Portugal’s Start Campus Launches SIN01, Advancing a 1.2GW Gigascale Vision |
Sines, Portugal (Atlantic Coast) |
2030+ |
Operational (First Building, SIN01) |
1.2 GW (Secured Total Grid Capacity) |
|
|
AWS European Cloud Region for Data Sovereignty |
Germany |
Initial launch by late 2026; full investment deployed by 2029 |
Confirmed / Under Construction |
Significant capacity as part of the total €7.8B investment in the region |
|
|
Start Campus SINES01 | Next-Generation Data Center Campus in Sines, Portugal |
ZILS (Sines Industrial and Logistics Zone), Sines, Portugal |
2028 - 2030 |
Under Construction / Phase 1 Operational |
1.2 GW |
|
|
WBS Power / Prime Capital Hyperscale Campus | Co-Located Project Jupiter AI Hub |
Former military airfield, Brandenburg, Germany |
Phased development |
Pre-Construction/Planning (Targeting 2026/2027 Start) |
500 MW |
|
|
DUB20 Hyperscale Campus |
Arklow, County Wicklow, Ireland (Greater Dublin Area) |
Target 2028-2030 |
Under Construction (Initial Phase Piling & Shell) |
90 MW |
|
|
Apto Data Center Campus in Lacchiarella |
Lacchiarella (Milan Metropolitan Area), Italy |
N/A |
Announced / Early Development Phase |
300 MW |
|
|
Global Switch London East GS2 | High-Density Colocation & Infrastructure Expansion |
London Docklands (East India Dock), United Kingdom |
Expected completion in the late 2020s. |
Upgrade/Reconfiguration - Underway |
74 MW |
|
|
Madrid Sur Campus by Echelon Iberdrola Digital Infra |
Madrid Sur Area, Spain (South of Madrid) |
N/A (Potential for 700 MW+ across the JV's secured portfolio) |
Planning / Pre-Construction (Secured Power Connection) |
230 MW |
|
|
Microsoft DUB14 Dublin Data Center | Next-Gen Hyperscale Compute Campus in Ireland |
Grange Castle Business Park, Clondalkin, Dublin, Ireland |
Projected over 5-7 years |
Under Construction / Phased Buildout |
240 MW |
|
|
CyrusOne FRA7 Frankfurt Westside Campus |
Griesheim (West of Frankfurt), Germany |
Expected completion in phases over several years. |
Under Construction |
126 MW |
|
|
SINES 4.0 | Next-Generation Data Center Campus in Sines, Portugal |
Sines, Portugal (ZILS - Sines Industrial and Logistics Area) |
Estimated by 2030-2035 (phased) |
Under Construction/Ongoing Phased Development |
Up to 1.2 GW |
|
|
Brookfield AI Data Center Campus Development |
Strängnäs (Stockholm Metro Area), Sweden |
Est. 2035 – 2040 (10-15 year construction timeline) |
Announced / Long-term Development |
Initial planned expansion from 300 MW to 750 MW |
|
|
VIRTUS Wustermark Megacampus | Next-Generation Colocation & Digital Infrastructure Campus |
Wustermark (30 km west of Berlin), Germany |
Est. 2028-2030 |
Under Construction / Phased Development |
Up to 300 MW (Across 9 data center buildings) |
|
|
Microsoft Middenmeer Campus | High-Performance AI & Cloud Infrastructure Expansion (AMS13/14) |
Middenmeer, Hollands Kroon (North Holland), Netherlands |
Long-term development |
Announced / Under Phased Construction |
Significant multi-MW capacity added over 50 hectares of new land |
|
|
Fossefall Data Center | AI Factory for Scalable Cloud & GPU Workloads |
Fyresdal, Vestfold and Telemark County, Norway |
Phased towards 500 MW goal by 2030 across the Nordic region. |
Announced / Acquisition Complete (Late 2025) Commissioning Commissioning Phased conversion, initial AI capacity launch expected H |
Initial 5.5 MW (Existing reserved capacity) |
|
|
