Center |
Slough SL2 5EJ, United Kingdom |
May 2026 (Complete 3-Building Campus Operational) |
Operational / Ready for Service (Achieved May 7, 2026) |
100 MW+ Ultimate Combined Campus Substation Grid Allocation |
|
|
Vantage Cardiff CWL12 |
The Celtic Way Glasgow, UK |
Estimated 2031 |
Planned / Site Infrastructure Under Development |
120 MW maximum expansion capacity |
|
|
Mistral AI EcoDataCenter 150MW Sustainable Sweden AI Campus |
Falun, Sweden |
Estimated 2029 |
Under Construction |
150 MW maximum allocated grid capacity |
|
|
Málaga Digital Gateway 45MW Tier III Andalusian Data Center |
Andalucía Tech Park District, Spain |
Estimated 2030 |
Planning & Site Acquisition Approved |
45 MW gross facility footprint capacity |
|
|
EdgeConneX Italy Hyperscale Expansion |
Milan Technology Hub, Italy |
Comprehensive portfolio development and final phase completions scheduled to scale through 2031 |
Active Development Phase |
300 MW cumulative gross utility power allocation across three core deployment sites |
|
|
Ark Data Centers Barcelona Project Montjuic 45 MW Investment |
La Maquinista, Barcelona, Spain |
Sequential multi-floor modular expansion phases projected to reach full capacity by 2031 |
Active Engineering & Permitting Phase |
45 MW gross electrical capacity delivered via independent high-voltage utility lines |
|
|
Equinix xScale Paris Hyperscale Data Center Expansion (23MW) |
114 Rue Ambroise Croizat, 93200 Saint-Denis |
February 2025 (PA13x fully operational and pre-leased) |
Operational |
23 MW total across primary xScale modules (expandable via future phases) |
|
|
Frankfurt Central IV Hyperscale Data Center 186MW Campus |
Frankfurt, EU |
Q4 2028 |
Under Construction |
186 MW Net IT Capacity |
|
|
Civicos Networking: Roubaix Cloud Node |
1 Rue Kellermann, 59100 Roubaix, France |
Seamlessly integrated into a multi-facility cluster including sister nodes in Tenerife, Lanzarote, and Madrid |
Active / Operational Cloud Services Node |
Up to 1.6 MW total localized operational power threshold, with densities scaling from 1.2 kW up to 10 kW per rack depending on hardware layout |
|
|
EXA Mareuil sur Ay |
Mareuil-sur-Ay (Marne) |
Continuous "build-to-suit" internal data hall adaptations executing based on carrier and enterprise interconnect requirements |
Active / Fully Operational Core Network & Colocation Node |
Scalable multi-megawatt allocation providing high-reliability power feeds to partial, full, and multi-cabinet cage deployments |
|
|
Digital Realty Paris 13: PAR13 Hyperscale |
14 Rue de l'Orme à Moineaux, 91940 Les Ulis, France |
Continuous internal space optimizations and dense cooling retrofits tracking completely active through June 2026 |
Active / Operational |
15 MW gross utility transformer capacity supporting high-density configurations |
|
|
SoftBank Dunkirk AI Campus: 3.1GW Sovereign Mega-Hub |
Port of Dunkirk (Loon-Plage), Hauts-de-France Region, France |
Sequential regional campus completions across Dunkirk, Bosquel, and Bouchain tracking for full delivery by 2031 |
Active / Pre-Construction & Fast-Track Planning Phase (Announced June 2026) |
3,100 MW regional allocation delivered via dedicated on-site 400 kV extra-high-voltage substations |
|
|
Yondr Frankfurt FRA02: 40MW Hyperscale Bischofsheim Node |
Industrial Zone Am Schindberg, 65474 Bischofsheim, Hesse, Germany |
Continuous modular server hall fit-outs pacing sequentially across the multi-story footprint through 2029 |
Active / Under Heavy Structural Construction (Tracking June 2026) |
40 MW gross utility line allocation feeding high-density rows scaling past 25 kW per rack |
|
|
NTT London LON3: 24MW High-Density Dagenham AI Campus |
Yew Tree Ave, Dagenham RM10 7FZ, United Kingdom |
Continuous modular data hall expansion scaling sequentially across the campus footprint through 2029 |
Active / Under Heavy Structural Construction (Tracking June 2026) |
24 MW gross utility capacity delivered via fully redundant, dedicated on-site transformer blocks |
|
|
Data4 Escaudain: €5B 700MW Hyperscale Campus in France |
Former Parc des Soufflantes Industrial Redevelopment Site, Escaudain, Northern France |
2032 - Q4 |
Active / Master Planning & Environmental Site Permitting Phase (Tracking June 2026) |
700 MW gross ultimate site power allocation engineered to sustain high-density AI server clusters and next-generation compute configurations |
|
|
Equinix MD6 Madrid 3.5MW Colocation Campus |
Calle de la Pedriza, 12, 28108 Alcobendas, Madrid, Spain |
Q2 2027 (Final BME Matching Engine Migration) |
Operational |
3.5 MW Marketed Power |
|
|
Milan CyrusOne MIL2 54MW Hyperscale Data Center |
Via Raffaele Rubattino no. 90, 20134, Milan, Italy |
Q4 2028 |
Under Development / Planning |
90 MVA Dual Active High-Voltage Supply Allocation |
|
|
London Kao Data KL03 40MW AI-Ready Data Center |
Park Royal, West London, UK |
Q4 2029 |
Under Development / Planning |
40 MW Dedicated Critical Power Allocation |
|
|
Digital Reef Havering 600MW AI Tech Campus London |
499-Acre Fen Lane & North Ockendon Site, Havering Green Belt Corridor, East London |
Incremental 12-building campus expansions rolling out sequentially across a 5-to-10-year horizon |
Under Construction |
200MW Phase 1 configuration (scalable up to 600MW full site allocation) |
|
|
Google Horndal: New 150MW Air-Cooled Sweden Data Center |
Greenfield industrial zone, Horndal, Avesta Municipality, Dalarna County, Sweden |
Projected 2030 |
Groundbreaking Achieved / Active Civil Construction (June 2, 2026) |
150.0 MW Phase 1 Baseline Capacity |
|
|
Bucharest ClusterPower 800MW Off-Grid AI Infrastructure Factory |
Strada Viitorului nr.2, 207405 Mlecănești, Romania |
Q2 2030 |
Under Construction (Phase 1 Fast-Track) |
800 MW |
|
|
Cambois Northumberland 720MW Massive Hyperscale Campus |
Northumberland , england |
Q4 2031 |
Under Construction (Enabling Works / Phase 1) |
