Portugal’s Start Campus Launches SIN01, Advancing a 1.2GW Gigascale Vision |
Sines, Portugal (Atlantic Coast) |
2030+ |
Operational (First Building, SIN01) |
1.2 GW (Secured Total Grid Capacity) |
|
|
Amazon Web Services (AWS) European Sovereign Cloud Region |
Germany |
Initial launch by late 2026; full investment deployed by 2029 |
Confirmed / Under Construction |
Significant capacity as part of the total €7.8B investment in the region |
|
|
Start Campus - Sines Data Center Campus (SINES01) |
ZILS (Sines Industrial and Logistics Zone), Sines, Portugal |
2028 - 2030 |
Under Construction / Phase 1 Operational |
1.2 GW |
|
|
WBS Power/Prime Capital Hyperscale Campus (Co-located with Project Jupiter) |
Former military airfield, Brandenburg, Germany |
Phased development |
Pre-Construction/Planning (Targeting 2026/2027 Start) |
500 MW |
|
|
DUB20 Hyperscale Campus |
Arklow, County Wicklow, Ireland (Greater Dublin Area) |
Target 2028-2030 |
Under Construction (Initial Phase Piling & Shell) |
90 MW |
|
|
Apto Lacchiarella Data-Center Campus |
Lacchiarella (Milan Metropolitan Area), Italy |
N/A |
Announced / Early Development Phase |
300 MW |
|
|
Global Switch London East (GS2) High-Density Upgrade |
London Docklands (East India Dock), United Kingdom |
Expected completion in the late 2020s. |
Upgrade/Reconfiguration - Underway |
74 MW |
|
|
Echelon Iberdrola Digital Infra - Madrid Sur Campus |
Madrid Sur Area, Spain (South of Madrid) |
N/A (Potential for 700 MW+ across the JV's secured portfolio) |
Planning / Pre-Construction (Secured Power Connection) |
230 MW |
|
|
Microsoft DUB14 Data Center Campus |
Grange Castle Business Park, Clondalkin, Dublin, Ireland |
Projected over 5-7 years |
Under Construction / Phased Buildout |
240 MW |
|
|
CyrusOne FRA7 (Frankfurt Westside) |
Griesheim (West of Frankfurt), Germany |
Expected completion in phases over several years. |
Under Construction |
126 MW |
|
|
SINES 4.0 (Sines Data Center) |
Sines, Portugal (ZILS - Sines Industrial and Logistics Area) |
Estimated by 2030-2035 (phased) |
Under Construction/Ongoing Phased Development |
Up to 1.2 GW |
|
|
Brookfield AI Data Center Campus |
Strängnäs (Stockholm Metro Area), Sweden |
Est. 2035 – 2040 (10-15 year construction timeline) |
Announced / Long-term Development |
Initial planned expansion from 300 MW to 750 MW |
|
|
VIRTUS Wustermark Megacampus |
Wustermark (30 km west of Berlin), Germany |
Est. 2028-2030 |
Under Construction / Phased Development |
Up to 300 MW (Across 9 data center buildings) |
|
|
Microsoft Middenmeer Campus Expansion (AMS13/14) |
Middenmeer, Hollands Kroon (North Holland), Netherlands |
Long-term development |
Announced / Under Phased Construction |
Significant multi-MW capacity added over 50 hectares of new land |
|
|
Fossefall AI Factory & Data Center |
Fyresdal, Vestfold and Telemark County, Norway |
Phased towards 500 MW goal by 2030 across the Nordic region. |
Announced / Acquisition Complete (Late 2025) Commissioning Commissioning Phased conversion, initial AI capacity launch expected H |
Initial 5.5 MW (Existing reserved capacity) |
|
|
Google Data Center Expansion, Saint-Ghislain Campus |
Saint-Ghislain, Hainaut Province, Belgium |
Continuous phased expansion over the next decade. |
Announced / Active Expansion (Investment committed late 2025) |
Significant increase from current load; scaled to support multi-phase gigawatt-scale AI requirements. |
|
|
Amsterdam Hyperscale Campus |
Greater Amsterdam Region, Netherlands |