Google Data Center Expansion, Saint-Ghislain Campus |
Saint-Ghislain, Hainaut Province, Belgium |
Continuous phased expansion over the next decade. |
Announced / Active Expansion (Investment committed late 2025) |
Significant increase from current load; scaled to support multi-phase gigawatt-scale AI requirements. |
|
|
Amsterdam Hyperscale Campus |
Greater Amsterdam Region, Netherlands |
To be determined (Likely multi-year development) |
Announced / Pre-Construction (Lease Secured) |
Up to €1 Billion in construction investment; Hyperscale scale, multi-megawatt IT load. |
|
|
Frankfurt Hyperscale Campus Colt DCS 4 & 5 |
Rhine-Main Region, Frankfurt, Germany |
TBC |
Announced / Land Secured & Power Contracts Signed |
63 MW (Total IT Load) |
|
|
Vantage CWL1 Cardiff | Next-Generation Colocation & Digital Infrastructure Campus |
Celtic Way, Newport, South Wales, UK |
Estimated completion of all three buildings by 2026-2027 |
Partially Operational / Expanding |
148MW+ (Upgradeable) |
|
|
Equinix Lelystad AI Data Center (AMS10) |
Flevokust Haven, Lelystad, Netherlands |
2030 |
Planning / Pre-Construction |
150 MW Dedicated Site Power |
|
|
QuantumBasel Tempo Hub | IonQ Quantum Computing & Data Science Platform |
uptownBasel Campus, Arlesheim/Basel, Switzerland |
2029 |
Active Expansion / Technology Integration |
Scalable Hub (Quantum systems are high-efficiency) |
|
|
Goodman GEDCDP | European Data Centre Development & Investment Partnership |
Frankfurt (Germany), Amsterdam (Netherlands), Paris (France) |
2030 |
Announced / Pre-construction |
435 MW Total Portfolio |
|
|
AMS11 Amsterdam Data Tower Campus by Digital Realty |
Science Park, Amsterdam, Netherlands |
Q3 2026 |
Live / Operational |
27 MW IT Capacity |
|
|
Sesterce "Rhône-Alps" AI Mega-Campus |
Lyon-Valence Logistics Hub, Auvergne-Rhône-Alpes |
2032 |
Latest Launch (Active Execution Phase - Jan 2026) |
1 GW (Initial Execution) |
|
|
Hertfordshire Campus Equinix DC01UK |
Hertfordshire, UK |
2029 |
Under Development / Construction Phase |
250 MW IT Load |
|
|
Villasequilla AI Campus | High-Performance AI Compute & Connectivity Facility |
Villasequilla, Spain |
2029 |
Approved / Ready-to-Build (RTB) |
600 MW IT Load |
|
|
Digital Realty FRA18: 16MW AI-Ready Heritage Facility |
Frankfurt |
Estimated late 2027 |
Phase 1 Live (Operational) |
16 MW Total |
|
|
DayOne Nurmijärvi: 300MW Renewable AI Campus |
Nurmijärvi, Finland |
2030 |
Phase 1 Groundbreaking / Early Construction |
300 MW (Total Campus Buildout) |
|
|
Mediterra Barcelona: 12MW AI-Ready Edge-Hyperscale Hub |
Strategic site in Catalonia, near Barcelona |
2029 |
Launched / Site Acquired (Feb 20, 2026) |
Secured 12 MW |
|
|
Osae-NFU 250MW AI Data Center Bordeaux France |
Former Industrial Site, Bordeaux Metropole |
2029 |
Groundbreaking (Today) |
250 MW IT Load |
|
|
Digital Realty FRA20: 16MW AI-Ready Hyper-Scale Frankfurt |
Digital Park Fechenheim, Frankfurt |
Estimated 2028–2029 (Total Campus) |
Under Construction (Phase 1 Groundbreaking) |
16 MW (IT Load) |
|
|
Google Skien Norway: 240MW Hyperscale AI-Ready Data Center |
Skådalsvegen, Skien, Telemark, Norway |
2030 (Planned 840 MW) |
Live / Commissioning |
240 MW |
|
|
atNorth SWE04 Sollefteå AI Campus (300 MW) |
Sollefteå (Långsele) |
2031 |
Announced (Feb 24, 2026) |
300 MW Total Utility Capacity |
|
|
AWS Aragon Expansion: 33.7B Euro AI & Cloud Infrastructure |
Zaragoza, Multi-site: Zaragoza, Huesca, and Teruel (Aragon Region) |