720 MW |
|
|
Solleftea atNorth 300MW High-Density Nordic AI Campus |
SWE04 Industrial Zone, Solleftea, Sweden |
Q4 2029 |
Under Construction (Phase 1 Framing) |
300 MW |
|
|
Paris Verne 500MW Sovereign AI High Performance Campus |
36-43 Great Sutton St, London EC1V 0AB, United Kingdom |
Q4 2030 |
Under Construction (Phase 1 Groundwork) |
500 MW |
|
|
Project Boreas: 800MW Nordic Hyperscale Campus |
Northern Sweden (Nordic Region) |
2031 |
Groundbroken / Under Construction |
800 MW dedicated capacity |
|
|
Granada: €3B Alto Infrastructure SP01 AI & HPC Campus Spain |
Escúzar, Granada (Andalusia) |
2029 |
Groundbreaking Initiated |
70 MW total master-planned power footprint (50 MW dedicated IT load) |
|
|
Philippsburg: 707MW Project Engrida Hyperscale Data Center Campus Germany |
Former Goodyear Tire Factory & Decommissioned Philippsburg Nuclear Power Plant (KKP Site) |
2032+ |
Pre-Construction / Municipal Council Preliminary Approval Received |
707 MW total grid capacity allocation (Supporting an estimated ~550 MW of continuous critical IT infrastructure) |
|
|
Vantage Frankfurt II FRA21 56MW AI Megacampus |
Alexander-von-Humboldt-Straße, 65479 Raunheim, Germany |
Mid-2026 |
Fully Operational / Undergoing Active High-Density Upgrades |
100 MVA Dedicated On-Site Substation via Westnetz |
|
|
Microsoft Azure NRW Germany 300MW AI Megacampus |
Rheinisches Revier Industrial Zone, NRW, Germany |
H2 2027 |
Fully Operational / Newly Launched |
300 MW Dedicated High-Voltage Transmission Substation Connection |
|
|
Digital Realty Lelystad Hyperscale Data Center Campus |
Flevokust Haven Industrial Estate, Lelystad, Netherlands |
Q4 2029 |
Planning / Pre-construction |
150 MW Total Substation Allocation |
|
|
Black Sea AI Gigafactory Campus (500MW Capacity) |
Constanța Logistics Zone, Black Sea Coast, Romania |
Q4 2031 |
Approved / Pre-construction |
500 MW total utility power allocation |
|
|
Google Farciennes AI-Ready Data Center Campus |
Rue de la Neuville 21, 6240 Farciennes, Belgium |
Q4 2029 |
Under Construction |
300 MW total utility power allocation |
|
|
Hscale MXP2 Hyperscale Milan Campus |
Milan Industrial District, Italy |
Q2 2030 |
Under Construction / Development |
120 MW total allocated utility power |
|
|
G2S Bourges Data Center: Tier III Groupama Core Facility |
Rue Denys Dodard, 18000 Bourges, France |
Q2 2015 (Complete operational stabilization) |
Fully Operational |
5 MW total allocated utility grid connection |
|
|
EXA Edge DC Poitiers: High-Availability French Node |
Zone d’Aménagement Concerté de Saint-Eloi, 86021 Poitiers, France |
Q4 2021 (Acquisition and asset integration under the EXA Infrastructure brand) |
Fully Operational |
2.0 MW total dedicated operational utility power |
|
|
SoftBank Northern France AI HyperCampus: 3.1GW Mega Hub |
Port of Dunkirk Western Harbour Zone, Loon-Plage, Hauts-de-France, France |
Q4 2033 (Realization of adjacent advanced electronics and containment assembly facilities) |
Pre-construction / Site Engineering (Announced May 2026) |
1.0 Gigawatt (GW) initial active site substation capability |
|
|
Vantage Dublin DUB1 Campus: 52MW Hyperscale Data Hub |
Profile Park, Clondalkin, Dublin 22, Ireland |
H2 2028 (Final system integration and handover of the second facility block) |
Active Construction Phase |
52 MW dedicated server-ready power deployment |
|
|
Pure DC Amsterdam Westpoort Hyperscale Campus (78 MW) |
Donauweg 12, Westpoort, Amsterdam |
2027 (All 3 towers operational) |
Under Construction |
78 MW Total Site Capacity |
|
|
STT Frankfurt 1 Hyperscale Data Centre Campus (96 MW) |
Business Park, Hanauer Landstraße, Frankfurt am Main |
Late 2028 |
Under Construction |
96 MW Total Scalable Substation Capacity |
|
|
Digital Realty Paris Digital Park Campus (PAR8–PAR11) |
2 Avenue Marcel Cachin, 93120 La Courneuve, Seine-Saint-Denis, France |
Q4 2025 (PAR11 Handover completing full 76 MW campus) |
Operational (PAR8, PAR9, PAR10 Live) / Final Phase Delivery (PAR11) |
85 MW gross utility capacity / 76 MW critical IT load |
|
|
Vantage FRA1 Frankfurt: 56MW German Hyperscale Data Center Campus |
Goethering 27, 63067 Offenbach am Main, Hesse, Germany |
2026–2027 (Completion across all 3 campus buildings) |
Operational / Active Campus Expansion |
56 MW total critical IT capacity |
|
|
Digital Realty FRA11 Frankfurt: 9MW Digital Park Ostend Hub |
Weismüllerstraße 40, 60314 Frankfurt am Main, Germany |
Operational |
Operational |
9.0 MW total critical IT capacity |
|
|
Digital Realty London Docklands: 30MW Financial Interconnection Hub |
1 Muirfield Crescent (Cloud House) & 227 Marsh Wall (Sovereign House), London E14, UK |
Operational |
Operational |
30.0 MW total critical IT load across campus facilities |
|
|
Digital Realty London LHR20 Data Center (Sovereign House) |
227 Marsh Wall, London E14 9SD, United Kingdom |
Operational |
Operational |
4.8 MW – 8.0 MW critical IT load |
|
|
Ada Infrastructure London Docklands: 210MW AI Data Campus |
St. Vincent Ferrer Lane, Silvertown, London E16 2AP, United Kingdom |
Active multi-phase development (Phase 1 delivery 2027) |
Under Construction (Broke ground March 2026) |
210.0 MW total critical IT load (3 x 70 MW buildings) |
|
|
Pure DC Brent Cross LON01 Expansion (LON01B2) |
Harp View, 12 Priestley Way, Brent Cross, London NW2 7AL, United Kingdom |
Q2 2029 (LON01B2 completion / 90 MW campus target) |
Under Construction (Active live campus expansion; West Cold Shell phase awarded) |
90.0 MW campus total IT load (70 MW added via LON01B2) |
|
|
Pure DC Seinäjoki: 550MW Hyperscale Finland AI Campus |
Ämmäläntie & Törnäväntie, Pihlajaniemi, 60200 Seinäjoki, Finland |
Multi-phase 10-year development master plan (550+ MW total capacity) |
Under Construction |
550.0 MW total critical IT capacity (110 MW Phase 1 capacity fully leased) |
|
|
Equinix LD11x Expansion: London Slough Hyperscale xScale Hub |