To be determined (Likely multi-year development) |
Announced / Pre-Construction (Lease Secured) |
Up to €1 Billion in construction investment; Hyperscale scale, multi-megawatt IT load. |
|
|
Colt DCS Frankfurt 4 & 5 Hyperscale Campus |
Rhine-Main Region, Frankfurt, Germany |
TBC |
Announced / Land Secured & Power Contracts Signed |
63 MW (Total IT Load) |
|
|
Vantage Cardiff CWL1 Campus |
Celtic Way, Newport, South Wales, UK |
Estimated completion of all three buildings by 2026-2027 |
Partially Operational / Expanding |
148MW+ (Upgradeable) |
|
|
Equinix Lelystad AI Data Center (AMS10) |
Flevokust Haven, Lelystad, Netherlands |
2030 |
Planning / Pre-Construction |
150 MW Dedicated Site Power |
|
|
IonQ QuantumBasel Tempo Hub |
uptownBasel Campus, Arlesheim/Basel, Switzerland |
2029 |
Active Expansion / Technology Integration |
Scalable Hub (Quantum systems are high-efficiency) |
|
|
Goodman European Data Centre Development Partnership (GEDCDP) |
Frankfurt (Germany), Amsterdam (Netherlands), Paris (France) |
2030 |
Announced / Pre-construction |
435 MW Total Portfolio |
|
|
Digital Realty AMS11 (Amsterdam Data Tower Campus) |
Science Park, Amsterdam, Netherlands |
Q3 2026 |
Live / Operational |
27 MW IT Capacity |
|
|
Sesterce "Rhône-Alps" AI Mega-Campus |
Lyon-Valence Logistics Hub, Auvergne-Rhône-Alpes |
2032 |
Latest Launch (Active Execution Phase - Jan 2026) |
1 GW (Initial Execution) |
|
|
Equinix Hertfordshire Campus (DC01UK) |
Hertfordshire, UK |
2029 |
Under Development / Construction Phase |
250 MW IT Load |
|
|
EdgeMode Villasequilla AI Campus |
Villasequilla, Spain |
2029 |
Approved / Ready-to-Build (RTB) |
600 MW IT Load |
|
|
Digital Realty FRA18: 16MW AI-Ready Heritage Facility |
Frankfurt |
Estimated late 2027 |
Phase 1 Live (Operational) |
16 MW Total |
|
|
DayOne Nurmijärvi: 300MW Renewable AI Campus |
Nurmijärvi, Finland |
2030 |
Phase 1 Groundbreaking / Early Construction |
300 MW (Total Campus Buildout) |
|
|
Mediterra Barcelona: 12MW AI-Ready Edge-Hyperscale Hub |
Strategic site in Catalonia, near Barcelona |
2029 |
Launched / Site Acquired (Feb 20, 2026) |
Secured 12 MW |
|
|
Osae-NFU 250MW AI Data Center Bordeaux France |
Former Industrial Site, Bordeaux Metropole |
2029 |
Groundbreaking (Today) |
250 MW IT Load |
|
|
Digital Realty FRA20: 16MW AI-Ready Hyper-Scale Frankfurt |
Digital Park Fechenheim, Frankfurt |
Estimated 2028–2029 (Total Campus) |
Under Construction (Phase 1 Groundbreaking) |
16 MW (IT Load) |
|
|
Google Skien Norway: 240MW Hyperscale AI-Ready Data Center |
Skådalsvegen, Skien, Telemark, Norway |
2030 (Planned 840 MW) |
Live / Commissioning |
240 MW |
|
|
atNorth SWE04 Sollefteå AI Campus (300 MW) |
Sollefteå (Långsele) |
2031 |
Announced (Feb 24, 2026) |
300 MW Total Utility Capacity |
|
|
AWS Aragon Expansion: 33.7B Euro AI & Cloud Infrastructure |
Zaragoza, Multi-site: Zaragoza, Huesca, and Teruel (Aragon Region) |
2030 |
Announced / Under Expansion |
Total regional capacity projected at 1 GW+ by full buildout |
|
|
DT-NVIDIA AI Factory Munich: €1B 10,000 Blackwell GPU Hub |
Munich (Refurbished Industrial Site) |
2028 |
Go-Live: March 4, 2026 |
10,000 NVIDIA Blackwell GPUs (Initial phase) |
|
|
Google Waltham Cross: $1B AI Data Centre Hertfordshire UK |
, Waltham Cross, Hertfordshire |
2026 |
Operational (Inaugurated Sept 2025) |
Estimated 100 MW Utility Feed |
|
|
Google Dietzenbach: €5.5B AI Data Center & Heat Recovery Germany |
Dietzenbach (near Frankfurt), Hesse |