2030 |
Announced / Under Expansion |
Total regional capacity projected at 1 GW+ by full buildout |
|
|
DT-NVIDIA AI Factory Munich: €1B 10,000 Blackwell GPU Hub |
Munich (Refurbished Industrial Site) |
2028 |
Go-Live: March 4, 2026 |
10,000 NVIDIA Blackwell GPUs (Initial phase) |
|
|
Google Waltham Cross: $1B AI Data Centre Hertfordshire UK |
, Waltham Cross, Hertfordshire |
2026 |
Operational (Inaugurated Sept 2025) |
Estimated 100 MW Utility Feed |
|
|
Google Dietzenbach: €5.5B AI Data Center & Heat Recovery Germany |
Dietzenbach (near Frankfurt), Hesse |
2029 |
Under Construction / Groundwork (March 2026) |
Part of a regional 4-GW-ready German grid strategy. |
|
|
Project Lusitanus Mérida: €2.8B AI Data Center FRV Spain |
Mérida (Extremadura) |
2029 |
Under Construction / Phase 1 Foundations (March 2026) |
1,000 MW (1 GW) Target |
|
|
Nostrum Evergreen Badajoz: €1.9B 500MW AI Data Center Spain |
Badajoz |
2029 (for 500MW) |
Permitting / Pre-Construction (March 2026) |
500 MW |
|
|
Microsoft Italy Project Raven | Next-Gen 800MW AI & Data Center Platform |
Lombardy and Lazio, Milan |
2027 |
Operational / Rapid Scaling Phase (March 2026) |
800 MW |
|
|
Newport Wales Data Centre | Microsoft £2.5B AI-Ready Hyperscale Campus (200MW) |
Newport, Wales |
2028 |
Under Construction / Fit-out (March 2026) |
200 MW |
|
|
Google Netherlands Winschoten | High-Performance AI & Hyperscale Cloud Hub |
Winschoten (Municipality of Oldambt), Groningen |
2026 (Active Scaling) |
Operational (Opened November 18, 2025) |
~200 MW (Phase 1) |
|
|
Lappeenranta AI Factory | Nebius 310MW Hyperscale Liquid-Cooling Infrastructure |
Lappeenranta |
2028 |
Announced / Pre-Construction (March 31, 2026) |
310 MW |
|
|
Stargate Norway Narvik | $1B 520MW AI Gigafactory |
Narvik (Kvandal), Nordland |
2028 |
Under Construction / Initial Phase (April 2026) |
520 MW |
|
|
Digital Realty FRA32 Frankfurt: 9MW AI-Ready Data Center |
Frankfurt am Main |
Operational (Ongoing high-density retrofits) |
Operational / High-Density Upgrade (April 2026) |
9.0 MW |
|
|
Google Azores Nuvem & Sol | 10MW AI-Ready Subsea Connectivity Data Center |
Tecnoparque da Lagoa, São Miguel, Azores |
Q1 2027 |
Under Construction (April 2026) |
10 MW |
|
|
Digital Realty PAR12 Paris AI & Connectivity Hub |
16 Avenue Joseph Froelicher, 77600 Ferrières-en-Brie, France |
Operational |
Operational / High-Density Optimized (April 2026) |
20.0 MW |
|
|
Paris Digital Park | Next-Generation 130MW Hyperscale AI Compute Campus |
12-14 Rue de la Gare, 93120 La Courneuve, France |
2026 (Final capacity tranches) |
Operational / Phased Expansion (April 2026) |
130.0 MW |
|
|
Digital Realty Marseille MRS5 River-Cooled AI Hub |
Port of Marseille Fos, Marseille, France |
2027 |
Under Construction (April 2026) |
14.0 MW |
|
|
London III West London Data Center | 56MW Hyperscale AI & Cloud Infrastructure Hub |
Digital Park, Crawley, UK |
2028 |
Under Construction / Phased Expansion (April 2026) |
56.0 MW |
|
|
Prime Finland: €6B Järvenpää AI-Ready 550MW Campus |
Vähänummi Industrial Area, Järvenpää |
2031 |
EIA Phase / Pre-Development (April 2026) |
550 MW |
|
|
Vantage BER1 Brandenburg | 56MW Hyperscale AI & Cloud Infrastructure Hub |
25-Acre Campus within Brandenburg Park |
2026 |
Operational / Active Phase 2 & 3 Expansion (April 2026) |
56.0 MW |
|
|
Google Kronstorf AI Data Center |
Business Park Kronstorf |