765/767 Henley Road, Slough Trading Estate, Slough, SL1 4JW, United Kingdom |
Q4 2023 – 2025 (Full 19 MW Capacity Expansion) |
Operational / Fully Energized Phase Expansion |
~24+ MW Utility Capacity / 19 MW Critical IT Load |
|
|
Iron Mountain AMS-1 Data Center Campus Expansion |
J.W. Lucasweg 35, 2031 BE Haarlem, Netherlands (23-acre campus) |
Q2 2027 (+10 MW Expansion Go-Live) / 2028–2030 (Full 43.1 MW Campus Target) |
Operational / Active Multi-Phase Campus Expansion |
43.1 MW Total Utility Capacity (13.1 MW Active / +10 MW Phase 2 / +20 MW Phase 3) |
|
|
Vantage Data Centers Milan: 96MW Italian Hyperscale & AI Infrastructure Hub |
Milan, Metropolitan City of Milan, Lombardy, Italy |
2027–2029 (Full 96 MW regional multi-campus completion) |
Active Operation (MXP1) / Active Expansion Construction (MXP2) |
96 MW Critical IT Power (64 MW MXP1 + 32 MW MXP2) |
|
|
Vantage Data Centers Warsaw WAW1: 48MW CEE Hyperscale Hub |
Zgrupowania AK "Kampinos" 42D, 01-949 Warsaw, Poland (12-acre campus) |
2025–2026 (Building 2 Full Buildout) |
Operational / Active Multi-Building Phase Expansion |
48 MW Critical IT Load (16 MW Building 1 + 32 MW Building 2)48 MW Critical IT Load (16 MW Building 1 + 32 MW Building 2) |
|
|
Digital Realty BER2 Berlin Data Center Campus |
Strategic Industrial Hub, Greater Metropolitan Berlin Area, Germany |
2027 – 2028 |
Under Development / Active Phased Buildout |
32 MW Critical IT Load (Initial Campus Capacity) |
|
|
Digital Realty MAD4 Madrid: 34MW Hyperscale Data Center |
Calle de Alfonso Gómez 4, 28037 Madrid, Spain |
Operational / Phased Expansion 2025–2027 |
Operational / Active Phased Capacity Expansion |
34 MW Critical IT Power Capacity |
|
|
Digital Realty MRS2 Marseille: Mediterranean Subsea & Interconnection Hub |
136 Chemin du Littoral, 13015 Marseille, France (Grand Port Maritime de Marseille) |
Operational / Phased Expansion 2024–2026 |
Operational / Active Multi-Phase Capacity Expansion |
12 MW Critical IT Power Capacity |
|
|
Digital Realty PAR9 Data Center (Paris Digital Park / Interxion PAR9) |
3 Avenue Marcel Cachin, 93120 La Courneuve, France (Paris Digital Park Campus) |
Operational / Continuous Phased Expansion |
Operational / Active Capacity Phasing |
19 MW Critical IT Power Capacity |
|
|
Digital Realty LON2 London: City Campus Financial Interconnection Hub |
11 Hanbury Street (Block C), London E1 6QR, United Kingdom |
Operational |
Operational / Active Multi-Tenant & High-Density Density Upgrades |
16 MW Utility / Substation Power Allocation |
|
|
Digital Realty DUB12 Dublin: 10.3MW Hyperscale & Cloud Hub |
Clonshaugh Industrial Estate, Clonshaugh Crescent, Dublin 17, D17 AW86, Ireland |
Operational / Phased AI & Density Density Optimizations Active |
Operational / Active Multi-Tenant & Cloud Capacity Expansion |
10.3 MW Critical IT Power Capacity / ~12 MW Gross Utility Allocation |
|
|
Digital Realty BRU3 Brussels: Carrier-Neutral Capital Interconnection Hub |
Wezembeekstraat 2, 1930 Zaventem, Greater Brussels Metropolitan Area, Belgium |
Operational / Phased Density and Cooling Upgrades Active |
Operational / Active Multi-Tenant Modernization & Density Upgrades |
1.3 MW Critical IT Power Capacity / 11kV Substation Feed |
|
|
Iron Mountain AMS-2 Amsterdam: 10MW Hyperscale & AI Expansion |
J.W. Lucasweg 35, 2031 BE Haarlem, Netherlands (23-Acre Amsterdam Campus) |
2028–2030 (Full 43.1 MW campus buildout) |
Active Development / Construction Phase |
10 MW Critical IT Power Capacity (AMS-2) / 43.1 MW Total Campus Substation |
|
|
Iron Mountain FRA-2 Frankfurt: 10.6MW Hyperscale & Connectivity Hub |
Am Martinszehnten Industrial Park, 60437 Frankfurt am Main, Germany |
Operational / Active Modernization & AI High-Density Modernization |
Operational / Active Multi-Tenant Capacity Expansion & Upgrades |
10.6 MW Critical IT Power Capacity (FRA-2) / 37.6 MW Combined Campus Total |
|
|
Iron Mountain LON-2 London Slough: 27MW Hyperscale Data Center |
110 Buckingham Avenue, Slough Trading Estate, Slough SL1 4PF, United Kingdom |
Operational |
Operational / Fully Commissioned Wholesale Facility |
27 MW Critical IT Power Capacity / 32+ MW Utility Substation Feed |
|
|
Colt DCS London Hayes Campus Expansion: 160MW Hyperscale & AI Hub |
Hayes Digital Park, London Borough of Hillingdon, West London, United Kingdom |
2029–2032+ (Phased delivery across London 6, 7, and 8) |
Approved / Pre-Construction Phase (Construction Start: 2026) |
97 MW Expansion Capacity / 160 MW Total Campus Capacity |
|
|
Nabiax Alcalá Madrid Campus: 100MW Hyperscale Data Center Expansion |
Av. Punto Com, 23, 28805 Alcalá de Henares, Madrid, Spain |
2026–2029+ (Phased delivery to 100 MW) |
Operational / Active Multi-Phase Hyperscale Expansion |
22.3 MW Operational IT Power / 100 MW Total Campus Power Potential |
|
|
atNorth FIN02 Helsinki Expansion: 45MW High-Density AI & HPC Campus |
Sinimäentie 6, 02630 Espoo, Greater Helsinki Area, Finland |
Q3/Q4 2027 (Completion of 45 MW Expansion Extension) |
Active Construction Phase (5-Story Extension Underway) |
35 MW Critical IT Power Capacity / 45 MW Gross Substation Feed |
|
|
Bulk OS-IX Oslo Internet Exchange: 14MW Carrier-Neutral Data Center |
Hans Møller Gasmanns vei 9, 0594 Oslo, Norway |
Operational / Continuous AI & High-Density Modernization |
Operational / Active High-Density & AI Expansion Phase |
14.4 MW Critical IT Power Capacity |
|
|
NTT DATA FRA5 Frankfurt: 80MW Sovereign AI & Hyperscale Campus |
Greater Frankfurt Metro Corridor / Offenbach East Region, Hesse, Germany |
2027–2029+ (Phased delivery across multi-building expansion blocks) |
Active Construction & Site Development Phase |
80 MW Critical IT Power Capacity |
|
|
Vantage Data Centers WAW2 Warsaw: 48MW Hyperscale & Cloud Hub |
ul. Zgrupowania AK "Kampinos" 42D, 01-949 Warsaw (Bielany District), Poland |
2025–2026 (Completion of Building 2 / WAW2 Expansion) |