2029 |
Under Construction / Groundwork (March 2026) |
Part of a regional 4-GW-ready German grid strategy. |
|
|
Project Lusitanus Mérida: €2.8B AI Data Center FRV Spain |
Mérida (Extremadura) |
2029 |
Under Construction / Phase 1 Foundations (March 2026) |
1,000 MW (1 GW) Target |
|
|
Nostrum Evergreen Badajoz: €1.9B 500MW AI Data Center Spain |
Badajoz |
2029 (for 500MW) |
Permitting / Pre-Construction (March 2026) |
500 MW |
|
|
Microsoft Project Raven Italy: €10B 800MW AI Cloud Region |
Lombardy and Lazio, Milan |
2027 |
Operational / Rapid Scaling Phase (March 2026) |
800 MW |
|
|
Microsoft Newport Wales: £2.5B 200MW AI Data Centre |
Newport, Wales |
2028 |
Under Construction / Fit-out (March 2026) |
200 MW |
|
|
Google Winschoten Netherlands: €1.1B AI & Cloud Hub |
Winschoten (Municipality of Oldambt), Groningen |
2026 (Active Scaling) |
Operational (Opened November 18, 2025) |
~200 MW (Phase 1) |
|
|
Nebius Lappeenranta Finland: 310MW Liquid-Cooled AI Factory |
Lappeenranta |
2028 |
Announced / Pre-Construction (March 31, 2026) |
310 MW |
|
|
Stargate Norway Narvik: $1B 520MW AI Gigafactory |
Narvik (Kvandal), Nordland |
2028 |
Under Construction / Initial Phase (April 2026) |
520 MW |
|
|
Digital Realty FRA32 Frankfurt: 9MW AI-Ready Data Center |
Frankfurt am Main |
Operational (Ongoing high-density retrofits) |
Operational / High-Density Upgrade (April 2026) |
9.0 MW |
|
|
Google Azores: 10MW Nuvem & Sol Subsea Cable Landing Hub |
Tecnoparque da Lagoa, São Miguel, Azores |
Q1 2027 |
Under Construction (April 2026) |
10 MW |
|
|
Digital Realty PAR12 Paris: 20MW High-Density AI & Connectivity Hub |
16 Avenue Joseph Froelicher, 77600 Ferrières-en-Brie, France |
Operational |
Operational / High-Density Optimized (April 2026) |
20.0 MW |
|
|
Paris Digital Park: 130MW Hyperscale AI & Cloud Campus |
12-14 Rue de la Gare, 93120 La Courneuve, France |
2026 (Final capacity tranches) |
Operational / Phased Expansion (April 2026) |
130.0 MW |
|
|
Digital Realty MRS5 Marseille: 14MW River-Cooled AI Hub |
Port of Marseille Fos, Marseille, France |
2027 |
Under Construction (April 2026) |
14.0 MW |
|
|
London III Data Center: 56MW West London AI Factory |
Digital Park, Crawley, UK |
2028 |
Under Construction / Phased Expansion (April 2026) |
56.0 MW |
|
|
Prime Finland: €6B Järvenpää AI-Ready 550MW Campus |
Vähänummi Industrial Area, Järvenpää |
2031 |
EIA Phase / Pre-Development (April 2026) |
550 MW |
|
|
Vantage BER1: 56MW AI-Ready Brandenburg Campus |
25-Acre Campus within Brandenburg Park |
2026 |
Operational / Active Phase 2 & 3 Expansion (April 2026) |
56.0 MW |
|
|
Google Kronstorf AI Data Center |
Business Park Kronstorf |
2029 |
Under Construction (Groundbreaking) |
150 MW IT Load |
|
|
Digital Realty ROM1 Rome |
Rome West |
2029 |
Under Construction (Phase 1) |
120 MW Total IT Load |
|
|
Pantheon AI Topusko |
Zagreb |
2032 |
Announced / Permitting |
500 MW IT Load |
|
|
Antimatter Nexus-1 | 100MW Distributed AI Neocloud Launch |
Distributed across Southern France |
2028 (1,000 Units Worldwide) |
Groundbreaking / Launch Phase |
100 MW (First 100 Units) |
|
|
Equinix MD5 Madrid: New Q2 2026 Launch for Southern Europe AI |
Madrid Metropolitan Area |
NA |
In Development / Targeted Q2 2026 Opening |
Multi-MW Scalable |
|
|
Pangea 5: TotalEnergies €100M AI Supercomputer & Heat Recovery |
Technical Center (CSTJF) pau |
2027 |
Project Announced / Design Phase (May 6, 2026) |
Scalable High-Density (HPC Optimized) |
|