2029 |
Under Construction (Groundbreaking) |
150 MW IT Load |
|
|
Digital Realty ROM1 Rome |
Rome West |
2029 |
Under Construction (Phase 1) |
120 MW Total IT Load |
|
|
Pantheon AI Topusko |
Zagreb |
2032 |
Announced / Permitting |
500 MW IT Load |
|
|
Nexus-1 | 100MW Distributed AI Cloud & High-Performance Compute Hub |
Distributed across Southern France |
2028 (1,000 Units Worldwide) |
Groundbreaking / Launch Phase |
100 MW (First 100 Units) |
|
|
Equinix MD5 Madrid | Next-Gen AI Data Center Launching Q2 2026 in Southern Europe |
Madrid Metropolitan Area |
NA |
In Development / Targeted Q2 2026 Opening |
Multi-MW Scalable |
|
|
Pangea 5 Supercomputer | €100M AI Compute & Sustainable Energy Infrastructure Hub |
Technical Center (CSTJF) pau |
2027 |
Project Announced / Design Phase (May 6, 2026) |
Scalable High-Density (HPC Optimized) |
|
|
TikTok Lahti | €1 Billion AI-Ready Expansion for European Data Sovereignty |
Lahti, Finland |
H2 2027 |
Phase 1 Planning / Tenant Agreement Signed (May 2026) |
128.0 MW (Full Build) |
|
|
Microsoft Centurion Spain: 300MW Aragon Hyperscale AI Region |
Centrovía Industrial Park, La Muela (Zaragoza) |
2029 (Projected) |
Phase 1 Commissioning / Active Buildout |
300 MW (Campus Total) |
|
|
Maincubes BER2: 186MW AI-Ready Hyperscale Campus Berlin |
Luckenwalde, South of Berlin |
Late 2027 |
Under Construction (Phase 2 Groundbreaking May 2026) |
186 MW Total Utility Power |
|
|
Transatlantic Innovation Campus: 500MW AI Hub Croatia |
Dugopolje |
2030 |
Under Construction (Announced May 2026) |
500 MW Total Utility Power |
|
|
Equinix AM11 International Business Exchange™ |
Lemelerbergweg 28, 1101 AH Amsterdam |
2026 / early 2027 |
Operational / Continuous Interconnection Optimization (May 2026) |
9.0 MW |
|
|
Equinix AM5: 13MW High-Density Amsterdam South East Hub |
Amsterdam |
Continuous Expansion / 2026 AI Infrastructure Upgrades |
Live / Operational (Active AI-Ready Upgrades) |
13 MW Total Utility Supply |
|
|
CyrusOne MIL1: 27MW Eco-Sovereign Data Center Milan |
Via delle Regioni, Segrate, Lombardy |
Late 2028 |
Under Construction (Groundbreaking March 25, 2026) |
35 MW Total Utility Connection |
|
|
CyrusOne AMS1: 54MW Hyperscale Amsterdam-Gateway Campus |
Linieweg 1, 1165 AA Halfweg (Haarlemmerliede) |
Ongoing / 2025-2026 |
Live / Operational (Active AI-Density Modernization) |
54 MW IT Load (27 MW Dedicated per Building) |
|
|
NTT Amsterdam 1: 40MW High-Density Network Gateway |
Aviolanda 1, 1437 Rozenburg |
2025–2026 |
Live / Operational (Active AI-Density Modernization) |
40 MW Total White Space Capacity |
|
|
Equinix PA10: 15MW Highly Connected Eco-Hub Paris |
114 Rue Ambroise Croizat, 93200 Saint-Denis |
2025–2026 |
Live / Operational (Active AI Liquid-Cooling Upgrades) |
15 MW Total Utility Connection |
|
|
Digital Realty BCN1: 14MW Mediterranean Interconnection Gateway |
Sant Adrià de Besòs Innovation Area, Barcelona, Catalonia |
May 18, 2026 |
Live / Operational (Launched May 18, 2026) |
14 MW Planned IT White Space Load |
|
|
Project Monet: €2.2B High-Density Hyperscale AI Campus |
Île-de-France Corridor |
Late 2027 |
Approved / Pre-Construction Planning (Siting Finalized May 2026) |
360 MW Maximum Allocated Site Power Envelope |
|
|
Yondr London Slough Building 3: 40MW Hyperscale Data Center |
Slough SL2 5EJ, United Kingdom |
May 2026 (Complete 3-Building Campus Operational) |
Operational / Ready for Service (Achieved May 7, 2026) |