Operational (Building 1) / Active Expansion (Building 2 / WAW2) |
48 MW Critical IT Power Capacity |
|
|
Data4 Milan Data Center Campus: 270MW AI Digital Hub |
Cornaredo (MIL01: Via Monzoro, 101-105) & Vittuone (MIL02: Via Giovanni Pascoli), Metropolitan City of Milan, Italy |
2028–2030 (Completion of all 18 Data Center Buildings across MIL01 & MIL02) |
Operational (MIL01 Phase 1–DC09) / Active Construction & Expansion (MIL01 expansion & MIL02) |
170 MW (MIL01 Campus) + 100 MW (MIL02 Campus) = 270 MW Total Capacity |
|
|
CyrusOne FRA5 Frankfurt Hanau Campus: 54MW Hyperscale & AI Hub |
Industrieweg 45, 63451 Hanau, Hesse, Germany (Metropolitan Frankfurt Metro Area) |
2026–2027 (Building 2 & Final AI High-Density Expansion) |
Operational / Active Phased Development & Expansion |
54 MW Total Critical IT Load (27 MW per building) / 90 MVA Grid Capacity |
|
|
Colt DCS Leeds Data Centre Campus: High-Density UK Digital Hub |
Leeds Metropolitan Area, West Yorkshire, United Kingdom |
Targeted 2027–2028 |
Active Development / Planned Regional Expansion |
~20 MW – 40 MW Grid Supply Capacity |
|
|
Echelon DUB20 Arklow Data Center Campus: 100MW Hyperscale Infrastructure Hub Ireland |
Avoca River Park / Vale Road, Arklow, Co. Wicklow, Ireland |
Targeted 2026–2027+ |
Under Construction / Phased Grid Integration & Site Development |
~100 MW – 120 MW Utility Connection Capacity |
|
|
atNorth HEL1 AI Data Center Helsinki Finland: Sustainable High-Density & AI Computing Hub |
Kuortaneenkatu 3, 00510 Helsinki, Finland |
Fully Operational / Ongoing High-Density AI Expansions |
Operational / Upgraded for AI & High-Density Workloads |
~1.5 MW Utility Supply Connection |
|
|
Etix Everywhere Regional Edge Data Center Network: Sovereign French Infrastructure |
Multi-site French Regional Edge Portfolio (e.g., ETIX Paris #3: Vélizy-Villacoublay, Yvelines; ETIX Nantes #1–#3: Chantenay/Saint-Herblain) |
Continuous Expansion & New Edge Acquisitions |
Operational / Active Regional Edge Expansion |
~2.0 MW to 7.0 MW per regional facility module (~20 MW–50 MW network total) |
|
|
KevlinX BRU01 Brussels Data Center Campus: 32MW+ AI-Ready Hub |
Avenue Antoon Van Oss / Av. Antoon Van Oss, 1120 Brussels, Belgium |
2026–2027 (Phased Whitespace Expansion) |
Operational (Live as of Q1 2026) |
~32 MW Critical IT Power (~68 MW Utility Power Capacity) |
|
|
MERLIN Edged LIS2 Lisbon Data Center Campus: 180MW Waterless AI Hub |
Plataforma Logística Lisboa Norte, Freguesia de Castanheira do Ribatejo, Vila Franca de Xira, 111405, Portugal |
2027–2029+ (Phased 5-Facility Expansion) |
Under Construction / Active Phase 1 Buildout |
180 MW Critical IT Power (Expandable to 300 MW) |
|
|
Digital Realty CPH1 Copenhagen Data Center: Ballerup Interconnection Hub |
Industriparken 20A–20C, DK-2750 Ballerup, Copenhagen, Denmark |
Operational Active Campus |
Operational |
~4.2 MW Total Utility Supply Allocation |
|
|
Beyond.pl WRO1 Wrocław Data Center Campus: 150MW AI-Ready Hub |
Strategic Industrial & Tech Corridor, Wrocław, Lower Silesia, Poland |
2027–2029+ |
Under Development / Planned Expansion |
150 MW Total Utility Capacity Allocation |
|
|
Green ZRH1 Zurich West Data Center Campus: High-Density Lupfig Hub |
Industriestrasse 31–33, 5242 Lupfig, Aargau, Switzerland |
Operational Active Expansion |
Operational / Active Expansion (Zurich West 4) |
40 MW+ Total Utility Allocation |
|
|
STACK Infrastructure AMS3 Amsterdam Data Center Campus: Hyperscale AI Hub |
Strategic Hyperscale Corridor, Amsterdam Metropolitan Area, Netherlands |
Phased Multi-Stage Expansion |
Planned / Under Development |
~50 MW – 100 MW Utility Power Allocation |
|
|
Colt LHR2 London West Data Center Campus: 9.4MW Park Royal Hub |
13 Volt Avenue, Park Royal, London NW10 6PW, United Kingdom |
Operational |
Operational |
15.0 MVA Total Utility Supply Provision |
|
|
Data4 Madrid MAD2 Data Center Campus: 80MW AI-Ready Hub |
Polígono Industrial Sur, 28750 San Agustín del Guadalix, Madrid, Spain |
2026–2028+ (Phased Multi-Building Rollout) |
Under Construction / Active Multi-Building Phase Buildout |
80 MW Total Utility Capacity Allocation |
|
|
EcoDataCenter Östersund Data Center Campus: 150MW Sustainable HPC Hub |
Municipality of Östersund, Jämtland County, Sweden |
2026–2028+ (Phased Multi-Building Expansion) |
Under Construction / Phased Campus Buildout |
150 MW Total Utility Capacity Allocation |
|
|
EcoDataCenter Falun Data Center Expansion: 80MW Sustainable AI Hub |
Slaggvarpsvägen 21, 791 77 Falun, Dalarna County, Sweden |
Operational Active Expansion |
Active Multi-Building Expansion / Under Construction |
80 MW Total Secured Utility Power Capacity |
|
|
Green Mountain OSL1 Oslo Data Center Campus: 93MW Sustainable Hub |
Granittveien 100, 1914 Ytre Enebakk, Norway |
Operational Active Expansion |
Operational / Active Expansion |
93 MW Total Utility Supply Allocation |
|
|
Bulk Infrastructure Gothenburg Data Center Campus: Nordic AI Hub |
Strategic Industrial Corridor, Gothenburg, Västra Götaland County, Sweden |
Phased Multi-Building Rollout |
Planned / Under Development |
~50 MW – 80 MW Total Secured Utility Capacity Allocation |
|
|
KevlinX Brussels Data Center Campus: 32MW+ AI-Ready Hub |
Av. Antoon Van Oss 1, 1120 Brussels, Belgium |
Active Multi-Building Campus Expansion |
Operational / Phased Active Expansion |
32 MW – 68 MW Total Utility Power Allocation |
|
|
Echelon DUB20 Data Center Campus: Ireland's 100MW Sustainable Hyperscale Hub |
Avoca River Park, Vale Road, Arklow, Co. Wicklow, Ireland |
Operational Active Campus Expansion |
Operational / Active Expansion Phase |
100 MW Secured Grid Utility Power Allocation |
|
|
Yondr Group Frankfurt Data Center Campus: 40MW Hyperscale Hub |
In der Niederwiese 3, 65474 Bischofsheim, Greater Frankfurt Metropolitan Area, Germany |
July 2025 (Full 40 MW Operational) |
Fully Operational / Active Campus Deployment |
40 MW Total Secured Utility Power Capacity Allocation |
|
|
atNorth DEN01 Copenhagen AI Data Center Campus: 30MW Sustainable HPC Hub in Denmark |
Tonsbakken 12, 2740 Skovlunde / Ballerup, Greater Copenhagen, Denmark |
Operational Active Campus |
Fully Operational / Active HPC & AI Deployment |
30 MW Total Secured Utility Power Capacity Allocation |
|
|
EdgeConneX WAW03 Warsaw Data Center Campus: 12MW Hyperscale & Edge Hub in Poland |
Posag 7 Panien 1, 02-495 Warsaw, Poland |
Operational Active Campus |
Fully Operational / Active Campus Expansion |
12 MW Secured Utility Power Allocation (WAW03 Facility) |
|
|
Green Mountain OML1 Bergen Data Center Campus: Sustainable Hyperscale Hub in Norway |
Hegglandsdalen, Osterøy Municipality, Greater Bergen Area, 5282 Osterøy, Norway |
Active Multi-Building Campus Expansion |
Fully Operational / Active Phased Expansion |
~93 MW Secured Utility Power Allocation |
|
|
Merlin Properties Lisbon AI Data Center Campus: 180MW Sustainable AI Hub |
Castanheira do Ribatejo, Vila Franca de Xira, Greater Lisbon Area, Portugal |
Active Multi-Phase Development |
Under Construction / Active Phase 1 Development |
180 MW Secured Utility Power Allocation (scalable to 300 MW) |
|
|
EcoDataCenter Stockholm Hyperscale Campus: 80MW Sustainable AI Hub in Sweden |
Greater Stockholm Region, Sweden |
Active Multi-Building Campus Development |
Active Development / Phased Buildout |
80 MW Secured Utility Power Allocation |
|
|
Yondr Group LON2 Slough Data Center: 30MW Hyperscale & AI Hub |
Slough Trading Estate Area, Slough, Berkshire, SL1 4DX, United Kingdom |
Active Multi-Phase Development |
Under Development / Active Phased Construction |
30 MW Secured Utility Power Allocation |
|
|
maincubes FRA04 Frankfurt Data Center Campus: 40MW Sustainable AI Hub |
Gulf Data Hub within the KAUST Research and Technology Park 23955 Thuwal Saudi Arabia |
Active Multi-Phase Development |
Under Development / Active Phased Planning |
40 MW Critical IT Load (60 MW Secured Utility Power Allocation) |
|
|
Start Campus SINES DC Portugal: 1.2GW Sustainable AI Data Center |
Zona C1.1, ZILS (Industrial and Logistics Zone of Sines), 7520 Sines, Portugal |
Active Multi-Phase Development through 2030 (1.2 GW total campus capacity) |
Operational (SIN01) & Active Multi-Facility Expansion (SIN02–SIN06) |
1.2 GW Secured Utility Power Allocation |
|
|
Equinix Warsaw Data Center Campus WA4x |
ul. Krakowiaków 91/101, 02-255 Warsaw, Poland (WA4x Hyperscale / Campus Node) |
Active Phased Development |
Operational & Active Multi-Building Expansion |
19.2 MW Secured Utility Power Allocation |
|
|
Equinix Warsaw WA1 Data Center: Premier Connectivity & Peering Hub in Poland |
Aleje Jerozolimskie 65/79, 00-697 Warsaw, Poland (LIM Center Skyscraper) |
Active Operational Facility |
Fully Operational Hub |
3.0 MW Secured Utility Power Allocation |
|
|
Equinix Warsaw WA2 Data Center: Regional Colocation & Cloud Node in Poland |
ul. Poleczki 23, 02-822 Warsaw, Poland |
Operational Active Facility |
Fully Operational Hub |
4.0 MW Secured Utility Power Allocation |
|
|
Equinix Warsaw WA3 Data Center: Sustainable Enterprise & Cloud Hub in Poland |
Aleje Jerozolimskie 213, 02-222 Warsaw, Poland |
Active Operational Facility |
Fully Operational Hub |
4.5 MW Secured Utility Power Allocation |
|
|
ITinSell Cloud La Ciotat Data Center: Tier IV Sovereign & HDS Hub in France |
785 Voie Antiope, Zone d'Activités Athélia III, 13600 La Ciotat, France |
Operational Active Facility |
Fully Operational Sovereign Cloud & Colocation Hub |
~3.5 MW Secured Utility Power Allocation |
|
|
DATA4 Marseille Campus: 120MW Sustainable Hyperscale & AI Hub in France |
Former Normed Shipyards Site, Zone d'Activités, 13600 La Ciotat / Marseille Metro, France |
Active Multi-Phase Development through 2030+ |
Active Development / Under Construction |
120 MW Secured Utility Power Allocation |
|
|
STACK Infrastructure MIL02A Milan Data Center: 5.6MW Colocation Hub |
Via Marche 9, 27010 Siziano (PV), Lombardy, Italy |
Operational Active Building |
Fully Operational Hub |
5.6 MW Secured Critical IT Utility Allocation |
|
|
Mainova WebHouse MWH01 Frankfurt Data Center: 30MW Sustainable Campus |
Gwinnerstraße 7 & Mergenthaler Straße 12, 60388 Frankfurt am Main, Germany |
Operational / Active Expansion Phase (MWH01.2 - 2025) |
Operational (MWH01.1) / Active Expansion (MWH01.2) |
30 MW Secured Utility Power Allocation |
|
|
Kao Data Manchester Campus (KMAN-01): 40MW AI & Hyperscale Hub |
Kenwood Point, Kenwood Road, Reddish, Stockport, SK5 6PH, United Kingdom |
Active Development Campus |
Active Development / Under Construction |
40 MW Secured Critical IT Utility Allocation |
|
|
atNorth NOR01 Data Center Campus: 350MW Sustainable Mega Hub in Haugaland, Norway |
Haugaland Business Park, 5570 Aksdal, Tysvær Municipality, Rogaland, Norway |
Active Multi-Phase Mega Campus Development |
Active Development / Under Construction |
350 MW Secured Critical IT Utility Allocation (Initial 120 MW) |
|
|
Digital Realty PAR3 Data Center Paris: Carrier-Neutral Colocation Hub in Saint-Denis |
7-9 avenue des Arts et Métiers, 93200 Saint-Denis, France |
Fully Operational Active Facility |
Fully Operational Carrier-Neutral Facility |
~10 MW to 14 MW Secured Utility Power Allocation |
|
|
Digital Realty FRA8 Data Center Frankfurt: Carrier-Neutral Hub on Weismüllerstraße |
Weismüllerstraße 36, 60314 Frankfurt am Main, Germany |
Fully Operational Active Facility |
Fully Operational Carrier-Neutral Facility |
~8 MW to 12 MW Secured Utility Power Allocation |
|
|
Hyperco Helsinki Data Center: Sustainable Hyperscale & Enterprise Hub in Finland |
Myllynkivenkuja 4, 01620 Vantaa, Finland |
Fully Operational Active Facility |
Fully Operational Hyperscale Facility |
~20 MW to 50 MW Total Secured Utility Power Capacity |
|
|
Atman Warsaw-1 (WAW-1) Data Center: Carrier-Neutral Hub in Poland |