100 MW+ Ultimate Combined Campus Substation Grid Allocation |
|
|
Vantage Cardiff CWL12 |
The Celtic Way Glasgow, UK |
Estimated 2031 |
Planned / Site Infrastructure Under Development |
120 MW maximum expansion capacity |
|
|
Mistral AI EcoDataCenter 150MW Sustainable Sweden AI Campus |
Falun, Sweden |
Estimated 2029 |
Under Construction |
150 MW maximum allocated grid capacity |
|
|
Málaga Digital Gateway 45MW Tier III Andalusian Data Center |
Andalucía Tech Park District, Spain |
Estimated 2030 |
Planning & Site Acquisition Approved |
45 MW gross facility footprint capacity |
|
|
EdgeConneX Italy Hyperscale Expansion |
Milan Technology Hub, Italy |
Comprehensive portfolio development and final phase completions scheduled to scale through 2031 |
Active Development Phase |
300 MW cumulative gross utility power allocation across three core deployment sites |
|
|
Ark Data Centers Barcelona Project Montjuic 45 MW Investment |
La Maquinista, Barcelona, Spain |
Sequential multi-floor modular expansion phases projected to reach full capacity by 2031 |
Active Engineering & Permitting Phase |
45 MW gross electrical capacity delivered via independent high-voltage utility lines |
|
|
Equinix xScale Paris Hyperscale Data Center Expansion (23MW) |
114 Rue Ambroise Croizat, 93200 Saint-Denis |
February 2025 (PA13x fully operational and pre-leased) |
Operational |
23 MW total across primary xScale modules (expandable via future phases) |
|
|
Frankfurt Central IV Hyperscale Data Center 186MW Campus |
Frankfurt, EU |
Q4 2028 |
Under Construction |
186 MW Net IT Capacity |
|
|
Civicos Networking: Roubaix Cloud Node |
1 Rue Kellermann, 59100 Roubaix, France |
Seamlessly integrated into a multi-facility cluster including sister nodes in Tenerife, Lanzarote, and Madrid |
Active / Operational Cloud Services Node |
Up to 1.6 MW total localized operational power threshold, with densities scaling from 1.2 kW up to 10 kW per rack depending on hardware layout |
|
|
EXA Mareuil sur Ay |
Mareuil-sur-Ay (Marne) |
Continuous "build-to-suit" internal data hall adaptations executing based on carrier and enterprise interconnect requirements |
Active / Fully Operational Core Network & Colocation Node |
Scalable multi-megawatt allocation providing high-reliability power feeds to partial, full, and multi-cabinet cage deployments |
|
|
Digital Realty Paris 13: PAR13 Hyperscale |
14 Rue de l'Orme à Moineaux, 91940 Les Ulis, France |
Continuous internal space optimizations and dense cooling retrofits tracking completely active through June 2026 |
Active / Operational |
15 MW gross utility transformer capacity supporting high-density configurations |
|
|
SoftBank Dunkirk AI Campus: 3.1GW Sovereign Mega-Hub |
Port of Dunkirk (Loon-Plage), Hauts-de-France Region, France |
Sequential regional campus completions across Dunkirk, Bosquel, and Bouchain tracking for full delivery by 2031 |
Active / Pre-Construction & Fast-Track Planning Phase (Announced June 2026) |
3,100 MW regional allocation delivered via dedicated on-site 400 kV extra-high-voltage substations |
|
|
Yondr Frankfurt FRA02: 40MW Hyperscale Bischofsheim Node |
Industrial Zone Am Schindberg, 65474 Bischofsheim, Hesse, Germany |
Continuous modular server hall fit-outs pacing sequentially across the multi-story footprint through 2029 |
Active / Under Heavy Structural Construction (Tracking June 2026) |