Grochowska 21a 04-186 Warsaw Poland |
Fully Operational Active 11-Building Campus |
Fully Operational Hyperscale & Enterprise Campus |
57.0 MW Total Allocated Utility Power Capacity |
|
|
Atman Warsaw-2 (WAW-2) Data Center: Carrier-Neutral Hub in Warsaw Business District |
5 Konstruktorska St, 02-673 Warsaw, Poland |
Fully Operational Active Facility |
Fully Operational Enterprise & Interconnection Facility |
16.0 MW Total Utility Power Allocation |
|
|
NDC-GARBE FRA02 Hanau Data Center Frankfurt: Sustainable Cloud & Hyperscale Hub |
Hanau Industrial Zone (Former Civil Defense Storage Site Brownfield Redevelopment), Hesse, Germany |
Fully Operational Active Facility |
Fully Operational Hyperscale Cloud Data Center |
~15.0 MVA Total Utility Power Capacity Allocation |
|
|
Apto DC Madrid Data Center Campus: 240MW Sustainable Hyperscale Hub in Fuenlabrada |
Calle Sauce 20, Fuenlabrada, 28942 Madrid (~14 km from Madrid City Centre), Spain |
Active Multi-Building Campus Development (5 Buildings Total) |
Under Development / Active Construction Phase |
240.0 MW Total Campus Utility Power Capacity Allocation |
|
|
Digital Realty Marseille MRS4 Data Center: 13MW Mediterranean Interconnection Hub |
ancienne base sous-marine, Enceinte Portuaire, Porte 4, 13015 Marseille, France |
Fully Operational Active Facility |
Fully Operational Enterprise & Cloud Hub |
13.0 MW Total Utility Critical IT Power Allocation |
|
|
Pulsant Manchester NW-1 Data Center: Regional Edge Colocation Hub UK |
1-2 Ball Green, Cobra Court, Trafford Park, Stretford, Manchester M32 0QT, United Kingdom |
Fully Operational Active Facility |
Fully Operational Regional Edge Data Center |
~1.6 MW Total Facility Primary Power Connection |
|
|
Conapto Stockholm 1 City Data Center Sweden: 1MW Central Colocation & Recovery Hub |
Sandhamnsgatan 63B, 115 28 Stockholm, Sweden |
Fully Operational Active Facility |
Fully Operational Enterprise & Colocation Facility |
1.0 MW Total Utility Critical Power Allocation |
|
|
Digital Realty CPH3 Data Center Copenhagen: 14MW Hyperscale & Interconnection Hub |
Industriparken 24, DK-2750 Ballerup, Copenhagen, Denmark |
Fully Operational Active Facility |
Fully Operational Hyperscale & Enterprise Facility |
~16.0+ MVA Total Utility Grid Supply Allocation |
|
|
Digital Realty Marseille MRS1 Data Center: 10MW Mediterranean Subsea Interconnection Hub |
40 Avenue Roger Salengro, 13003 Marseille, France |
Fully Operational Active Facility |
Fully Operational Enterprise & Cloud Interconnection Hub |
10.0 MW Total Utility Power Grid Connection Allocation |
|
|
Digital Realty Marseille MRS6 Data Center: 50MW Sovereign Cloud & AI Hub |
Avenue Ferdinand de Lesseps, 13320 Bouc-Bel-Air (Marseille Metro Area), France |
Active Multi-Hall Warehouse Conversion & Campus Development |
Under Development / Planned Greenfield Conversion |
~60.0+ MVA Total Utility Grid Connection Allocation |
|
|
Digital Realty Paris PAR8 Data Center: 19MW Hyperscale & Enterprise Hub France |
2 Avenue Marcel Cachin, 93120 La Courneuve, Paris, France |
Fully Operational Active Facility |
Fully Operational Enterprise & Cloud Facility |
Dual independent high-voltage utility grid feeds, static N+1 uninterruptible power supply (UPS) modules, automated switchgear, and multi-megawatt N+1 standby emergency diesel generator arrays with on-site fuel reserve autonomy. |
|
|
Vantage CWL21 Cardiff Data Center: 28MW Sustainable Hyperscale Hub UK |
Imperial Park, Celtic Way, Marshfield, Newport / Cardiff CF3 0XW, United Kingdom |
Active Greenfield Campus Development |
Active Development / Phased Delivery |
~35.0 MVA Primary Grid Utility Connection Allocation |
|
|
Vantage CWL44 Bridgend Data Center: 20MW Hyperscale & AI Campus South Wales UK |
Bridgend Industrial Estate / Waterton Industrial Estate, Bridgend CF31 3WT, South Wales, United Kingdom |
Active Greenfield Campus Development |
Active Development / Planned Greenfield Campus |
~25.0 MVA Primary Grid Utility Connection Allocation |
|
|
Verne Helsinki Vantaa Data Center: 10MW Sustainable AI & Cloud Hub Finland |
Verne Mittalinja 1 01260 Vantaa Finland |
Fully Operational Active Campus |
Fully Operational Enterprise, Cloud & AI Campus |
~12.0 MVA Total Utility Grid Connection Allocation |
|
|
VIRTUS Cardiff Data Center Campus: Hyperscale & AI Expansion Hub Wales UK |
Cardiff Metropolitan Corridor, South Wales, United Kingdom |
Active Regional Campus Pipeline |
Active Development / Master-Planned Regional Expansion |
Scalable Primary High-Voltage Utility Substation Supply Allocation |
|
|
Serverfarm Amsterdam AMS1 Data Center: 18MW AI-Ready Colocation Hub Netherlands |
Keienbergweg 22, 1101 GB Amsterdam / Archangelkade 1, 1013 BE Amsterdam, Netherlands |
Fully Operational Active Facility |
Fully Operational Enterprise, Cloud & AI Colocation Hub |
30.0 MVA Total Primary Utility Grid Supply Allocation |
|
|
Serverfarm London LON1 Data Center: 11.4MW AI-Ready Colocation Hub Feltham UK |
Unit 4, Westgate Estate, Staines Road, Feltham TW14 8RS, London, United Kingdom |
Fully Operational Active Facility |
Fully Operational Enterprise, Cloud & AI Colocation Hub |
~15.0 MVA Total Primary Grid Utility Connection Power Allocation |
|
|
SoftBank Group Bosquel AI Data Center: 1GW Sovereign Hyperscale Campus Hauts-de-France |
Bosquel, Communauté de Communes Somme Sud-Ouest, Hauts-de-France, France |
Target 2031 (Complete 1 GW Master-Planned AI Factory Delivery) |
Announced / Pre-Development & Site Planning |
~1.2 GVA Dedicated High-Voltage Substation Grid Capacity Allocation |
|
|
SoftBank Group Bouchain AI Data Center: 400MW Repurposed Industrial AI Factory Hauts-de-France |
Former EDF Thermal Power Plant Industrial Brownfield Site, Bouchain, Nord, Hauts-de-France, France |
Target 2031 (Complete 400 MW Industrial Conversion) |
Announced / Preferred Bidder Selected & Active Due Diligence Phase |
~500.0 MVA High-Voltage Grid Substation Capacity Allocation |
|
|
Microsoft Zaragoza Data Center Campus: €6.7B Hyperscale Cloud Hub Aragon Spain |
Rda. Externa Anillar (Z-40) 50007 Zaragoza Spain |
Long-Term Phased Campus Expansion (2026–2034) |
Permitted / Under Construction & Site Preparation |
~350 MVA Grid Capacity Allocation across Planned Substation Additions |
|
|
LEV002 Data Center (AtlasEdge Leverkusen LEV002) |
Dornierstraße 10, 51381 Leverkusen-Quettingen, North Rhine-Westphalia, Germany |
Integrated Operations across Leverkusen Campus (LEV001 + LEV002 = ~14.4 MW total capacity) |
Under Construction / Active Development |
~6.0 MVA Dedicated Utility Grid Substation Allocation |
|
|
Maincubes BER01 Berlin Data Center: Go West Campus Colocation Specs |
Mecklenburgische Straße 32 (Go West Campus), 14197 Berlin, Germany |
Active Commercial Colocation Center |
Operational |
~11.0 MVA Dedicated Utility Grid Substation Allocation |
|
|
TikTok Kouvola Data Center: €1B Project Clover Hyperscale Facility Finland |
Kouvola, Kymenlaakso, Southern Finland |
Multi-Phase Phased Delivery (Complemented by Lahti Data Center Expansion) |
Under Construction / Commissioning Phase |
~60+ MVA Dedicated Substation Grid Service Allocation |
|
|
CloudHQ Lisses CDG Data Center Campus Paris France Specs |
Rue Léonard de Vinci, 91090 Lisses, Île-de-France, France |
Multi-Phase 148.8 MW Master Campus Rollout (CDG1 & CDG2) |
Operational / Multi-Phase Expansion |
~180+ MVA Dedicated Substation Grid Service Allocation |
|
|
Icade Rungis Data Center Paris: Hyperscale Tech Park Development France |
70 Rue des Solets, Parc d'affaires Paris Orly-Rungis, 94150 Rungis, Île-de-France, France |
Multi-Phase Hyperscale Campus Rollout |
Planned / Under Development |
~45+ MVA Dedicated Utility Grid Substation Allocation |
|
|
Campus AI Paris France: €8.5B MGX Bpifrance Mistral AI Megacampus Specs |
Route Départementale 57 (D57), 77390 Fouju, Seine-et-Marne, Île-de-France, France |
Multi-Phase Gigawatt Campus Rollout across Fouju and secondary expansion sites |
Under Development / Early Site Preparation |
~1.6+ GVA Dedicated Substation Grid Service Allocation (Fouju Campus) |
|
|
Colt Berlin Data Center Campus: Enterprise Colocation Germany Specs |
Uhlandstraße 181, 10623 Berlin / Kitzingstraße 15-18, 12277 Berlin, Germany |
Active Commercial Colocation & Network Hub |
Operational / Phased Expansion |
~5.28 MVA Utility Grid Allocation |
|
|
Colt Frankfurt 3 Hyperscale Data Centre: Germany Expansion Specs |
Wilhelm-Fay-Straße, 65936 Frankfurt am Main (Sossenheim), Germany |
Active Multi-Phase Hyperscale Deployment |
Under Construction / Phased Delivery |
~40 MVA Total Utility Grid Provision / 32.4 MW Critical IT Capacity |
|
|
Arcem Joroinen Data Center Campus: Powered Land Development Finland Specs |
Vättiläntie 1227, Huutokoski Industrial Area, 79620 Joroinen, Finland |
Multi-Phase Master-Planned Campus Development |
Planned / Site Origination & Permitting Phase |
~30+ MVA Initial Substation Grid Access (Scalable to match site footprint) |
|
|
DataVita dv2 Data Centre Chapelhall: York Road Edge Hub Scotland Specs |
Unit 1, York Road, Chapelhall Industrial Estate, Chapelhall, Airdrie, ML6 8NW, Scotland, United Kingdom |
Active Commercial Operations & Corporate HQ |
Operational |
~3.5 MVA Utility Substation Allocation |
|
|
IFB Altens Data Centre Aberdeen: Scotland Managed Hosting Specs |
54 Hareness Road, Altens Industrial Estate, Aberdeen, AB12 3LE, Scotland, United Kingdom |
Active Commercial Colocation & Managed Cloud Hub |
Operational |
~1 MVA Utility Substation Connection |
|
|
IFB Union Street Data Centre Aberdeen: Central Scotland Colocation Specs |
387 Union Street, Aberdeen, AB11 6BX, Scotland, United Kingdom |
Active Commercial Colocation & Network Facility |
Operational |
~0.8 MVA Utility Grid Provision |
|
|
Brightsolid Aberdeen Data Centre: Whitemyres Ave Tier III Specs |
Whitemyres Avenue / Lang Stracht, Mastrick, Aberdeen, AB16 6HQ, Scotland, United Kingdom |
Active Commercial Operations & Colocation Hub |
Operational |
~2.5 MVA Utility Grid Allocation / 2.0 MVA Backup Generation |
|
|
Blackdog Data Center Campus Aberdeen: Multi-Gigawatt AI Hub Scotland Specs |
A92 & Aberdeen Western Peripheral Route (AWPR / A90 Junction), AB23 8AR Blackdog, Aberdeenshire, Scotland, United Kingdom |
Multi-Phase Gigawatt Master Campus Rollout |
Proposed / Planning Permission in Principle (Masterplan Entitlements) |
600 MW Initial Substation/Power Allocation (Scalable to Multi-GW) |
|
|
iomart Glasgow Data Centre DC1: Middlesex Street Colocation Specs |
88 Middlesex Street, Kinning Park, Glasgow, G41 1EE, Scotland, United Kingdom |
Operational Colocation & Managed Services Hub |
Operational |
1.0 MVA Total Grid Provisioning |
|
|
Schuberg Philis Boeing Avenue Data Center: Schiphol-Rijk Specs |
Boeing Avenue 271, 1119 PD Schiphol-Rijk, Haarlemmermeer, The Netherlands |
Active Commercial Operations & Sovereign Cloud Center |
Operational |
~4.5 MVA Utility Grid Provision |
|
|
Digital Realty AMS10 Pudongweg Data Center: Schiphol Colocation Specs |
Pudongweg 25, 1437 EM Aalsmeerderbrug (Schiphol-Rijk area), The Netherlands |
Active Commercial Colocation & Interconnection Hub |
Operational |
~31.2 MW Total Utility Power Provision |
|
|
Digital Realty AMS8 Pudongweg Data Center: Schiphol Colocation Specs |
Pudongweg 37, 1437 EM Rozenburg, North Holland, The Netherlands |
Active Commercial Operations & Cloud Campus Facility |
Operational |
~20 MVA Total Utility Substation Capacity |
|
|
nLighten Amsterdam AMS II Data Center: Schiphol-Rijk Specs |
Koolhovenlaan 120, 1119 NR Schiphol-Rijk, Haarlemmermeer, The Netherlands |
Active Commercial Edge Colocation Operations |
Operational |
~5.0 MVA Total Utility Substation Capacity Allocation |
|
|
EdgeConneX Amsterdam EDCAMS05: Schiphol-Rijk Hyperscale Specs |
Boeing Avenue 201-203, 1119 PD Schiphol-Rijk, Haarlemmermeer, The Netherlands |