40 MW gross utility line allocation feeding high-density rows scaling past 25 kW per rack |
|
|
NTT London LON3: 24MW High-Density Dagenham AI Campus |
Yew Tree Ave, Dagenham RM10 7FZ, United Kingdom |
Continuous modular data hall expansion scaling sequentially across the campus footprint through 2029 |
Active / Under Heavy Structural Construction (Tracking June 2026) |
24 MW gross utility capacity delivered via fully redundant, dedicated on-site transformer blocks |
|
|
Data4 Escaudain: €5B 700MW Hyperscale Campus in France |
Former Parc des Soufflantes Industrial Redevelopment Site, Escaudain, Northern France |
2032 - Q4 |
Active / Master Planning & Environmental Site Permitting Phase (Tracking June 2026) |
700 MW gross ultimate site power allocation engineered to sustain high-density AI server clusters and next-generation compute configurations |
|
|
Equinix MD6 Madrid 3.5MW Colocation Campus |
Calle de la Pedriza, 12, 28108 Alcobendas, Madrid, Spain |
Q2 2027 (Final BME Matching Engine Migration) |
Operational |
3.5 MW Marketed Power |
|
|
Milan CyrusOne MIL2 54MW Hyperscale Data Center |
Via Raffaele Rubattino no. 90, 20134, Milan, Italy |
Q4 2028 |
Under Development / Planning |
90 MVA Dual Active High-Voltage Supply Allocation |
|
|
London Kao Data KL03 40MW AI-Ready Data Center |
Park Royal, West London, UK |
Q4 2029 |
Under Development / Planning |
40 MW Dedicated Critical Power Allocation |
|
|
Digital Reef Havering 600MW AI Tech Campus London |
499-Acre Fen Lane & North Ockendon Site, Havering Green Belt Corridor, East London |
Incremental 12-building campus expansions rolling out sequentially across a 5-to-10-year horizon |
Under Construction |
200MW Phase 1 configuration (scalable up to 600MW full site allocation) |
|
|
Google Horndal: New 150MW Air-Cooled Sweden Data Center |
Greenfield industrial zone, Horndal, Avesta Municipality, Dalarna County, Sweden |
Projected 2030 |
Groundbreaking Achieved / Active Civil Construction (June 2, 2026) |
150.0 MW Phase 1 Baseline Capacity |
|
|
Bucharest ClusterPower 800MW Off-Grid AI Infrastructure Factory |
Strada Viitorului nr.2, 207405 Mlecănești, Romania |
Q2 2030 |
Under Construction (Phase 1 Fast-Track) |
800 MW |
|
|
Cambois Northumberland 720MW Massive Hyperscale Campus |
Northumberland , england |
Q4 2031 |
Under Construction (Enabling Works / Phase 1) |
720 MW |
|
|
Solleftea atNorth 300MW High-Density Nordic AI Campus |
SWE04 Industrial Zone, Solleftea, Sweden |
Q4 2029 |
Under Construction (Phase 1 Framing) |
300 MW |
|
|
Paris Verne 500MW Sovereign AI High Performance Campus |
36-43 Great Sutton St, London EC1V 0AB, United Kingdom |
Q4 2030 |
Under Construction (Phase 1 Groundwork) |
500 MW |
|
|
Project Boreas: 800MW Nordic Hyperscale Campus |
Northern Sweden (Nordic Region) |
2031 |
Groundbroken / Under Construction |
800 MW dedicated capacity |
|
|
Granada: €3B Alto Infrastructure SP01 AI & HPC Campus Spain |
Escúzar, Granada (Andalusia) |
2029 |
Groundbreaking Initiated |
70 MW total master-planned power footprint (50 MW dedicated IT load) |
|
|
Philippsburg: 707MW Project Engrida Hyperscale Data Center Campus Germany |
Former Goodyear Tire Factory & Decommissioned Philippsburg Nuclear Power Plant (KKP Site) |
2032+ |
Pre-Construction / Municipal Council Preliminary Approval Received |
707 MW total grid capacity allocation (Supporting an estimated ~550 MW of continuous critical IT infrastructure) |
|