Active Commercial Operations & Cloud Edge Hub |
Operational |
~25 MVA Dedicated Utility Substation Allocation |
|
|
DayOne Aragon AI Data Center Campus: Technical Specs & Infrastructure |
Ctra. de Quinto de Ebro a Gandesa (A-221), 50790 Escatrón, Zaragoza, Spain |
Operational in phased 50 MW–100 MW high-density modules |
Announced / Under Development |
~300 MW High-Voltage Grid Substation & Direct Generation Capacity |
|
|
Campus Data Navarra: Grupo VDR Data Center Specs |
Polígono de servicios de Gazólaz (Calle A & Calle C), 31190 Gazólaz, Navarra, Spain |
2029 (Buildings 2–4 with 100 MW capacity each) |
Announced / Pre-Construction & Urbanization Phase |
~350 MVA Total Substation Grid Capacity |
|
|
Tillion Aragon Data Center Campus: Technical Specs |
~80-Hectare Master Site, Carretera A-129, 50162 Villamayor de Gállego, Zaragoza, Spain |
2032–2034 (Multi-Phase Rollout to 300 MW Total Scale over 7–8 Years) |
Announced / Pre-Construction Phase (DIGA Approved) |
~350 MVA Total Utility Substation Capacity (150 MW Initial Secured Grid Concession, Expandable to 300 MW) |
|
|
Apto Lacchiarella Data Center Campus: Technical Specs |
Via SP105 / SP40 Junction Area, 20084 Lacchiarella, Metropolitan City of Milan, Italy |
2029–2030 (Multi-Phase Rollout Across All 3 Buildings) |
Announced / Pre-Construction & Permitting Phase |
~220 MVA Dedicated Substation Grid Connection |
|
|
Adriatic DC Bari Data Center: Technical Specs |
Via Francesco de Blasi, Ex-Manifattura Tabacchi Industrial Zone, 70123 Bari, Puglia, Italy |
2030 (Multi-Phase Campus Deployment) |
Announced / Permitting & Site Regeneration Phase |
~250 MVA Dedicated Utility Substation Capacity |
|
|
EDF OpCore Montereau AI Data Center France Hyperscale Campus |
Former Montereau Thermal Power Station Site, Montereau-Fault-Yonne, 77130, France |
Q4 2029 |
Under Construction / Master Development |
200 MW Gross Utility Power Capacity (Campus Limit) |
|
|
Polarise Amberg AI Data Center Bavaria Germany |
Amberg Industrial Park, 92224 Amberg, Bavaria, Germany |
Q2 2028 |
Under Construction |
100 MW Gross Utility Power Capacity |
|
|
Prime Esbjerg ESB01 Data Center Nordre Tovrupvej Denmark Prime Data Centers |
Nordre Tovrupvej, 6705 Esbjerg, Denmark |
Q4 2033 (Full 550MW Campus Buildout) |
Under Development / Planned |
650 MW Gross Utility Power Capacity |
|
|
Île-de-France AI Infrastructure Campus Ardian Verne Paris France |
Greater Paris Metropolitan Area, Île-de-France, France |
Q4 2029 (Full 120MW IT Buildout) |
Under Development / Planned |
150 MW Gross Utility Power Capacity |
|
|
Goodman AMS01 Data Centre (Amsterdam) |
Hybrideweg 101, 2141 DM Vijfhuizen, Netherlands |
Expected 2027–2028 |
Planning & Power Secured / Under Development |
76.0 MW Secured Power Capacity / 48.0 MW Total IT Load Campus Capacity |
|
|
Goodman PAR01A Data Centre 13 Rue Charles Cros Tremblay en France Paris Goodman Group |
13 Rue Charles Cros, 93290 Tremblay-en-France, France |
Q4 2028 |
Under Development / Planning Phase |
48.0 MW Gross Utility Power Allocation / 32.0 MW Total IT Load |
|
|
Goodman PAR01 Data Centre Campus |
13 Rue Charles Cros, 93290 Tremblay-en-France / Paris, France |
Q4 2029 |
Under Development / Planning Phase |
96.0 MW Gross Utility Power Allocation / 64.0 MW Total Campus Critical IT Load |
|
|
Goodman PAR02 Data Centre Campus |
34 Rue Louis Armand, 94190 Villeneuve-Saint-Georges, France |
Q4 2030 |
Under Development / Planning Phase |
108.0 MW Gross Utility Power Allocation / 72.0 MW Total Campus Critical IT Load |
|
|
Nscale Oslo AI Data Center Campus Norway Renewable Hydro Compute Hub |
Hønefoss, Buskerud, Norway |
Q4 2026 |
Operational & High-Density AI Expansion Phase |
25.0 MW Gross Power Allocation / 20.0 MW Critical IT Load |
|
|
atNorth ICE02 Keflavik Mega Data Center Sjónarhóll Reykjanesbær Iceland |
Sjónarhóll 6, 235 Reykjanesbær (Keflavik), Iceland |
Operational / Multi-Phase High-Density Expansion |
Operational & High-Density Expansion Phase |
80.0 MW Gross Power Allocation / 64.0 MW Critical IT Load |
|
|
Microsoft Bornasco Data Center Campus |
Via dei Pioppi & Via Olivetti (ex Via Rimembranze), 27010 Bornasco (PV), Italy |
Early 2029 |
Under Construction Phase (Groundbreaking Q1 2026) |
65.0 MW Gross Power Allocation / 50.0 MW Critical IT Power Load |
|
|
Microsoft Cologne INKA Data Center Campus Bergheim terra nova Industrial Park Germany |
Industrial Park INKA:terra nova, 50126 Bergheim, North Rhine-Westphalia, Germany |
Q4 2029 |
Under Construction Phase (Groundbreaking Q1 2026) |
115.0 MW Gross Power Allocation / 90.0 MW Critical IT Power Load |
|
|
Vantage FRA2 Frankfurt II Data Center Campus – 56 MW IT Load |
Alexander-von-Humboldt-Strasse 4, 65479 Raunheim, Germany |
2025 (56 MW total across 2 buildings) |
Phase 1 Operational / Phase 2 Expansion |
56 MW critical IT load allocation |
|
|
Northern Data European AI Mega Campus Frankfurt – 60 MW HPC |
Main-Biopark Industrial Zone, Frankfurt Metropolitan Area, Germany |
Q2 2026 (Full 60 MW IT load operational) |
Fully Operational / Phased Expansion |
75 MW grid supply allocation |
|
|
CyrusOne FRA4 Frankfurt Data Center Sossenheim – 11 MW |
Wilhelm-Fay-Straße 58, 65936 Frankfurt am Main, Germany |
Q4 2021 (Full 11 MW critical load operational across 4 floors) |
Fully Operational |
15 MW utility grid supply |
|
|
Vantage FRA13 Offenbach Frankfurt Data Center – Hyperscale Campus |
Goethering 27, 63067 Offenbach am Main, Hesse, Germany |
Q4 2024 / Q1 2025 |
Fully Operational / Active Phase |
70 MVA Gross Grid Allocation (56 MW IT Load) |
|
|
STACK Infrastructure STO01 Stockholm Sovereign Data Center – 30 MW |
Smedbyvägen 6, 194 30 Upplands Väsby, Stockholm, Sweden |
2024 / 2025 (Complete 30 MW active across STO01A and STO01B) |
Fully Operational (STO01A) / Expansion Active (STO01B) |
35+ MVA dedicated grid transformation capacity |
|